Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


define the zero date in project management

Answers were Sorted based on User's Feedback



define the zero date in project management..

Answer / parish

the project start date after complete approval from
technical ,financial and regilatory agency.This is called
zero date of project.

Is This Answer Correct ?    43 Yes 10 No

define the zero date in project management..

Answer / satish

The zero date of a project signals the effective start of
the project. It is an important part of the project planning
and establishment. The completion of projection will be
counted from this point of time. It is important to ensure
that all activities that effect project performance like
arrangement of finance, infrastructure facilities, formation
of new company, division, government and clearance etc.
beside time, cost and technical parameters are fully dealt
/designed / established / started by this time.

Is This Answer Correct ?    30 Yes 5 No

define the zero date in project management..

Answer / ashok

Zero date is the effective start date of the project. Usually it is the date of LOI / Contract signing date. Duration of the project is calculated on basis of this date.

Is This Answer Correct ?    9 Yes 3 No

define the zero date in project management..

Answer / abdulrahman

Zero date is milestone.

Is This Answer Correct ?    13 Yes 9 No

define the zero date in project management..

Answer / chellaiah

Zero date is the project start date.

Is This Answer Correct ?    5 Yes 5 No

define the zero date in project management..

Answer / a.barakat

zero date : is the identified date for the start of the project

Is This Answer Correct ?    1 Yes 1 No

define the zero date in project management..

Answer / sarat

In a Power Plant Project, the date on which a contract document is signed with the EPC contractor for BTG Package is considered as a Zero Date

Is This Answer Correct ?    2 Yes 2 No

define the zero date in project management..

Answer / anoop kumar

If the activity of the project is not on the critical path.
The activity is called as zero date. WHich actually means
no schedule and effort varince in to the project.

Is This Answer Correct ?    21 Yes 35 No

Post New Answer

More Project Management Interview Questions

How do you handle conflicts in the Team Management ?

0 Answers   Microsoft,


Sally is a project manager working on the Resource Planning process. She should consider all of the following when developing the resource requirements output except: A. WBS B. Supply purchase policies C. Resource rates D. Special knowledge and talents

0 Answers  


Explain the difference between risk and issues?

0 Answers  


Brainstorming and the Delphi technique are two types of information-gathering techniques found in which process? A. Risk Management Planning B. Risk Response Control C. Risk Identification D. Quantitative Risk Analysis

0 Answers  


Each of the following is true regarding the risk management plan except: A. The risk management plan is an output of the Risk Management Planning process B. The risk management plan includes a description of the responses to risks and triggers. C. The risk management plan includes thresholds, scoring and interpretation methods, responsible parties, and budgets. D. The risk management plan is an input to all the remaining risk planning processes.

0 Answers  


You are a project manager for a new software development project. You have a few activities that require specialized testing. The testing might need to be repeated more than once. Which of the following do you choose? A. The Graphical Evaluation and Review Technique because it allows for conditional branching and looping for the testing activity B. The Critical Path Method because it allows for float time to be calculated for the testing activity C. The Program Evaluation and Review Technique because it allows for conditional branching and looping for the testing activity D. The Program Evaluation and Review Technique because it allows for a weighted average distribution, which will even out the time needed for the testing activity

0 Answers  


You are project manager for a nonprofit organization. Your project has come about due to a social need. Your sponsor wants to get right to the Planning process. However, you know that a project charter should be published prior to proceeding to the Planning processes. All of the following are true regarding project charters except: A. Project charters always include cost and time estimates. B. Project charters always include the product description and business need for the product. C. Project charters recognize and acknowledge the existence of the project. D. Project charters commit organizational resources to the project.

0 Answers  


What are the skills required to be a project manager? Followup question, Rate yourself in each of the skill with examples.

18 Answers   Cognizant, Microsoft,


Explain the difference between Project management and IT management.

0 Answers   TCS,


how to handle project single handed?and what are the roles and responsibilities of a project leader?

4 Answers   Areva,


You are the project manager for a construction company that is building a new city and county office building in your city. You recently looked over the construction site to determine if the work to date was conforming to the requirements and quality standards. Which tool and technique of Quality Control are you using? A. Performance measurements B. Inspection C. Sampling D. Prevention

0 Answers  


As a PMP, you will be required to comply with the Project Management Professional Code of Professional Conduct. This code refers to all of the following except: A. Reporting conflicts of interest B. Reporting experience and PMP status truthfully C. Complying with stakeholder requirements D. Complying with rules and policies of foreign countries

0 Answers  


Categories