A and B can finish a piece of work in 20 days .B and C in
30 days and C and A in 40 days.
In how many days will A alone finish the job?
Answers were Sorted based on User's Feedback
(A+B)'s 1 day's work = 1/20
(B+C)'s 1 day's work = 1/30
(C+A)'s 1 day's work = 1/40
Adding above, 2(A+B+C)=(1/20)+(1/30)+(1/40)
=13/120
A+B+C =13/240
To get A's work,(A+B+C)-(B+C)=(13/240)-(1/30)
=5/240
Therefore A can finishes the work in 240/5 days .ie 48 days
| Is This Answer Correct ? | 144 Yes | 7 No |
How to Count number of nucleotide substitutions ?
How to predict the structure of a sequence?
How many bonds are present in CO2 molecule?
What is the idea behind ?weighting? sequences in the package CLUSTAL W for multiple alignment? How are these weights calculated?
Suppose the Blast search returned 100 hits. Of these, 17 were false positives and we knew that there were 165 sequences in the database which should have returned a hit with our sequence. How many false negatives were there, and what is the sensitivity and selectivity of Blast in this instance?
What is the difference in terms of connectivity between a scale free network and random network?
If cos2A + cos2B + cos2C = 1 then ABC is which type of triangle?
what is a qi number?
Which of the following is most acidic? (a) C2H5OH (b) CH3CHOHCH3 (c) Ethanol (d) CH3OH.
? : BGLQ : : YDIN : VAFK
What is Pharmacogenomics?
WHY YOU SELECT BIOINFORMATICS AS YOUR MAJOR FIELD??