Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


You are the newly appointed project manager for a pharmaceutical company. Your company has asked you to head up a project to research a new children's medication. You've identified the lab equipment you'll need, the software needed to perform analysis and measurements, and the skill level and types of the technicians and researchers for this project. Which of the following is true?
A. The project manager and resources have been identified as part of the outputs of the Initiation process, and this information can be found in the project charter.
B. The resources and project manager have been identified as an input to the project Initiation phase. Further information is needed to produce the project charter, which will include the resources and project manager.
C. The project manager and resources have been identified as part of the project selection process. The selection committee requires resource information to make a final decision.
D. The resources and project manager have been identified as part of the project selection process. The selection committee requires resource information to make a final decision.


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

Project selection criteria might include: A. Benefit measurement methods B. Constrained optimization analysis C. NPV calculations D. Potential market share or increased public perception

0 Answers  


Which of the following describes a unique characteristic of the project Executing and Controlling processes? A. The core processes in the Executing and Controlling processes are from the Project Integration knowledge area from the Project Integration knowledge area. B. Both the Executing and Controlling processes measure variances in project performance and use corrective action to bring performance hack in line with the plan. C. Executing is an input to the Controlling processes, and Controlling is an input to Execution. D. Executing and controlling each have only one core process.

0 Answers  


Change control system, configuration management, performance measurement, additional planning, and project management information system are tools and techniques of which process? A. Integrated Change Control B. Scope Change Control C. Schedule change control D. Cost change control

0 Answers  


Which performance measurement is the cost of work budgeted for an activity within a certain time frame? A. AV B. PV C. EV D. EAC

0 Answers  


You are a project manager for Bluebird Technologies. Bluebird writes custom billing applications for several industries. A scope change has been requested. You know change is concerned with all of the following except: A. Managing change B. Verifying change C. Influencing causes of change D. Determining that a change occurred

0 Answers  


You are a project manager with technical expertise in the pharmaceutical industry. You've decided to try your hand at project management in the entertainment industry. Which of the following is true? A. You will likely be successful because communication skills are your strong suit. You anticipate having technical experts on your project team to address industry specifics that you're not familiar with. B. You will likely be successful because your organizational skills are excellent. You anticipate having technical experts on your project team to address industry specifics that you're not familiar with. C. You will probably be successful because you have a friend in the entertainment industry that has briefed you on all the important aspects of this project that you'll need to know. You anticipate having technical experts on your project team to address industry specifics that you're not familiar with. D. You will probably not be successful because you have little knowledge of the entertainment industry even though you anticipate having technical experts on your project team to address industry specifics that you're not familiar with.

0 Answers  


What is one of the problems with project management software? A. The project manager manages the software instead of the project B. Project duration calculations are sometimes approximate. C. You cannot override the project management software decisions regarding schedules. D. It’s expensive and difficult to use.

0 Answers  


All of the following are true regarding Pareto diagrams and Pareto theory except: A. Pareto diagrams are histograms. B. Pareto diagrams rank order factors. C. A small number of causes create the majority of problems. D. Pareto diagrams use two variables.

0 Answers  


You are a project manager for a software manufacturing firm. The project you've just finished created a new software product that is expected to become a number-one seller. A friend of yours is a certified software instructor. They have asked you for a copy of the software prior to the beta release through the marketing department so they can get familiar with it. What is the most appropriate response? A. Since your friend is certified to teach your company's brand of software, provide them with a copy of the software. B. Ask them to sign a nondisclosure agreement before releasing a copy of the software. C. Decline the request since you stand to gain from this transaction by receiving free training. D. Decline the request because the software is the intellectual property of the company.

0 Answers  


You have been assigned to a project in which the objectives are to direct customer calls to an Interactive Voice Response system before being connected to a live agent. You are in charge of the media communications for this project. You report lo the project manager in charge of this project and the VP of marketing, who share responsibility for this project. Which organizational structure do you work in? A. Functional organization B. Weak matrix organization C. Projectized organization D. Balanced matrix organization

0 Answers  


How to deal with underperforming team members?

0 Answers  


You are working on a project that was proceeding well until a manufacturing glitch occurred that requires corrective action. It turns out the glitch was an unintentional enhancement to the product, and the marketing people are absolutely crazy about its potential. The corrective action is canceled, and you continue to produce the product with the newly discovered enhancement. As the project manager, you know that a change has occurred to the product scope as the glitch changed the characteristics of the product. Which of the following is true? A. Changes to product scope are reflected in the project scope. B. Changes to product scope are reflected in the integrated change control plan. C. Changes to product scope are a result of changes to the product description. D. Changes to product scope are a result of corrective action.

0 Answers  