Project Management Interview Questions
Questions Answers Views Company eMail

You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any rime during the day. The project sponsor has promised you a bonus if you get this project completed two weeks sooner than the scheduled project end date. The bonus will come in handy on your trip to the Bahamas planned for later this spring. You've got a few remaining project activities to wrap up before you can close out the project. Which of the following is the most appropriate response? A. You tell the sponsor the project is complete and treat the remaining activities as though they're problems that came up after project closure so that you can still get the bonus. B. You tell the sponsor the remaining activities are outside the scope of the project so the project really is completed and collect your bonus. C. You tell the sponsor the stakeholders added these requirements after the project was well under way and you never agreed to include them in the project so the project really is complete, and you collect your bonus. D. You tell the sponsor you aren't going to make the two-week early completion date as there are remaining activities to finish up.

587

You've reached a stale of independence where you're able to express yourself and perform at your peak level of performance. Being the best you can be is the motivator that drives you. Which of the following is true? A. This is an example of the Expectancy theory. B. You've reached self-actualization in Maslow's Hierarchy. C. This is an example of the Hygiene theory. D. You've reached the highest level of the Achievement theory.

661

Intellectual property includes all of the following except: A. Software B. Patents C. Hardware D. Business processes

473

The project manager, stakeholders, and project team members all have roles and responsibilities throughout the project. As the project manager, you might link the project scope definition to the project roles and indicate which activities each person will participate in. You might display this information in which of the following ways: A. PDM B. RAM C. SOW D. RRM

499

During a recent team meeting, you reached a resolution to a problem that's been troubling the team for several weeks. You took responsibility for searching out the facts of this problem and uncovered the right answer to this problem. You presented the facts at the project status meeting, and everyone reached agreement on the recommended solution based on the facts you presented. This is an example of what type of conflict resolution technique? A. Compromise B. Smoothing C. Confrontation D. Forcing

847

You are a project manager for Capella Systems. Your company writes custom software for accounting and financial systems for medium- to large-sized corporations. Your recent project has experienced some setbacks, and you've been forced to rework the design of one of the programs because it doesn't match the customer's requirements. Since some parts of the program have already been written, it will have to be rewritten so that it matches the design changes. This rework has increased costs, and you're beginning to notice some signs of poor morale because of the rework. Which of the following is true? A. The problems occurred because the WBS was not constructed properly. B. The quality assurance plan was carried out correctly, which is how the design problems were discovered. C. The problems occurred as a result of poor scope definition. D. The Risk Management Planning process details these kinds of risks and the responses you should put into place should they occur.

554

You are a project manager for a network cabling project for your organization. Your project team is made up of six full-time employees and three contractors. This is the first time they have all worked together. This project requires accurate information exchange at all times during the life of the project. How many lines of communication exist among the project team members? A.36 B.41 C.18 D.34

563

You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any time during the day. You need to purchase an expensive piece of hardware as part of this project. One of the vendors bidding on the project is a close friend. In order to win the bid, she needs to know how much money the company is willing to spend on the equipment and consulting. Your friend asks you to give her this confidential information and not tell anyone you did. Which of the following is the most appropriate response? A. Tell your friend that as a PMP, you're required to abide by the Project Management Professional Code of Professional Conduct and this would violate the code as it's a conflict of interest. B. Tell your friend that as a PMP, you're required to abide by the Project Management Professional Code of Professional Conduct and this would violate the code as it’s a personal gain. C. Tell your friend that as a PMP, you're required to abide by the Project Management Professional Standards and Ethics Code and this would violate the code as it’s a conflict of interest. D. Tell your friend that as a PMP, you’re required to abide by the Project Management Professional Standards and Ethics Code and this would violate the code as it’s an ethics violation.

622

Which of the following describes a unique characteristic of the project Executing and Controlling processes? A. The core processes in the Executing and Controlling processes are from the Project Integration knowledge area from the Project Integration knowledge area. B. Both the Executing and Controlling processes measure variances in project performance and use corrective action to bring performance hack in line with the plan. C. Executing is an input to the Controlling processes, and Controlling is an input to Execution. D. Executing and controlling each have only one core process.

747

You are preparing a cash flow analysis for a project the company is considering undertaking. The project's cost is $525,000, and expected cash inflows are $125,000 the first year and then $75,000 per quarter the second year and $100,000 per quarter after that. What is the payback period? A. 16 months B. 27 months C. 32 months D. 28 months

615

You are going to lake some performance measurements for your current project. You know that PV = 450, AC = 500, and EV= 375. What is the CPI and SPI respectively? A. CPI = .90, and SPI = 1.2. B. CPI = .75, and SPI = .83. C. CPI = 1.2, and SPI = .90. D. CPI = .83, and SPI = .75.

