define the zero date in project management

Answers were Sorted based on User's Feedback



define the zero date in project management..

Answer / parish

the project start date after complete approval from
technical ,financial and regilatory agency.This is called
zero date of project.

Is This Answer Correct ?    43 Yes 10 No

define the zero date in project management..

Answer / satish

The zero date of a project signals the effective start of
the project. It is an important part of the project planning
and establishment. The completion of projection will be
counted from this point of time. It is important to ensure
that all activities that effect project performance like
arrangement of finance, infrastructure facilities, formation
of new company, division, government and clearance etc.
beside time, cost and technical parameters are fully dealt
/designed / established / started by this time.

Is This Answer Correct ?    30 Yes 5 No

define the zero date in project management..

Answer / ashok

Zero date is the effective start date of the project. Usually it is the date of LOI / Contract signing date. Duration of the project is calculated on basis of this date.

Is This Answer Correct ?    9 Yes 3 No

define the zero date in project management..

Answer / abdulrahman

Zero date is milestone.

Is This Answer Correct ?    13 Yes 9 No

define the zero date in project management..

Answer / chellaiah

Zero date is the project start date.

Is This Answer Correct ?    5 Yes 5 No

define the zero date in project management..

Answer / a.barakat

zero date : is the identified date for the start of the project

Is This Answer Correct ?    1 Yes 1 No

define the zero date in project management..

Answer / sarat

In a Power Plant Project, the date on which a contract document is signed with the EPC contractor for BTG Package is considered as a Zero Date

Is This Answer Correct ?    2 Yes 2 No

define the zero date in project management..

Answer / anoop kumar

If the activity of the project is not on the critical path.
The activity is called as zero date. WHich actually means
no schedule and effort varince in to the project.

Is This Answer Correct ?    21 Yes 35 No

Post New Answer

More Project Management Interview Questions

Which of the following is constraint chat you might find during the Organizational Planning process? A. Organizational structure, expected staff assignments, collective bargaining agreements, and project management team preferences B. Organizational structure, organizational interfaces, technical interfaces, and interpersonal interfaces C. Organizational interfaces, expected staff assignments, collective bargaining agreements, and project management team preferences D. Organizational interfaces, technical interfaces, and interpersonal interfaces

0 Answers  


You are a project manager for Penguin Software. Your company creates custom software programs for hospitals and large dental offices. You have just completed a project and are gathering the documentation of the product of the project. This might include all of the following except: A. Technical specifications B. Electronic files C. Programming plans D. Performance measurements

0 Answers  


You are a project manager for Swirling Seas Cruises food division. You're considering two different projects regarding food services on the cruise lines. The initial cost of Project Fish'n for Chips will be $800,000 with expected cash inflows of $300,000 per quarter. Project Picnic's payback period is six months. Which project should you recommend? A. Project Fish'n for Chips because its payback period is two months shorter than Project Picnic’s B. Project Fish'n for Chips because the costs on Project Picnic are unknown C. Project Picnic because Project Fish'n for Chips' payback period is four months longer than Project Picnic’s D. Project Picnic because Project Fish'n for Chips' payback period is two months longer than Project Picnic's

0 Answers  


You are implementing a sap project. implementation compled and development started and at that time you found that there is major problem with the system .It would take again time and customer is not happy with that ,in that case how do you convince customer?

2 Answers   Siemens,


Your selection committee is debating between two projects. Project A has a payback period of 18 months. Project B has a cost of $125,000 with expected cash inflows of $50,000 the first year and $25,000 per quarter after that. Which project should you recommend? A. Either Project A or Project B because the payback periods are equal B. Project A because Project B's payback period is 21 months C. Project A because Project B's payback period is 24 months D. Project A because Project B's payback period is 20 months

0 Answers  






You are a project manager for a network cabling project for your organization. Your project team is made up of six full-time employees and three contractors. This is the first time they have all worked together. You know that the team will go through the stages of team development in the following order: A. Forming, storming, norming, and performing B. Storming, norming, forming, and performing C. Norming, storming, forming, and performing D. Forming, norming, storming, performing

0 Answers  


Information-gathering techniques used in the Risk Identification process include all of the following except: A. Brainstorming B. Delphi technique C. Interviewing D. Kaizen technique

0 Answers  


You are ready to perform the Activity Sequencing process for your project. To make your job easier, you're going to use a software tool to help you draw a PDM network diagram. Most software programs use this technique. You know all of the following are true regarding the PDM except: A. It shows the activities on arrows and connects them to dependencies usually depicted as circles. B. It’s also called AON. C. It shows the activities in boxes with arrows connecting the dependent activities. D. It uses four types of dependency relationships of which finish to start is one.

0 Answers  


Which of the following are the outputs of the Contract Closeout process? A. Project archives, formal acceptance and closure, contract file B. Contract file, formal acceptance and closure C. Project archives, contract file D. Contract file, formal acceptance and closure, lessons learned

0 Answers  


You are a project manager with several years of experience in project management. You’ve just accepted your first project in a foreign country. You've been in the country a week or two and are experiencing some disoriented feelings. This is known as: A. Collocation B. Diversity shock C. Global culturing D. Culture shock

0 Answers  


You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. You do not expect these variances to continue, as they're atypical. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 25 B. 760 C. 775 D. 833

0 Answers  


You are a project manager in the manufacturing industry. You are using sample variance measurements to monitor the results of the process over time. Which tool and technique of Quality Control are you using? A. Statistical sampling B. Scatter diagrams C. Control charts D. Pareto diagrams

0 Answers  


Categories