You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail store for the option of opening two new stores in a foreign country. You've been told that it is culturally unacceptable to eat certain foods in this country. You know that one of these foods happens to be a secret ingredient in the pizza sauce. What is the most appropriate response?
A. Inform the potential partners that your sauce recipe is secret, but you’re certain there are no forbidden ingredients in it.
B. Inform the potential partners that you suspect there might be a forbidden ingredient in the sauce and you'll request an investigation to determine if any of them exist in the sauce.
C. Inform the potential partners that a forbidden ingredient exists in the sauce and determine to work with them to come up with another ingredient to replace that one.
D. Don't tell the potential partners about the ingredient because the sauce they'll be using in the stores is shipped to them already prepared in cans. They won't know the ingredient is in the sauce.
Answer / Ankit Chaudhary
A. Inform the potential partners that your sauce recipe is secret, but you’re certain there are no forbidden ingredients in it.
| Is This Answer Correct ? | 0 Yes | 0 No |
Your company has asked you to be the project manager for the product introduction of their new DeskTop Rock media system. You recently published the scope statement and the supporting detail. The supporting detail contains all of the following except: A. Constraints B. Other project information not noted in the scope statement C. Code of accounts D. Assumptions
Project managers have the highest level of authority and the most power in which type of organizational structure? A. Projectized B. Strong matrix C. Functional D. Balanced matrix
You are implementing a sap project. implementation compled and development started and at that time you found that there is major problem with the system .It would take again time and customer is not happy with that ,in that case how do you convince customer?
What are the tools and techniques used in the Initiation process? A. Project selection criteria, historical information, expert judgment B. Project selection methods, historical information, expert judgment C. Project selection criteria, expert judgment D. Project selection methods, expert judgment
How a project is made and deliverd to client? please put all detailed steps internally?
You are a project manager for an international marketing firm. You are ready to assign resources to your new project using a work authorization system. All of the following are true except: A. Work authorization systems clarify and initiate the work for each work package. B. Work authorization systems are written procedures defined by the organization. C. Work authorization systems are tools and techniques of the Project Plan Execution process. D. Work authorization systems are an output of the Project Plan Execution process.
You are a project manager for Swirling Seas Cruises food division. You're considering two different projects regarding food services on the cruise lines. The initial cost of Project Fish'n for Chips will be $800,000 with expected cash inflows of $300,000 per quarter. Project Picnic's payback period is six months. Which project should you recommend? A. Project Fish'n for Chips because its payback period is two months shorter than Project Picnic’s B. Project Fish'n for Chips because the costs on Project Picnic are unknown C. Project Picnic because Project Fish'n for Chips' payback period is four months longer than Project Picnic’s D. Project Picnic because Project Fish'n for Chips' payback period is two months longer than Project Picnic's
Obtaining formal project plan approval and sign-off is important for all of the following reasons except: A. Stakeholders are able to recommend a project Planning methodology to follow throughout the remaining process groups. B. Stakeholders are aware of the project details, which make them more likely to participate in future project decisions. C. Stakeholders will be more likely to cooperate. D. Stakeholders are aware of the specific details regarding project schedules, budgets, and risks.
You are a project manager for Laurel’s theater productions. Your new project is coming in over budget and requires a cost change through the cost change control system. The cost variance was projected using which of the following tools and techniques? A. Performance measurements B. Cost baseline measurements C. Computerized tools D. Performance reports
You are a project manager for Penguin Software. Your company creates custom software programs for hospitals and large dental offices. You have just completed a project and are gathering the documentation of the product of the project. This might include all of the following except: A. Technical specifications B. Electronic files C. Programming plans D. Performance measurements
Your organization regularly uses a tool and technique of the Contract Closeout process to identify lessons learned, including the successes and failures, which will benefit future activity on this project and on future projects. Which tool and technique arc they using? A. Product documentation inspection B. Contract process review C. Performance measurement review D. Procurement audit
Your project sponsor has requested a cost estimate for the project. She would like the cost estimate to be as accurate as possible as this might be her one and only chance to secure the budget for this project due to recent cuts in special projects. You decide: A. To use analogous estimating techniques B. To use bottom-up estimating techniques C. To use top-down estimating techniques D. To use expert judgment techniques