You are a project manager for Bluebird Technologies. Bluebird writes custom billing applications for several industries. A scope change has been requested. You know change is concerned with all of the following except:
A. Managing change
B. Verifying change
C. Influencing causes of change
D. Determining that a change occurred
No Answer is Posted For this Question
Be the First to Post Answer
What are the different types of software risks?
You are a project manager for Laurel’s theater productions. Your new project is coming in over budget and requires a cost change through the cost change control system. The cost variance was projected using which of the following tools and techniques? A. Performance measurements B. Cost baseline measurements C. Computerized tools D. Performance reports
You are a contract project manager working with the State of Bliss. Your latest project involves rewriting the Department of Revenue's income tax system. As project manager, you have taken all the appropriate actions regarding confidentiality of data. One of the key stakeholders is a huge movie huff, and she has the power to promote you into a better position at the conclusion of this project. She's reviewing some report data that just happens to include confidential information regarding one of her favorite movie superstars. What is the most appropriate response? A. Report her to the management team. B. Request that she immediately return the information, citing conflict of interest and violation of confidential company data. C. Do nothing as she has the proper level of access rights to the data and this information showed up unintentionally. D. Request that she immediately return the information until you can confirm that she has the proper level of access rights to the data.
Which of the following is true regarding NPV? A. NPV assumes reinvestment at the cost of capital. B. NPV decisions should be made based on the highest value for all of the selections. C. NPV assumes reinvestment at the prevailing rate. D.NPV assumes reinvestment at the NPV rate.
The grouping of project elements by deliverables is known as what? A. The code of accounts B. The work package C. The work breakdown structure D. The work breakdown dictionary
You are project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements. All of the following are valid options except: A. You document the poor performance in written form and send the correspondence to the subcontractor change request through Contract Administration. B. You terminate the contract for poor performance and submit a change request through Contract Administration. C. You submit a change request through Contract Administration to ask the subcontractor to comply with the terms of the contract. D. You agree to meet with the subcontractor to see if a satisfactory solution can be reached.
Which of the following processes are performed in the Closing process group and in what order? A. Administrative Closure then Contract Closeout B. Scope Verification then Administrative Closure C. Contract Closeout then Scope Verification D. Contract Closeout then Administrative Closure
You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. You do not expect these variances to continue, as they're atypical. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 25 B. 760 C. 775 D. 833
What is the difference between direct and indirect measures?
People are motivated by the need for achievement, power, or affiliation according to which theory? A. Expectancy theory B. Achievement theory C. Contingency theory D. Theory X
How a project is made and deliverd to client? please put all detailed steps internally?
You are the project manager for the Late Night Smooth Jazz Club chain, with stores in 12 states. Smooth Jazz is considering opening a new club in Kansas City or Spokane. You have derived the following information: Project Kansas City: The payback period is 27 months, and the IRR is 35 percent. Project Spokane: The payback period is 25 months, and the IRR is 32 percent. Which project should you recommend to the selection committee? A. Project Spokane because the payback period is shortest B. Project Kansas City because the IRR is highest C. Project Spokane because the IRR is lowest D. Project Kansas City because the payback period is longest ?