Obtaining formal project plan approval and sign-off is important for all of the following reasons except:
A. Stakeholders are able to recommend a project Planning methodology to follow throughout the remaining process groups.
B. Stakeholders are aware of the project details, which make them more likely to participate in future project decisions.
C. Stakeholders will be more likely to cooperate.
D. Stakeholders are aware of the specific details regarding project schedules, budgets, and risks.
No Answer is Posted For this Question
Be the First to Post Answer
Which of the following are the tools and techniques of the Cost Budgeting process? A. Project management information system, analogous estimating, bottom-up estimating, mathematical analysis B. Analogous estimating, bottom-up estimating, mathematical analysis, computerized tools C. Project management software, analogous estimating, bottom-up estimating, parametric modeling D. Analogous estimating, bottom-up estimating, parametric modeling, computerized tools
You are a project manager for Snow Fun, a chain of retail shops specializing in winter sports gear and clothing. You’ve been working on contract with Snow Fun and are ready to move on to your next assignment. The customer has signed off on the project, formal acceptance notices have been distributed, and project closure procedures have been performed. What type of project ending is this? A. Extinction B. Starvation C. Integration D. Addition
You are a project manager for Dakota Software Consulting Services. You're working with a major retailer that offers their products through mail-order catalogs. They're interested in knowing customer characteristics, the amounts of first-time orders, and similar information. As a potential bidder for this project, you worked on the RFP response and submitted the proposal. When the selection committee received the RFP responses from all the vendors bidding on this project, they used a weighted system to make a selection. Which process did this occur in? A. Source Selection B. Solicitation C. Requisition D. Contract Administration
You are a project manager working on contract with a company in a foreign country. At the project kick-off meeting, you are given an expensive-looking gift. The person who presented this to you said that it is customary in their country to give their business partners gifts. What is the most appropriate response? A. Thank them and decline. Explain that this is considered personal gain, which is unacceptable in your country. B. Thank them and accept. You don't believe there is a conflict of interest or an integrity issue at stake. C. Thank them and decline. Explain that this is considered a conflict of interest, which is unacceptable in your country. D. Thank them and accept since you know that it would be considered offensive to decline the gift in their culture. Immediately report the acceptance of the gift to the appropriate parties at your company so that your actions are not called into question later.
What are the triple constraints? A. Time, schedules, and quality B. Time, availability, and quality C. Time, money, and schedules D. Time, money, and quality
Which of the following processes assess the likelihood of risk occurrences and their consequences using numeric probability assignments? A. Qualitative Risk Analysis B. Risk Identification C. Quantitative Risk Analysis D. Risk Response Planning
Sally is a project manager working on the Resource Planning process. She should consider all of the following when developing the resource requirements output except: A. WBS B. Supply purchase policies C. Resource rates D. Special knowledge and talents
You are a project manager for Star Light Strings. Star Light manufactures strings of lights for outdoor display. Their products range from simple tight strings to elaborate lights with animal designs, bug designs, memorabilia, and so on. Your newest project requires a change. One of the business unit managers submitted a change through the change control system, which utilizes a CCB. Which of the following is true regarding the CCB? A. Describes how change requests are managed B. Requires all change requests in writing C. Approves or denies change requests D. Requires updates to the appropriate management plan
Critical path tasks are those tasks that: A. Have equal pessimistic, optimistic, and most likely estimated times B. Have a float rime of zero C. Have the same start date D. Have multiple early start dates and early finish dates
What is the meaning of scope of the project?
What is tracing process? How this can be enabled?
Your nonprofit organization is preparing to host its first annual 5K run/walk in City Park. You worked on a similar project for the organization two years ago when it co-hosted the 10K run through Overland Pass. Which of the Initiation process inputs might be helpful to you on your new project? A. The strategic plan, because you'll want to make sure the project reflects the overall strategic direction of the organization. B. Historical information on the 10K run project. You might be able to gather helpful project information since this new project is similar in nature. C. The product description, which would describe all the details of the run/walk program. D. Historical information from the recent blood drive project.