As a PMP, you will be required to comply with the Project Management Professional Code of Professional Conduct. Part of your responsibility concerns applying professional knowledge. All of the following are part of applying professional knowledge except:
A. Developing relationships based on mutual respect
B. Staying abreast of project management practices
C. Keeping up with industry trends and new technology
D. Honestly reporting your project management experience


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

The grouping of project elements by deliverables is known as what? A. The code of accounts B. The work package C. The work breakdown structure D. The work breakdown dictionary

0 Answers  


Your nonprofit organization is preparing to host its first annual 5K run/walk in City Park. You worked on a similar project for the organization two years ago when it co-hosted the 10K run through Overland Pass. Which of the Initiation process inputs might be helpful to you on your new project? A. The strategic plan, because you'll want to make sure the project reflects the overall strategic direction of the organization. B. Historical information on the 10K run project. You might be able to gather helpful project information since this new project is similar in nature. C. The product description, which would describe all the details of the run/walk program. D. Historical information from the recent blood drive project.

0 Answers  


You are a project manager working on contract with a company in a foreign country. At the project kick-off meeting, you are given an expensive-looking gift. The person who presented this to you said that it is customary in their country to give their business partners gifts. What is the most appropriate response? A. Thank them and decline. Explain that this is considered personal gain, which is unacceptable in your country. B. Thank them and accept. You don't believe there is a conflict of interest or an integrity issue at stake. C. Thank them and decline. Explain that this is considered a conflict of interest, which is unacceptable in your country. D. Thank them and accept since you know that it would be considered offensive to decline the gift in their culture. Immediately report the acceptance of the gift to the appropriate parties at your company so that your actions are not called into question later.

0 Answers  


What do you mean by business object,condition object and costomising object?

1 Answers   DELL, Satyam,


You are a project manager for Laurel’s theater productions. Your new project is coming in over budget and requires a cost change through the cost change control system. The cost variance was projected using which of the following tools and techniques? A. Performance measurements B. Cost baseline measurements C. Computerized tools D. Performance reports

0 Answers  






You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization’s operating system on 236 servers. You performed this project under contract. You are in the Closing process and know that product verification is for what purpose? A. To verify the goals of the project and assure the product of the project is complete B. To evaluate all the work of the project and compare results to project scope C. To verify all the work was completed correctly and satisfactorily D. To evaluate project goals and assure the product of the project meets the requirements

0 Answers  


You know that BAC = 375, PV = 300, AC = 200, and EV = 250. Variances that have occurred on the project to date are not expected to continue. What is the ETC? A. 75 B. 50 C. 125 D. 150

0 Answers  


You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. You do not expect these variances to continue, as they're atypical. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 25 B. 760 C. 775 D. 833

0 Answers  


You are the project manager for a new construction project in your city. Your longtime personal friend is bidding on the project. They've asked you to give them an indication of the budget for this project so that they do not overbid and lose the deal. What is the most appropriate response? A. Give the information to your friend. You know their character and can trust that they won't tell anyone. B. Tell your friend that after all this time, they should know you better than to think you'd put your personal integrity on the line or compromise your job due to a conflict of interest. Decline to give them the information. C. Tell your friend you'll give them the information if they'll promise not to tell anyone and if they'll agree to help you out with some materials on your basement-refinishing project. D. Give the information to your friend and inform the project sponsor so that the information can be shared with the other bidders as well.

0 Answers  


If you know expected value is 500 and the standard deviation is 12, you can say with approximately a 95 percent confidence rating which of the following? A. The activity will take between 488 and 512 days. B. The activity will take between 464 and 536 days. C. The activity will take between 494 and 506 days. D. The activity will take between 476 and 524 days.

0 Answers  


You are a contract project manager working with the State of Bliss. Your latest project involves rewriting the Department of Revenue's income tax system. As project manager, you have taken all the appropriate actions regarding confidentiality of data. One of the key stakeholders is a huge movie huff, and she has the power to promote you into a better position at the conclusion of this project. She's reviewing some report data that just happens to include confidential information regarding one of her favorite movie superstars. What is the most appropriate response? A. Report her to the management team. B. Request that she immediately return the information, citing conflict of interest and violation of confidential company data. C. Do nothing as she has the proper level of access rights to the data and this information showed up unintentionally. D. Request that she immediately return the information until you can confirm that she has the proper level of access rights to the data.

0 Answers  


Your company has asked you to be the project manager for the product introduction of their new DeskTop Rock media system. You recently published a document that establishes the scope baseline. Which of the following is true? A. This is the scope statement, which is an output of the Scope Planning process. B. This is the scope statement, which is an output of the Scope Definition process. C. This is the scope statement, which is a tool and technique of the Scope Definition process. D. This is the scope management plan, which is an output of the Scope Definition process.