571

All of the following are true regarding the Executing processes except: A. Executing has one core process. B. The majority of the project budget is spent here. C. The greatest conflicts are schedule conflicts. D. Project performance is measured to identify variances.

527

You are a project manager for a network cabling project for your organization. Your project team is made up of six full-time employees and three contractors. This is the first time they have all worked together. You know that the team will go through the stages of team development in the following order: A. Forming, storming, norming, and performing B. Storming, norming, forming, and performing C. Norming, storming, forming, and performing D. Forming, norming, storming, performing

523

All of the following are tools and techniques of the Quality Control process except: A. Monte Carlo Analysis B. Statistical sampling C. Pareto diagrams D. Trend analysis

523

You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. You do not expect these variances to continue, as they're atypical. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 25 B. 760 C. 775 D. 833

708


Post New Project Management Questions

Un-Answered Questions { Project Management }

Your project is progressing as planned. The project team has comp up with a demo that the sales team will use when making presentations to perspective clients. You will do which of the following at your next stakeholder process. A. Report on the progress of the demo and note that it's a completed task B. Preview the demo for stakeholders and obtain their approval and sign-off C. Review the technical documentation of the demo and obtain approval and sign-off D. Report that the demo has been noted as a completed task in the information retrieval system

592


Which of the following is true regarding the scope statement? A. It describes how to make changes to project scope. B. It describes project deliverables and serves as a baseline for future project decisions. C. It assesses the stability of the project scope and is a baseline for future project decisions. D. It assesses the reliability of the project scope and describes the frequency of changes and their impacts.

995


You are a project manager for Star Light Strings. Star Light manufactures strings of lights for outdoor display. Their products range from simple tight strings to elaborate lights with animal designs, bug designs, memorabilia, and so on. Your newest project requires a change. One of the business unit managers submitted a change through the change control system, which utilizes a CCB. Which of the following is true regarding the CCB? A. Describes how change requests are managed B. Requires all change requests in writing C. Approves or denies change requests D. Requires updates to the appropriate management plan

597


You have been hired as a contract project manger for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. One of the activities for this project is the installation and testing of several new servers. You know from past experience it takes about 16 hours per server to accomplish this task. Since you're installing 10 new servers, you estimate this activity to take 160 hours. Which of the estimating techniques have you used? A. Analogous estimating B. Bottom-up estimating C. Quantitatively based duration D. Reserve time

518


The purpose of the Initiation process is to: A. Formally recognize the existence of a project or project phase B. Formally recognize the need that brought about the project be it marketing demand, customer requests, business need, technological advances, or legal requirements C. Formally recognize the stakeholders of the project and identify them in the project charter D. Formally recognize the project sponsor and document his or her project goals

656






What is the process in the Executing process group that determines if the project satisfies quality standards, identifies lessons learned, and review quality management activities to verify the correct quality elements are being examined? A. Quality Control B. Quality Monitoring and Control C. Quality Assurance D. Scope Verification

568


How do you communicate bad news in your team?

515


You are the project manager for a new website for the local zoo. You need to perform Qualitative Risk Analysis. When you've completed this process, you'll produce all of the following outputs except: A. Overall risk ranking for the project B. List of prioritized risks C. Inputs to other processes D. List of risks for additional analysis and management

651


These diagrams rank order factors for corrective action by frequency of occurrence. They are also a type of histogram: A. Control charts B. Process flowcharts C. Scatter diagrams D. Pareto diagrams

714


You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail store for the option of opening two new stores in a foreign country. You have been invited to dinner with the prospective foreign business partners and their spouses upon your arrival. You know that all of the following are generally true except: A. You should spend time building relationships with your prospective foreign business partners before getting down to business. B. You should explain your company's rules, standards, and operating policies at your first meeting with the prospective foreign business partners. C. You should build an atmosphere of mutual trust and cooperation. D. You should respect the cultural differences you'll encounter when working with your prospective foreign business partners.

609


As a PMP, you will be required to comply with the Project Management Professional Code of Professional Conduct. Part of your responsibility concerns applying professional knowledge. All of the following are part of applying professional knowledge except: A. Developing relationships based on mutual respect B. Staying abreast of project management practices C. Keeping up with industry trends and new technology D. Honestly reporting your project management experience

528


You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 778 B. 780 C. 861 D. 833

771


What are the outputs of the Performance Reporting process? A. Performance reports and change requests B. Performance reports and other project records C. Change requests and performance reporting D. Change requests and performance measurements

561


You are a project manager for Laurel’s theater productions. Your new project is coming in over budget and requires a cost change through the cost change control system. The cost variance was projected using which of the following tools and techniques? A. Performance measurements B. Cost baseline measurements C. Computerized tools D. Performance reports

585


What are the 10 knowledge areas of project management?

464