Which of the following is true regarding IRR?
A. IRR assumes reinvestment at the cost of capital.
B. IRR is the discount rate when NPV is greater than zero.
C. IRR is a constrained optimization method.
D. IRR is the discount rate when NPV is equal to zero. ?


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

You have collected the performance measurement documentation for your project to be included in the project archives. What is the purpose of the performance measurement documentation? A. It's used as part of the formal acceptance process to verify contract expenditures. B. It's reviewed to make certain the project goals and objectives were met. C. It's included in the project archive documentation after confirming the accuracy of the measurements. D. It’s used as historical information for future project that are similar in scope to this project.

0 Answers  


what is the use of computer in project management system ?

2 Answers  


How do you quantitatively analysis the quality of a project during development?

3 Answers  


Each of the following describes an element of the Scope Definition process except: A. Breaking down the major deliverables of the project into smaller, manageable components B. Supporting detail C. Decomposition D. Improving the accuracy of time and cost estimates

0 Answers  


During the opening rounds of contract negotiation, the other party uses a fait accompli lactic. Which of the following is true? A. One party agrees to accept the offer of the other party but secretly knows they will bring the issue hack up at a later time. B. One party claims the issue under discussion was documented and accepted as part of Scope Verification. C. One party claims the issue under discussion has already been decided and can't be changed. D. One party claims to accept the offer of the other party provided a contract change request is submitted describing the offer in detail.

0 Answers  






Your team is split between two buildings on either side of town. As a result, the team isn't very cohesive because the members don't know each other very well. The team is still in the storming stage because of the separation issues. Which of the following should you consider? A. Corrective action B. Collocation C. Training D. Conflict resolution

0 Answers  


You are preparing a diagram that plots two variables, the dependent variable and the independent variable, to see the relationship between the two elements. What kind of diagram are you using? A. Cause-and-effect diagram B. Control chart C. Flowchart D. Scatter diagram

0 Answers  


You are the project manager for a new website for the local zoo. You need to perform Qualitative Risk Analysis. When you've completed this process, you'll produce all of the following outputs except: A. Overall risk ranking for the project B. List of prioritized risks C. Inputs to other processes D. List of risks for additional analysis and management

0 Answers  


All of the following are true regarding the tools and techniques of Activity Sequencing except: A. GERT uses analogous methods. B. GERT allows for loops. C. GERT is a conditional diagramming method. D. GERT allows for conditional branches.

0 Answers  


Your project got delayed by 40 days and you have to keep it back.what steps you would take.

4 Answers   Alstom, Wipro,


You are ready to perform the Activity Sequencing process for your project. To make your job easier, you're going to use a software tool to help you draw a PDM network diagram. Most software programs use this technique. You know all of the following are true regarding the PDM except: A. It shows the activities on arrows and connects them to dependencies usually depicted as circles. B. It’s also called AON. C. It shows the activities in boxes with arrows connecting the dependent activities. D. It uses four types of dependency relationships of which finish to start is one.

0 Answers  


You are the project manager for a large construction project. The project objective is to construct a set of outbuildings to house the Olympic support team that will be arriving in your city 18 months from the project start date. You've been given a budget of $12 million to complete this project. Resources are easily attained. Which of the triple constraints is the primary constraint for this project? A. Time, because the date cannot be moved B. Money, because the budget is set at $12 million C. Resources, because they're not fixed D. Quality, because the buildings have to be functional and safe

0 Answers  


Categories