All of the following are true regarding Ishikawa diagrams in the Quality Planning process except:
A. They are also called cause-and-effect diagrams.
B. They are also called fishbone diagrams.
C. They are a tool and technique of this process.
D. They are an output of this process.


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

You are a project manager responsible for the construction of a new office complex. You are taking over for a project manager who recently left the company. The prior project manager completed the project charter and the scope statement for this project. In your interviews with some key stakeholders, you conclude that the scope statement was poorly constructed. You know all of the following are true except: A. It will be difficult to assess future project decisions from this scope statement. B. It will be difficult to decompose the deliverables from this scope statement. C. It will be difficult to assess cost and time estimates from this scope statement. D. It will be difficult to create an accurate WBS from this scope statement.

0 Answers  


what are function points ,how do you estimate task based on function points?

1 Answers  


You are a project manager for a telecommunications firm. You're working on a project that entails upgrading technical hardware and equipment. The estimated cost of the hardware and equipment is $1,725,000. You are reviewing products from three different vendors. One of the vendors offers you and your family the use of the company yacht for the upcoming three-day weekend. What is the most appropriate response? A. Thank them and accept. You don't believe there is a conflict of interest or an integrity issue at stake. B. Thank them and decline. You know this could be considered personal gain, which could call your integrity into question. C. Thank them and accept. Immediately report your actions to the project sponsor so that your motives are not called into question after the fact. D. Thank them and decline. You know this could be considered an integrity issue on the part of the vendor.

0 Answers  


The primary function of the Closing process is to: A. Formalize lessons learned and distribute this information to project participants B. Perform audits to verify the project results against the project requirements C. Formalize project completion and disseminate this information to project participants D. Perform post-implementation audits to document project successes and failures

0 Answers  


If your expected value is ll0 and the standard deviation is l2, which of the following is true? A. There is approximately a 99 percent chance of completing this activity between 86 and 134 days. B. There is approximately a 68 percent chance of completing this activity between 98 and 122 days. C. There is approximately a 95 percent chance of completing this activity between 98 and 122 days. D. There is approximately a 75 percent chance of completing this activity between 86 and 134 days.

0 Answers  






You are working on a project that will upgrade the phone system in your customer service center. You have used bottom-up estimating techniques to assign costs to the project activities and have determined the cost baseline. Which of the following is true? A. You have completed the Cost Estimating process and now need to complete the Cost Budgeting process to determine the project's baseline. B. You have completed the Project Plan Development process and established a project baseline to measure future project performance against. C. You have completed the Cost Estimating process and now need to complete the Project Plan Development process to establish a project baseline to measure future project performance against. D. You have completed the Cost Budgeting process, and the cost baseline will be used to measure future project performance.

0 Answers  


During the opening rounds of contract negotiation, the other party uses a fait accompli lactic. Which of the following is true? A. One party agrees to accept the offer of the other party but secretly knows they will bring the issue hack up at a later time. B. One party claims the issue under discussion was documented and accepted as part of Scope Verification. C. One party claims the issue under discussion has already been decided and can't be changed. D. One party claims to accept the offer of the other party provided a contract change request is submitted describing the offer in detail.

0 Answers  


Waht is the level of criticallity in Project management for a Project which is started in maintenance Phase ? Which phase of Project management theory must be more focused for such kind of projects .

6 Answers   ABB, BGR Energy, TCS,


What are the tools and techniques of the Quantitative Risk Analysis process? A. Checklists, flowcharting, interviewing B. Interviewing, sensitivity analysis, decision tree analysis, simulation C. Checklists, sensitivity analysis, decision tree analysis, information-gathering techniques D. Interviewing, checklists, assumptions analysis, risk probability impact

0 Answers  


You are a project manager working in a foreign country. You observe that some of your project team members are having a difficult time adjusting to the new culture. You provided them training on cultural differences and the customs of this country before arriving, but they still seem uncomfortable and disoriented. Which of the following is true? A. This is the result of working with teams of people from two different countries. B. This condition is known as culture shock. C. This is the result of jet lag and travel fatigue. D. This condition is known as global culturalism.

0 Answers  


All of the following are true regarding the tools and techniques of Activity Sequencing except: A. GERT uses analogous methods. B. GERT allows for loops. C. GERT is a conditional diagramming method. D. GERT allows for conditional branches.

0 Answers  


Which of the following is true regarding the scope statement? A. It describes how to make changes to project scope. B. It describes project deliverables and serves as a baseline for future project decisions. C. It assesses the stability of the project scope and is a baseline for future project decisions. D. It assesses the reliability of the project scope and describes the frequency of changes and their impacts.

0 Answers  


Categories