What is CMM-1,2,3,4,5 Level Company?
How much levels are there like CMM?

Answers were Sorted based on User's Feedback



What is CMM-1,2,3,4,5 Level Company? How much levels are there like CMM?..

Answer / eswar

capability maturity model, this shows the company standards
the procedured

1) Initial: The software process is characterized as ad hoc,
and occasionally even chaotic. Few processes are defined,
and success depends on individual effort and heroics.
2) Repeatable: Basic project management processes are
established to track
cost, schedule, and functionality. The necessary process
discipline is in place to repeat earlier successes on
projects with similar applications.
3) Defined :The software process for both management and
engineering activities is documented, standardized, and
integrated into a standard software process for the
organization. All projects use an approved, tailored version
of the organization's standard software process for
developing and maintaining software.
4) Managed :Detailed measures of the software process and
product quality are collected. Both the software process and
products are quantitatively understood and controlled.
5) Optimizing :Continuous process improvement is enabled by
quantitative feedback from the process and from piloting
innovative ideas and technologies.

Is This Answer Correct ?    10 Yes 2 No

What is CMM-1,2,3,4,5 Level Company? How much levels are there like CMM?..

Answer / glamorous

1.Initial: Initial process
2.Managed:Basic project management
Steps in level2: Requirements Management
Project Planning
Project Monitoring & Control
Measurement & Analysis
Process & Product Quality Assurance
Configuration Management
3.Defined:Process standardization
Steps in level3:Requirements Development
Technical Solution
Product Integration
verification
validation
Organisational Process focus
Organisational Process definition
Organisational Training
Integrated Project Management
Risk Management
Integrated Teaming
Decision analysis and resolution
Organizational environment for integration
4.Quantitatively Managed:Quantitative management
Steps in level4:Organizational procee performance
quantitative project management
5.optimising:Continuous process improvement
Steps in level5:organizational innovation and deployment
analysis and resolution
-----------------------------------------------------------


Requirements Development Process

Templates: SRS
Checklists: RD Process, SRS
INPUTS:URD
REQUIREMENTS DEVELOPMENT:Develop product requirements
Analyze and Validate requirements
Use cases development
OUTPUTS:
Develop product requirements
Analyze and Validate requirements
Use cases development
METRICS:Time spent on analysis phase
VERIFICATION:Review of SRS by PM & approved by SDH
SQA reviews the SRS
------------------------------------------------------------

Product Integration Process

Checklist: PI Checklist
INPUTS:
HLD
LLD
SDP
PRODUCT INTEGRATION:
Product integration planning
Product integration testing
OUTPUTS:Integration plan(SDP)
Integration testing
Integration test cases
VERIFICATION:PL and PM reviews the Product Integration items
------------------------------------------------------------
Design Process

Templates: Design Change Request, HLD , LLD

Checklists:HLD,LLD, Architectural Design Review Checklist
INPUTS:
Design constraints
SRS
Change requests
URD
SDP
DESIGN PROCESS:
High Level Design
Low Level Design
Use case diagrams
Sequence diagrams
Data Flow
Physical data base design
OUTPUTS:TS plan
HLD
LLD
METRICS:SQA audit NC
Time spent on design Phase
VERIFICATION:PM verifies and approves the HLD, LLD &
database documents.
SQA verifies the design items.
------------------------------------------------------------
Coding and Development Process

Templates: Unit Test Case, Unit Test Report, Customer
Acceptance form

Guidelines: Coding guidelines
INPUTS:
Project Plan
SRS
HLD
LLD
Coding standards
Design updates
CODING/DEVELOPMENT:Development
Unit testing
OUTPUTS:Code
Code review report
Code peer review reports
Unit test cases
Unit test reports
METRICS:Coding defects
Time spent on coding
Unit test results(Bug reports)
Audit NC
VERIFICATION:PM and SQA verifies the development items.
------------------------------------------------------------
Validation Process

Templates: Software Test Plan, Test Case form, Defect
Report, Test Summary Report,
Tester weekly Status Report
Checklists: Validation Process Checklist
INPUTS:
Managed Code
HLD
LLD
Test Plan
Test Cases
SDP
VALIDATION:
Integration Testing
System Testing
User Acceptance Testing
OUTPUTS: Test cases(UI, functional,
integration)
Defect reports
Test summary report
METRICS:Defect removal Efficiency
Time spent on validation
Audit NC’s
Defect detection rate
Defect Density
Defect injection rate
VERIFICATION:PM reviews the test plan and SDH approves the
test plan
Test Lead and SQA verifies test items
------------------------------------------------------------

Verification Process, Review Procedure

Templates: Peer review log, SRM Review Report, Peer Review
Report
Checklists: Verification Process Checklist
INPUTS:
SDP
MPP
VERIFICATION:
Verification of artifacts
Verification of code
OUTPUTS:Review report
Peer review log
METRICS:
Time spent on reviews
Review efficiency
Audit NC’s
VERIFICATION:PM and SQA reviews the verification process.
------------------------------------------------------------

Is This Answer Correct ?    9 Yes 2 No

What is CMM-1,2,3,4,5 Level Company? How much levels are there like CMM?..

Answer / friend

Thanks for Answers

Is This Answer Correct ?    2 Yes 3 No

Post New Answer

More Manual Testing Interview Questions

What are the type of testinmg to test in Unit, System,Integration and User acceptance testing< client side>

1 Answers  


difference between sretagic test plan & test plan?

2 Answers   IBM,


what is the format of traceability matrix u prepared in ur company?

3 Answers  


difference between change management and configuration management

0 Answers  


I have a build in which there are 17 files, now 3 new files added, in this case what type of testing will do

6 Answers   Calsoft,






functional testing test cases for transfer funds ?

0 Answers   PCS,


How would you do the ollowing Security Testing for web application? 1) Authentication. 2) Authorization. 3) cookies. 4) penetration testing. 5) session testing. 6) encryption and decryption testing

1 Answers   TCS, Wipro,


when u involved in uat suppose if u find one defect then do u intmate it or not

3 Answers  


Hi, Please tell how to write system test cases for between two modules. please ans real time expirience people... thanks in advance..

0 Answers  


Which design document supports to choose test data and how to select test data ranges ?

1 Answers  


Name some bug tracking tools???

3 Answers  


How to test login Page ? What wud be the possible Test cases ?

3 Answers  


Categories