Who will assign severity and priority to the bug?

Answers were Sorted based on User's Feedback



Who will assign severity and priority to the bug? ..

Answer / sj16

Both severity and priority is assigned by Tester only.Do not
confused with severity and priority.At same time when we
open a defect we have to assigned both severity and priority.

Is This Answer Correct ?    18 Yes 3 No

Who will assign severity and priority to the bug? ..

Answer / satya

Severity is defined based upon the Impact of the bug on the
functionality of the Application.
It is assigned by the Test Analyst who submitted the defect.

Priority is defined based upon the need of fixing the
defect and time constraints before pushing the code into
prodution.
Ex: The severity of the bug is High but due to some
constraints like cost and time,the priority can be set as
Low.In the same way a Low Severity defect can have a high
priority.

Priority can be assigned by Test Team Lead/Development
Manager who is aware of the criticality in fixing the
defect.

Is This Answer Correct ?    9 Yes 3 No

Who will assign severity and priority to the bug? ..

Answer / rkcr

Severity is given by test engineer and priority is given
by development team.

Is This Answer Correct ?    7 Yes 5 No

Who will assign severity and priority to the bug? ..

Answer / priyanka

While testing we find a bug and according to its impact on the application ,functionality we (testers) decides the severity
Priority is about to fixing the defect,that's why priority is assign by developers only..

Is This Answer Correct ?    2 Yes 0 No

Who will assign severity and priority to the bug? ..

Answer / syam

thank you rajesh

Is This Answer Correct ?    0 Yes 0 No

Who will assign severity and priority to the bug? ..

Answer / s.anvesh

As per my Knowledge
Both severity and priority can be decided by test engineer.

Is This Answer Correct ?    0 Yes 0 No

Who will assign severity and priority to the bug? ..

Answer / adnan

Severity is assigned by the tester , but before proritizing
a bug tester needs to talk to team lead.

Is This Answer Correct ?    1 Yes 2 No

Who will assign severity and priority to the bug? ..

Answer / rajesh.pothina

Severity is given by the Test engineer and the priority is
given by the Team Lead.

Is This Answer Correct ?    1 Yes 6 No

Who will assign severity and priority to the bug? ..

Answer / k.r.mohan

Severity is given by test engineer and priority is given
by developer.and are decided by team lead.

Is This Answer Correct ?    0 Yes 5 No

Who will assign severity and priority to the bug? ..

Answer / jp

As of my knowledge...

Severity is given by the Test Engineer and Priority is
given by the Client.

Is This Answer Correct ?    0 Yes 8 No

Post New Answer

More Manual Testing Interview Questions

What is integration level testing?

0 Answers  


What is difference between Smoke&Sanitary Testing?

9 Answers   HCL, Infotech,


Hi, Glamrous Should I write the test case for dropdown field For Above: -ve test case Test Case Name Expected Esult Without selecting Category - Default category should get select Is this a valid test case?

2 Answers  


waht is deffect?

9 Answers  


please make me understand what is client server and web application?

1 Answers   HCL,






Give me an example of something you tried at work but did not work out so you had to go at things another way.

0 Answers   Ordain Solutions,


What is Dynamic Binding and Dynamic Loss?

0 Answers   Digient Technologies,


.what are the types of recording modes in winrunner 2.what are the three modes of running a test in winrunner 3.what is synchronization point 4.what are the contents present in a test case 5.do we need testing for the project 6.what is code review and code walk through At which phase the testing starts (begin) in the project How do we test Client server applications and a Web applications what is verification and validation what is adhoc testing what is traceability matrix what is base line document what is Test Life Cycle what is regression testing and retesting what is a BUG LIFE CYCLE what is a Bug what are defects what is functionality testing and system testing. a project has to be released in one day but the testing people got that project from the developers half of the day before so what they have to do to complete the testing process. 20 what are severity level and priority levels

1 Answers   Stag Computers,


If there are more number of test cases, how can u pick up a selective test case?

4 Answers   Wipro,


I give you a functional requirement document(FRD) of 10 pages.Now you tell me,how to calculate Test effort,As i Need to say to the client ?