Civil Engineering Interview Questions
Questions Answers Views Company eMail

Time required for curing of wall tiles before fixing

1754

how to do soil testing briefly with details

Deepak Enterprises,

3 5255

Is there the dry coefficient of cement is constant?

1822

Please let me know about answer for my Question as "What is the maximum wastage allowable of HYSD Steel in any Bridge project as per Code and Code reference also ?

Amit Enterprises, ICT,

1433

What is the cost of formwork for columns/beams/rcc walls also what is the cost of shuttering for roof slab at height of 25 feet

Tirupati Exim,

2069

As per IS 2502 2(A+B)+24d formula is given for stirrups detailing,but explination not given for how that 24d came

L&T,

1 5123

what is Quantity of stone and sand required for one cubic meter of stone work (UCR)

1637

How to make tiles floor step by step procedure?

AMS, Construction,

1481

How to improve the strength of fly ash bricks to avoid corner damge? How to get the color lighter similar to normal concrete blocks/

1350

How to avoid fly ash seed ball formations in the concrete mixer while mixing of raw materials for fly ash block manufacturing?

1436

what is the weight if 1m3 M25 concrete after setting?

1 2754

50m3 concrete volume how much cement sand aggregate details radio m20grade

L&T, Mars Planning Engineering Services, Relcon Infraprojects,

5 9604

how will remove spiderweb cracking in plaster ? what the reasone of make it ?

Bharat, JLV,

1496

1.0 what is the permissible westage of steel in structural steel fabrication say gantry , trustle of power plant unit 2.0 what is the permissible westage of cement in construction work as above

PMC,

3 3362

What is vertical dpc and where it is construct?

Kanwarji Construction,

1 3532


Post New Civil Engineering Questions

Un-Answered Questions { Civil Engineering }

manhole height is 1500 mm and width of brickwork is 230 mm dia of manhole covering is 560 mm brick masonry 1:4 horizontal length is 1500 mm and plaster 12 mm thick on both side 1:3. how to estimate the quantity of brickwork with mortar cement and sand for manhole chamber.

1642


i need the syllabus for the direcr recruitement of executive engineers in andhrapradesh

1830


How to calculate the area of a irregular sized land in square feet?and what will be the total area of this land South-51.1ft , North-47.7ft , East-53.3ft , West-54ft ?please explain me how to calculate?

1473


What out turn civil works

6340


Q 1) 1 Mason and 2 LABOUR / _________CUM brick work Q 2) 1 Mason and 1 LABOUR / _________SQ FT Plaster work Q 3) 1 Carpenter & 2 Labour/_________SQ FT shuttering work Q 4) 100 SQ FT roof slab concreting ____________mason and labour required

1531






How much cement and water required for cement selery????

1416


Providing ,Cutting, bending and positioning of TMT Bar with cost of binding wire

1140


can you please tell me what the current rate of construction material and different construction labourers charge in bangalore ???

1442


i have to give lap joint fo 1Mtr steel of dia12mm,whenever i did mistake i cut less 5cm plz tell me how much i will give lap joint so that length comes 1Mtr

1539


what is derating factor in cable? what does it mean if derating factor is high/low in terms of thermal resistivity of soil?

2090


How much cement will require for 1Rmt Skirting laying

1877


1)What is the total volume of aggregates required for 1cu.mtr.solid hard concrete? 2)What is total mass of wet concrte and dry concrete after 28 days of M25? 3) Is 28 days strength is the final strength of concrete or it gets increasing as the time period increses.? 4)What is the volumetric proportion of concrete grade of M25.M30,M35,M40

2248


What is the value of live load that should be incorporated in design of locker room and cash vault room while designing a building for commercial bank?

2224


what is the venturi effect in buildings? what is green house concept?different types of dams? which dam is economical arch dam or gravity dam. what are the conditions favourible to both of them?

2622


asubmerged weir is one in which the water level on the down stream side of the weir is just at the crest level below the crest level above the crest level at stamp elevation as water surface on upstream

1455