Your selection committee meets on a semiannual basis. They've determined that projects must meet or exceed a specific profit limit in order to be accepted and prioritized on the project list. Which of the following is true?
A. The selection committee has defined project selection criteria, which is a tool and technique of Initiation.
B. The selection committee has defined project selection methods, which is a tool and technique of Initiation.
C. The selection committee has defined project selection methods, which is an input to Initiation.
D. The selection committee has defined project selection criteria, which is an input to Initiation.
No Answer is Posted For this Question
Be the First to Post Answer
You are the project manager for Design Your Web Site, Inc. Your company is designing the website for a national grocery score chain. You have your activity list in hand and are ready to diagram the activity dependencies using the PD technique. You know that: A. PDM uses AON diagramming methods. B. PDM uses AOA diagramming methods. C. PDM uses ADM diagramming methods. D. PDM uses PDM diagramming methods.
You are the project manager for Heartthrobs by the Numbers Dating Services. You’re working on an updated Internet site that will display pictures as well as short bios of prospective heartbreakers. You have your activity list and resource requirements in hand and are planning on using qualitatively based durations and reserve time to determine activity durations. Which of the following is true? A. You are using inputs of the Activity Duration Estimating process. B. You are using tools and techniques of the Cost Estimating process. C. You are using tools and techniques of the Activity Duration Estimating process. D. You are using inputs of the Cost Estimating process.
All of the following are characteristics of the project Closing processes except: A. Probability for success is greatest here. B. The project manager's influence is greatest here. C. The stakeholders' influence is least here. D. Risk is greatest here.
You are the project manager for Zippy Tees. Your company has decided to outsource the manufacturing of miniature bears to be attached to your trendy T-shirts. Which of the following is true? A. A good product description is all that's required. The project manager will supply this to the vendor. B. The contract can serve as the project charter. The product description will be included in the contract. C. The project manager should write the project charter because the project manager will be managing the vendor portion of this project as well. D. The vendor should write the project charter as they are responsible for manufacturing the bears.
You are a contract project manager for a wholesale flower distribution company. Your project is to develop a website for the company that allows retailers to place their flower orders online. You will also provide a separate link for individual purchases that are ordered, packaged, and mailed to the consumer directly from the grower's site. This project involves coordinating the parent company, growers, and distributors. You are preparing a performance review and have the following measurements at hand: PV = 300; AC = 200; and EV = 250. What do you know about this project? A. The EAC is a positive number, which means the project will finish under budget. B. You do not have enough information to calculate CPI. C. The CV is a negative number in this case, which means you've spent less than what you planned as of the measurement date. D. The CV is a positive number in this case, which means you're under budget as of the measurement date.
You know that PV = 475, AC = 430, EV = 480, EAC = 40, and BAC = 525. What is VAC? A. 440 B. 390 C. 485 D. 435
You are a project manager for Star Light Strings. Star Light manufactures strings of lights for outdoor display. Their products range from simple light strings to elaborate lights with animal designs, bug designs, memorabilia, and so on. Your newest project requires a scope change. You have documented the characteristics of the product and its functionality using which of the following tools and techniques? A. Change control system B. Corrective action C. Configuration management D. Updates to the scope management plan
What are the different types of software risks?
You are a project manager who believes people will always perform at their best if given the proper expectations and motivation. Which theory do you subscribe to? A. Theory X B. Hygiene theory C. Contingency theory D. Theory Y
You have been hired as a contract project manager for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. Customers must pre-register before being allowed to order wine over the Internet so that legal age can be established. You tested using data from Grapevine's existing database. This new module cannot be tested until the data from the existing system is loaded. This is an example of which of the following? A. Preferential logic B. Soft logic C. Discretionary dependency D. Hard logic
Your project's primary constraint is quality. In order to make certain the project team members don't feel too pressed for time and to avoid schedule risk, you decide to use which of the following activity estimating tools? A. Expert judgment B. Quantitatively based durations C. Reserve time D. Analogous estimating
The Critical Path Method is a mathematical tool and technique of the Schedule Development process. All of the following are true regarding CPM except: A. Determines a single early and late start date and a single early and late finish date B. Calculates expected value C. Focuses on the calculation of float time D. Shows the critical path, or the path with the longest duration