Answer / neethu sebastian

Entry criteria for unit test
1.) All the requirement and documents are reviewed, finalized and approved.
2.) Application development should be completed
3.) Test environment is ready
4.) UnitTest Framework must be ready (in case of automated unit testing)
5.) Unit testing tools like Rational Software, JavaScript Assertion Unit, CUT, Dotunit ...etc (if tools are using) must be installed and configured.
(** last 2 points are optional hence can be avoided in interviews)

Exit criteria for Unit testing
1.) All the Unit test cases are executed.
2.) All the defects are resolved.
3.) coding is completed
4.) Code optimization (removal of redundant code, labeling of codes, removal of unused labels, removal of warning ..etc) is completed.

Entry criteria for integration testing
1.) Unit test exit criteria must meet
2.) Test environment should be ready
3.) Integration plan should be ready.
4.) Each module must gone through unit testing before the integration process.

Exit Criteria for Integration testing
1.) Successful execution of the integration tests.
2.) All priority bugs are resolve and closed.


Entry criteria for System testing
1.) Successful completion of integration testing process.
2.) Priority bugs found during integration testing must be fixed and closed.
3.) System testing environment must be available.
4.) Test cases must be available to execute

Exit Criteria for system testing
1.) Successful execution of the system tests.
2.) All specified business and functional requirements must be met.
3.) Priority bugs have been fixed and closed.
4.) Systems compatibility must be tested on various platforms

Entry Criteria for acceptance testing
1.) Successful completion of system testing phase.
2.) Priority bugs found during previous testing activities must be fixed and closed.
3.) Functional and Business requirement must be met.
4.) Acceptance testing environment should be ready.
5.) Test cases must be available.

Exit Criteria of Acceptance testing
1.) Successful execution of the user acceptance tests.
2.) approval for test Closure
3.)All Business requirements must be fulfilled.
4.) No critical defects are left out.

Is This Answer Correct ?    0 Yes 0 No

Post New Answer

More Manual Testing Interview Questions

What is 2-Tier and 3-Tier Architecture?

4 Answers  


Write the test cases for file transfer from one user to other from Google Drive/drop box?

0 Answers   IBM, PanTerra,


how can we test an application to know the expiration period (i.e,below or equal to expiry-date it shud work and above it shud fail). [assume this s/w app'n validity period is 2months]

3 Answers  


What is difference between system and functional testing?

6 Answers   BMC,


Hello. I am not here to answer your question. I jus found a job as software QA engr. And i am totally new to software testing. So can someone pls help me in the following scenario? there is this registration screen, and it contain: One textbox called Nickname which only accept alphanumerical One textbox called Contact which only accept numerical, One textbox called Email which can be filled with alphanumerical and symbol and One button called Register now becos there is so many textboxes, where i can filled with alphabet, number, symbol, "just space", leading zeros, leading space. there will be lots of combination. can someone pls help.. i will be appreciated if u can post the test case of the scenario i mentioned. Lots of Thanks

0 Answers  






why we develop Test plan for a project ?

4 Answers   Wipro,


I have 2 yrs 10 months experience in manual testing. there is a gap of 3 yrs in between. just 3 months before i rejoined the same company. I am looking for new & better job.What I have to enhance my career to up level, should I have to do Automation course or any other. Guide me properly.

0 Answers  


WHAT R THE TYPES OF TESTING U KNOW AND U EXPERIENCED?

5 Answers   Infosys,


Please send me Sample Template on Test Strategy. Tnx in Advance.

0 Answers  


exactly what is the purpose of configuration mgt tool? also give some examples?

8 Answers   Accenture,


explain statement coverage?

3 Answers   Wipro,


what is product backlog...

2 Answers   HCL, Wells Fargo,


Categories