What is "Readjustig goal and Milestone" in project
managment and project planing

Answers were Sorted based on User's Feedback



What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / tushar waghode

Re-adjusting goals can be viewed as a part of change
management where impact of changes result in change of
scope of the deliverables or project.
Milestone is used as a checkpoint at logical points in a
schedule to ascertain completeness of work at that point.
In Microsoft project a milestone is a zero duration, zero
resource intentive activity.

Is This Answer Correct ?    25 Yes 2 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / rashmi ranjan sinha

Milestone: Date by which major activities are performed.
Readjusting: If the milestone seems not to be achieved as
targeted or incur a risk, it should be readjusted setting
goals with different approach.

Is This Answer Correct ?    17 Yes 5 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / manzoor

The recognition of an important event within the project,
usually the achievement of a key project deliverable

Is This Answer Correct ?    9 Yes 3 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / san

milestone is a point were we can check our process
achivements steps and if are not in proper way throu we
must here come readjusting goal. every team always go to
this process planing->devlopment->testing in time sedule.
if it not happen goto Readjustig goal same work in diffrent
way

Is This Answer Correct ?    12 Yes 8 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / a dilipkumar

Ideally both Goals and Milestones(completion/sign-off of a
major activity or deliverable) are fixed at the beginning
of the Project Planning Phase based on the Project Charter.
However, during certain cases, during the course of the
project, the goals and/or milestones becomes irrelevant to
the changed business context. Hence, instead of pursuing
the earlier establised goal, with the apporval of the
Project Sponsor (who had approved the Project charter), the
goals and subsequently the milestones to achieve the
revised goals can be planned and changed to reflect the
revised business requirement.

Is This Answer Correct ?    4 Yes 2 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / saravanan

In addition to above mentioned points, During Project
development process, whenever there is a requirement
change / requirement correction happens. PM will need to re-
adjust the goal and milestone.

Is This Answer Correct ?    6 Yes 6 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / indranil bhattacharya

"Readjustig goal and Milestone" is a common technique used
in large projects. Here depending upon the requirement we
need to change the Scope of the project resulting the
deliverable vs. time table. Here always we need to keep in
mind about the BAC (budget at completion) of the project.

Is This Answer Correct ?    3 Yes 3 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / cristina giese

Readjust goals and milestones can be shares resulting from process of change management, where a scope change was requested and approved and will be implemented.
This action affects the entire project planning because it is necessary to revise the scope, cost estimating, the schedule and project risks. Just as the baseline.

Is This Answer Correct ?    0 Yes 0 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / surender yadav

The Partial blocks of achievement is a milestone.
Particulary for projects more than of 6 months period If
percieved due to constraint -Technology Change , fresh
demand from customer(changing the SOW),products becoming
obsolete there can be mutual negotitation to change the
milestone dates (some times penalty may be leivied) and the
goal.

Is This Answer Correct ?    2 Yes 3 No

What is "Readjustig goal and Milestone" in project managment and project planing..

Answer / amarnath

It is a process which must be carried out during the
project Management or to be planned during the project
planning stage to list the actions to be taken in case of
any requirement changes arises. This term is used while
communicating with the stakeholders. For example, “If there
are any changes in the system requirements we need to
Readjust the goal and milestones” and if the stakeholders
ask, we should be able to list the planed steps for the
process, which depends on the project in hand.

Is This Answer Correct ?    1 Yes 2 No

Post New Answer

More Project Management Interview Questions

You are a contract project manager for a wholesale flower distribution company. Your project is to develop a website for the company that allows retailers to place their flower orders online. You will also provide a separate link for individual purchases that are ordered. This project involves coordinating the parent company, growers, and distributors. You are preparing a performance review and have the following measurements at hand: PV = 300; AC = 200; and EV = 250. What is the CPI of this project? A. 0.80 B. 1.25 C. 1.5 D. 0.83

0 Answers  


Each of the following is true regarding the risk management plan except: A. The risk management plan is an output of the Risk Management Planning process B. The risk management plan includes a description of the responses to risks and triggers. C. The risk management plan includes thresholds, scoring and interpretation methods, responsible parties, and budgets. D. The risk management plan is an input to all the remaining risk planning processes.

0 Answers  


Your company has asked you to be the project manager for the product introduction of their new DeskTop Rock media system. You recently published the scope statement and the supporting detail. The supporting detail contains all of the following except: A. Constraints B. Other project information not noted in the scope statement C. Code of accounts D. Assumptions

0 Answers  


You are a project manager working on contract. You’ve performed earned value analysis and discovered that the project will be completed on time and under the original estimated amount. This means the profit to your company will decrease as will your personal bonus. Which of the following should you do? A. Add activities to the project to increase the cost enough to meet the original estimated amount. B. Tell the customer you're adding additional requirements to the project chat were originally cut because of cost constraints. C. Inform the customer that the project is completed and has come in under budget. D. Bill the customer for the full amount of the contract as this was the original agreed-upon price.

0 Answers  


What is one of the problems with project management software? A. The project manager manages the software instead of the project B. Project duration calculations are sometimes approximate. C. You cannot override the project management software decisions regarding schedules. D. It’s expensive and difficult to use.

0 Answers  






Explain on the project management life cycle process?

0 Answers  


You are a project manager for Star Light Strings. Star Light manufactures strings of lights for outdoor display. Their products range from simple light strings to elaborate lights with animal designs, bug designs, memorabilia, and so on. Your newest project requires a scope change. You have documented the characteristics of the product and its functionality using which of the following tools and techniques? A. Change control system B. Corrective action C. Configuration management D. Updates to the scope management plan

0 Answers  


During contract negotiations, your vendor tells you that the equipment originally bid in the RFP is no longer available. They say the best solution is to buy the new equipment they're offering, which is a higher price than the original equipment. You have concerns that the new equipment might not be compatible with existing equipment and try to discuss this with them. They remind you that this decision was already made during the last contract negotiation meeting so there's no need to continue to discuss it. This is an example of which of the following? A. Proposal B. Compromise C. Storming D. Fair accomplish

0 Answers  


What is the process in the Executing process group that determines if the project satisfies quality standards, identifies lessons learned, and review quality management activities to verify the correct quality elements are being examined? A. Quality Control B. Quality Monitoring and Control C. Quality Assurance D. Scope Verification

0 Answers  


Many times software delivery is late, why? Give reason.

0 Answers  


As a PMP, you will be required to comply with the Project Management Professional Code of Professional Conduct. Part of your responsibility concerns applying professional knowledge. All of the following are part of applying professional knowledge except: A. Developing relationships based on mutual respect B. Staying abreast of project management practices C. Keeping up with industry trends and new technology D. Honestly reporting your project management experience

0 Answers  


You are working on a project that will upgrade the phone system in your customer service center. You have used bottom-up estimating techniques to assign costs to the project activities and have determined the cost baseline. Which of the following is true? A. You have completed the Cost Estimating process and now need to complete the Cost Budgeting process to determine the project's baseline. B. You have completed the Project Plan Development process and established a project baseline to measure future project performance against. C. You have completed the Cost Estimating process and now need to complete the Project Plan Development process to establish a project baseline to measure future project performance against. D. You have completed the Cost Budgeting process, and the cost baseline will be used to measure future project performance.

0 Answers  


Categories