Answer / v.ramachandran
More Precisely it is the back tracking of information about
to which parent material a child item is allocated
Is This Answer Correct ? | 17 Yes | 2 No |
Answer / sundhu
Use of Pegged Requiremets:
You can use the Pegged requirements function to retrace
from any BOM level
1) which requirements are the source of which procurement
proposals
2) which independent requirements (especially sales orders)
are affected if a procurement proposal is cancelled or a
date or quantity is changed on a lower level.
Is This Answer Correct ? | 7 Yes | 1 No |
Answer / devesh bohre
we can take is as"where used Item" by which one can come to
know about the presenece of one particular Item
(RM/SF/Componant) in Numbers of Finished good or in various
BOMs.
e.g
if item A is used in BOM of S,T U and X and X is also used
in S so out put will be as
A--S--x
--T
--U
--X
Is This Answer Correct ? | 5 Yes | 2 No |
Answer / prasanna
A requirement linked to a demand is called a pegged
requirement.
Is This Answer Correct ? | 5 Yes | 2 No |
Answer / vinod
it a link between the reciept and issue/requirement
elements.
by this we can get the exact relation like eg: the
production order and sales order or planned order and
independent requirement....
Is This Answer Correct ? | 2 Yes | 1 No |
Answer / girish
Sundhu is exacly right .
It is as per SAP education Book provided.
Pegged Requirement function provide the facility to find out,
Which requirements(like sales order or PIR) have caused to generate which procurement proposal(like planned order or Purchase req. or purch. order ). and It finds the link between the that requirement and its respective procurement proposal.
Is This Answer Correct ? | 2 Yes | 1 No |
Answer / anand patil
More precisely it is the back tracking of information to
which prod. order that component is allocated
Is This Answer Correct ? | 2 Yes | 10 No |
What are the levels of batch, explain batch determination process?
Explain transaction code KO88 or CO88.
what is the difference between backward scheduling and forward scheduling ?
Scheduling times can be defined in the material master record by?
What is a ‘routing’ in pp?
Difference between Manual reorder point and Automatic reorder point.
What is variant material ?
Mention how mrp (material requirement planning) types are classified?
We have deleted a group key in an operation in routing and the same does not appear for this routing (CA02). But we noticed that entries are maintained in table PLPO and the deletion indicator is not set. How does the system remember this deletion of group key?
Have idea about variant configure
2 Answers Accenture, ASD Lab, Cap Gemini, IBM, Sunbeam,
What are the basic dates?
What is alternative bom