What is "Readjustig goal and Milestone" in project
managment and project planing

Answer Posted / tushar waghode

Re-adjusting goals can be viewed as a part of change
management where impact of changes result in change of
scope of the deliverables or project.
Milestone is used as a checkpoint at logical points in a
schedule to ascertain completeness of work at that point.
In Microsoft project a milestone is a zero duration, zero
resource intentive activity.

Is This Answer Correct ?    25 Yes 2 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

People are motivated by the need for achievement, power, or affiliation according to which theory? A. Expectancy theory B. Achievement theory C. Contingency theory D. Theory X

526


How do you motivate team members?

519


You are the project manager for Design Your Web Site, Inc. Your company is designing the website for a national grocery store chain. You have your activity list in hand and several time estimates and are ready to diagram the activity dependencies. You should use which of the following? A. PDM techniques B. PDM or ADM techniques C. AON techniques D. ADM techniques

518


You are a project manager for Waterways Houseboats, Inc. You have been asked to perform a benefit/cost analysis for two proposed projects. Project A costs $2.4 million with potential benefits of $12 million and future operating cost of $3 million. Project B costs $2.8 million with potential benefits of $14 million and future operating costs of $2 million. Which project should you recommend? A. Project A because the cost to implement is cheaper than Project B B. Project A because the potential benefits plus the future operating costs are less in value than the same calculation for Project B C. Project B because the potential benefits minus the implementation and future operating costs are greater in value than the same calculation for Project A D. Project B because the potential benefits minus the costs to implement are greater in value than the same calculation for Project A

683


What are the characteristics of management?

567






All of the following are tools and techniques of the Schedule Development process except? A. CPM B. RAM C. GERT D. PERT

541


Describe resource planning during the estimation of software project.

475


Three people are responsible for establishing cost of quality theories. Crosby and Juran are two of them, and their theories respectively are: A. Grades of quality, fitness for use B. Fitness for use, zero defects C. Zero defects, fitness for use D. Cost of quality, zero defects

557


Which of the following describes a unique characteristic of the project Executing and Controlling processes? A. The core processes in the Executing and Controlling processes are from the Project Integration knowledge area from the Project Integration knowledge area. B. Both the Executing and Controlling processes measure variances in project performance and use corrective action to bring performance hack in line with the plan. C. Executing is an input to the Controlling processes, and Controlling is an input to Execution. D. Executing and controlling each have only one core process.

762


You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any rime during the day. The project sponsor has promised you a bonus if you get this project completed two weeks sooner than the scheduled project end date. The bonus will come in handy on your trip to the Bahamas planned for later this spring. You've got a few remaining project activities to wrap up before you can close out the project. Which of the following is the most appropriate response? A. You tell the sponsor the project is complete and treat the remaining activities as though they're problems that came up after project closure so that you can still get the bonus. B. You tell the sponsor the remaining activities are outside the scope of the project so the project really is completed and collect your bonus. C. You tell the sponsor the stakeholders added these requirements after the project was well under way and you never agreed to include them in the project so the project really is complete, and you collect your bonus. D. You tell the sponsor you aren't going to make the two-week early completion date as there are remaining activities to finish up.

605


Project managers have the greatest amount of authority in which kind of organizational structure? A. Functional B. Projectized C. Weak matrix D. Balanced matrix

652


Halloween is approaching fast. Your market research shows that the little yellow chicks and pink bunny marshmallow candies are the best-selling candy at Easter time, outselling all other types of candies. This prompts the company to introduce a new version of marshmallow candies with Halloween themes this season. Which of the following is true? A. This project came about due to customer request, and the primary constraint is time B. This project came about due to market demand, and the primary constraint is time. C. This project came about due to market demand, and the primary constraint is quality. D. This project came about due to customer request, and the primary constraint is quality.

632


As a PMP, one of your responsibilities is to ensure integrity on the project. When your personal interests are put above the interests of the project or when you use your influence to cause others to make decisions in your favor without regard for the project outcome, this is considered: A. Conflict of interest B. Using professional knowledge inappropriately C. Culturally unacceptable D. Personal conflict issue

542


Project managers have the highest level of authority and the most power in which type of organizational structure? A. Projectized B. Strong matrix C. Functional D. Balanced matrix

678


Explain the meaning of management.

537