As a PMP, you will be required to comply with the Project Management Professional Code of Professional Conduct. Part of your responsibility concerns applying professional knowledge. All of the following are part of applying professional knowledge except:
A. Developing relationships based on mutual respect
B. Staying abreast of project management practices
C. Keeping up with industry trends and new technology
D. Honestly reporting your project management experience
No Answer is Posted For this Question
Be the First to Post Answer
You have been asked to submit a proposal for a project that has been put out for bid. First, you attend the bidders conference to ask questions of the buyers and to hear the questions some of the other bidders will ask. Which of the following is true? A. Bidders conferences are a tool and technique of the Source Selection process. B. Bidders conferences are an output of the Source Selection process. C. Bidders conferences are an output of the Solicitation process. D. Bidders conferences are a tool and technique of the Solicitation process.
Which of the following tools and techniques shows the impacts of one decision over another as well as the probability and cost of each risk along a logical path? A. Simulation B. Decision tree C. Probability/impact risk matrix D. Sensitivity analysis
Your company manufactures small kitchen appliances. They are introducing a new product line of appliances in designer colors with distinctive features for kitchens in small spaces. These new products will be offered indefinitely starting with the spring catalog release. In order to determine the characteristics and features of the new product line, you will have to perform which of the following? A. Fast tracking B. Consulting with the stakeholders C. Planning the project life cycle D. Progressive elaboration
You are preparing a diagram that plots two variables, the dependent variable and the independent variable, to see the relationship between the two elements. What kind of diagram are you using? A. Cause-and-effect diagram B. Control chart C. Flowchart D. Scatter diagram
Which of the following project-scheduling techniques allows for conditional and probabilistic treatment? A. GERT B. CPM C. PERT D. CPM and PERT
You are going to take some performance measurements for your current project. You know that PV = 450, AC = 500, and EV = 375. What is the CV and SV respectively? A. CV = 125, and SV = 75 B. CV=-75, and SV=-125 C. CV = 75, and SV = 125 D. CV=-125, and SV=-75
What is the triple constraint triangle in project management?
What are the tools and techniques used in the Initiation process? A. Project selection criteria, historical information, expert judgment B. Project selection methods, historical information, expert judgment C. Project selection criteria, expert judgment D. Project selection methods, expert judgment
You are a project manager for Star Light Strings. Star Light manufactures strings of lights for outdoor display. Their products range from simple tight strings to elaborate lights with animal designs, bug designs, memorabilia, and so on. Your newest project requires a change. One of the business unit managers submitted a change through the change control system, which utilizes a CCB. Which of the following is true regarding the CCB? A. Describes how change requests are managed B. Requires all change requests in writing C. Approves or denies change requests D. Requires updates to the appropriate management plan
You are the project manager for a cable service provider. Your team members are amiable with each other and are careful to make project decisions jointly. Which of the following is true? A. They are in the smoothing stage of Team Development. B. They are in the norming stage of Team Development. C. They are in the forming stage of Team Development. D. They are in the forcing stage of Team Development.
What is "Readjustig goal and Milestone" in project managment and project planing
You are a project manager for a network cabling project for your organization. Your project team is made up of six full-time employees and three contractors. This is the first time they have all worked together. You know that the team will go through the stages of team development in the following order: A. Forming, storming, norming, and performing B. Storming, norming, forming, and performing C. Norming, storming, forming, and performing D. Forming, norming, storming, performing