What is "Readjustig goal and Milestone" in project
managment and project planing
Answers were Sorted based on User's Feedback
Answer / tushar waghode
Re-adjusting goals can be viewed as a part of change
management where impact of changes result in change of
scope of the deliverables or project.
Milestone is used as a checkpoint at logical points in a
schedule to ascertain completeness of work at that point.
In Microsoft project a milestone is a zero duration, zero
resource intentive activity.
| Is This Answer Correct ? | 25 Yes | 2 No |
Answer / rashmi ranjan sinha
Milestone: Date by which major activities are performed.
Readjusting: If the milestone seems not to be achieved as
targeted or incur a risk, it should be readjusted setting
goals with different approach.
| Is This Answer Correct ? | 17 Yes | 5 No |
Answer / manzoor
The recognition of an important event within the project,
usually the achievement of a key project deliverable
| Is This Answer Correct ? | 9 Yes | 3 No |
Answer / san
milestone is a point were we can check our process
achivements steps and if are not in proper way throu we
must here come readjusting goal. every team always go to
this process planing->devlopment->testing in time sedule.
if it not happen goto Readjustig goal same work in diffrent
way
| Is This Answer Correct ? | 12 Yes | 8 No |
Answer / a dilipkumar
Ideally both Goals and Milestones(completion/sign-off of a
major activity or deliverable) are fixed at the beginning
of the Project Planning Phase based on the Project Charter.
However, during certain cases, during the course of the
project, the goals and/or milestones becomes irrelevant to
the changed business context. Hence, instead of pursuing
the earlier establised goal, with the apporval of the
Project Sponsor (who had approved the Project charter), the
goals and subsequently the milestones to achieve the
revised goals can be planned and changed to reflect the
revised business requirement.
| Is This Answer Correct ? | 4 Yes | 2 No |
Answer / saravanan
In addition to above mentioned points, During Project
development process, whenever there is a requirement
change / requirement correction happens. PM will need to re-
adjust the goal and milestone.
| Is This Answer Correct ? | 6 Yes | 6 No |
Answer / indranil bhattacharya
"Readjustig goal and Milestone" is a common technique used
in large projects. Here depending upon the requirement we
need to change the Scope of the project resulting the
deliverable vs. time table. Here always we need to keep in
mind about the BAC (budget at completion) of the project.
| Is This Answer Correct ? | 3 Yes | 3 No |
Answer / cristina giese
Readjust goals and milestones can be shares resulting from process of change management, where a scope change was requested and approved and will be implemented.
This action affects the entire project planning because it is necessary to revise the scope, cost estimating, the schedule and project risks. Just as the baseline.
| Is This Answer Correct ? | 0 Yes | 0 No |
Answer / surender yadav
The Partial blocks of achievement is a milestone.
Particulary for projects more than of 6 months period If
percieved due to constraint -Technology Change , fresh
demand from customer(changing the SOW),products becoming
obsolete there can be mutual negotitation to change the
milestone dates (some times penalty may be leivied) and the
goal.
| Is This Answer Correct ? | 2 Yes | 3 No |
Answer / amarnath
It is a process which must be carried out during the
project Management or to be planned during the project
planning stage to list the actions to be taken in case of
any requirement changes arises. This term is used while
communicating with the stakeholders. For example, “If there
are any changes in the system requirements we need to
Readjust the goal and milestones” and if the stakeholders
ask, we should be able to list the planed steps for the
process, which depends on the project in hand.
| Is This Answer Correct ? | 1 Yes | 2 No |
Suppose you did all your work in a 32 bit system, the production server is 64 bit system, you find that during UAT, the system fails and is not working, how will u communicate to your customer, what solution will you provide to the client?
Which of the following is true regarding the critical path? A. It should never be compressed. B. It allows for looping and branching. C. The critical path technique is the same as PERT. D. It's the duration of all tasks with zero float.
Your project was just completed, accepted, and closed. As is customary for your organization, you conduct a post-implementation audit. The purpose of this audit includes all of the following except: A. Evaluating project goals and comparing them to project product B. Reviewing successes and failures C. Documenting the acceptance of the work results D. Documenting possible improvements for future projects
You have been hired as a contract project manger for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. One of the activities for this project is the installation and testing of several new servers. You know from past experience it takes about 16 hours per server to accomplish this task. Since you're installing 10 new servers, you estimate this activity to take 160 hours. Which of the estimating techniques have you used? A. Analogous estimating B. Bottom-up estimating C. Quantitatively based duration D. Reserve time
Your project involves the research and development of a new food additive. You’re ready to release the product to your customer when you discover that a minor reaction might occur in people with certain conditions. The reactions to date have been very minor, and no known long-lasting side effects have been noted. As project manager you should: A. Do nothing because the reactions are so minor that very few people will be affected. B. Inform the customer that you've discovered this condition and tell them you'll research it further to determine the impacts. C. Inform your customer that there is no problem with the additive release the product to them. D. Tell the customer you'll correct the reaction problems in the next batch but you'll release the first batch of product to them now to begin using.
Theory Y managers believe which of the following? A. That people are motivated only by money, power, or position B. That people will perform their best if they're given proper motivation and expectations C. That people are motivated to achieve a high level of competency D. That people are motivated by expectation of good outcomes
You are the project manager for Zippy Tees. Your company has decided to outsource the manufacturing of miniature bears to be attached to your trendy T-shirts. Which of the following is true? A. A good product description is all that's required. The project manager will supply this to the vendor. B. The contract can serve as the project charter. The product description will be included in the contract. C. The project manager should write the project charter because the project manager will be managing the vendor portion of this project as well. D. The vendor should write the project charter as they are responsible for manufacturing the bears.
All of the following are characteristics of the project Closing processes except: A. Probability for success is greatest here. B. The project manager's influence is greatest here. C. The stakeholders' influence is least here. D. Risk is greatest here.
Your selection committee meets on a semiannual basis. They've determined that projects must meet or exceed a specific profit limit in order to be accepted and prioritized on the project list. Which of the following is true? A. The selection committee has defined project selection criteria, which is a tool and technique of Initiation. B. The selection committee has defined project selection methods, which is a tool and technique of Initiation. C. The selection committee has defined project selection methods, which is an input to Initiation. D. The selection committee has defined project selection criteria, which is an input to Initiation.
During a recent team meeting, you reached a resolution to a problem that's been troubling the team for several weeks. You took responsibility for searching out the facts of this problem and uncovered the right answer to this problem. You presented the facts at the project status meeting, and everyone reached agreement on the recommended solution based on the facts you presented. This is an example of what type of conflict resolution technique? A. Compromise B. Smoothing C. Confrontation D. Forcing
The Project which is handled by you is in RED, customer has given you 4 weeks to show improvement, still nothing has worked out. The Customer again gives 3 weeks to improve and you do your best to improve, but nothing works out. Now the customer is not at all happy, HOW TO CONVINCE THIS CUSTOMER ???
8 Answers AZS, BGR Energy, Wipro,
Three people are responsible for establishing cost of quality theories. Crosby and Juran are two of them, and their theories respectively are: A. Grades of quality, fitness for use B. Fitness for use, zero defects C. Zero defects, fitness for use D. Cost of quality, zero defects