Entry criteria for unit test
1.) All the requirement and documents are reviewed, finalized and approved.
2.) Application development should be completed
3.) Test environment is ready
4.) UnitTest Framework must be ready (in case of automated unit testing)
5.) Unit testing tools like Rational Software, JavaScript Assertion Unit, CUT, Dotunit ...etc (if tools are using) must be installed and configured.
(** last 2 points are optional hence can be avoided in interviews)
Exit criteria for Unit testing
1.) All the Unit test cases are executed.
2.) All the defects are resolved.
3.) coding is completed
4.) Code optimization (removal of redundant code, labeling of codes, removal of unused labels, removal of warning ..etc) is completed.
Entry criteria for integration testing
1.) Unit test exit criteria must meet
2.) Test environment should be ready
3.) Integration plan should be ready.
4.) Each module must gone through unit testing before the integration process.
Exit Criteria for Integration testing
1.) Successful execution of the integration tests.
2.) All priority bugs are resolve and closed.
Entry criteria for System testing
1.) Successful completion of integration testing process.
2.) Priority bugs found during integration testing must be fixed and closed.
3.) System testing environment must be available.
4.) Test cases must be available to execute
Exit Criteria for system testing
1.) Successful execution of the system tests.
2.) All specified business and functional requirements must be met.
3.) Priority bugs have been fixed and closed.
4.) Systems compatibility must be tested on various platforms
Entry Criteria for acceptance testing
1.) Successful completion of system testing phase.
2.) Priority bugs found during previous testing activities must be fixed and closed.
3.) Functional and Business requirement must be met.
4.) Acceptance testing environment should be ready.
5.) Test cases must be available.
Exit Criteria of Acceptance testing
1.) Successful execution of the user acceptance tests.
2.) approval for test Closure
3.)All Business requirements must be fulfilled.
4.) No critical defects are left out.
| Is This Answer Correct ? | 0 Yes | 0 No |
a apllication is given to you but the requirements and functionalities are missing what will you do to start the testing?
What did your base your test cases?
In manual testing, what are stubs and drivers?
How do you decide when you have 'tested enough?'
Why performance testing is performed? What are tools of performance testing?
When to do Black box testing?
waht is the quality in your company?
Difference between postponed and deferred bug
Why testing is importent in software?
Tell me the SRS based review,brs based review
why we go for winrunner ? and when we go for winrunner
What is system testing? What is defect leakage? What is penetration testing? What is regression testing?