You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any rime during the day. The project sponsor has promised you a bonus if you get this project completed two weeks sooner than the scheduled project end date. The bonus will come in handy on your trip to the Bahamas planned for later this spring. You've got a few remaining project activities to wrap up before you can close out the project. Which of the following is the most appropriate response? A. You tell the sponsor the project is complete and treat the remaining activities as though they're problems that came up after project closure so that you can still get the bonus. B. You tell the sponsor the remaining activities are outside the scope of the project so the project really is completed and collect your bonus. C. You tell the sponsor the stakeholders added these requirements after the project was well under way and you never agreed to include them in the project so the project really is complete, and you collect your bonus. D. You tell the sponsor you aren't going to make the two-week early completion date as there are remaining activities to finish up.
1050You've reached a stale of independence where you're able to express yourself and perform at your peak level of performance. Being the best you can be is the motivator that drives you. Which of the following is true? A. This is an example of the Expectancy theory. B. You've reached self-actualization in Maslow's Hierarchy. C. This is an example of the Hygiene theory. D. You've reached the highest level of the Achievement theory.
1218Intellectual property includes all of the following except: A. Software B. Patents C. Hardware D. Business processes
891The project manager, stakeholders, and project team members all have roles and responsibilities throughout the project. As the project manager, you might link the project scope definition to the project roles and indicate which activities each person will participate in. You might display this information in which of the following ways: A. PDM B. RAM C. SOW D. RRM
911During a recent team meeting, you reached a resolution to a problem that's been troubling the team for several weeks. You took responsibility for searching out the facts of this problem and uncovered the right answer to this problem. You presented the facts at the project status meeting, and everyone reached agreement on the recommended solution based on the facts you presented. This is an example of what type of conflict resolution technique? A. Compromise B. Smoothing C. Confrontation D. Forcing
1558You are a project manager for Capella Systems. Your company writes custom software for accounting and financial systems for medium- to large-sized corporations. Your recent project has experienced some setbacks, and you've been forced to rework the design of one of the programs because it doesn't match the customer's requirements. Since some parts of the program have already been written, it will have to be rewritten so that it matches the design changes. This rework has increased costs, and you're beginning to notice some signs of poor morale because of the rework. Which of the following is true? A. The problems occurred because the WBS was not constructed properly. B. The quality assurance plan was carried out correctly, which is how the design problems were discovered. C. The problems occurred as a result of poor scope definition. D. The Risk Management Planning process details these kinds of risks and the responses you should put into place should they occur.
991You are a project manager for a network cabling project for your organization. Your project team is made up of six full-time employees and three contractors. This is the first time they have all worked together. This project requires accurate information exchange at all times during the life of the project. How many lines of communication exist among the project team members? A.36 B.41 C.18 D.34
1027You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any time during the day. You need to purchase an expensive piece of hardware as part of this project. One of the vendors bidding on the project is a close friend. In order to win the bid, she needs to know how much money the company is willing to spend on the equipment and consulting. Your friend asks you to give her this confidential information and not tell anyone you did. Which of the following is the most appropriate response? A. Tell your friend that as a PMP, you're required to abide by the Project Management Professional Code of Professional Conduct and this would violate the code as it's a conflict of interest. B. Tell your friend that as a PMP, you're required to abide by the Project Management Professional Code of Professional Conduct and this would violate the code as it’s a personal gain. C. Tell your friend that as a PMP, you're required to abide by the Project Management Professional Standards and Ethics Code and this would violate the code as it’s a conflict of interest. D. Tell your friend that as a PMP, you’re required to abide by the Project Management Professional Standards and Ethics Code and this would violate the code as it’s an ethics violation.
1100Which of the following describes a unique characteristic of the project Executing and Controlling processes? A. The core processes in the Executing and Controlling processes are from the Project Integration knowledge area from the Project Integration knowledge area. B. Both the Executing and Controlling processes measure variances in project performance and use corrective action to bring performance hack in line with the plan. C. Executing is an input to the Controlling processes, and Controlling is an input to Execution. D. Executing and controlling each have only one core process.
1216You are preparing a cash flow analysis for a project the company is considering undertaking. The project's cost is $525,000, and expected cash inflows are $125,000 the first year and then $75,000 per quarter the second year and $100,000 per quarter after that. What is the payback period? A. 16 months B. 27 months C. 32 months D. 28 months
1015You are going to lake some performance measurements for your current project. You know that PV = 450, AC = 500, and EV= 375. What is the CPI and SPI respectively? A. CPI = .90, and SPI = 1.2. B. CPI = .75, and SPI = .83. C. CPI = 1.2, and SPI = .90. D. CPI = .83, and SPI = .75.
976All of the following are true regarding the Executing processes except: A. Executing has one core process. B. The majority of the project budget is spent here. C. The greatest conflicts are schedule conflicts. D. Project performance is measured to identify variances.
969You are a project manager for a network cabling project for your organization. Your project team is made up of six full-time employees and three contractors. This is the first time they have all worked together. You know that the team will go through the stages of team development in the following order: A. Forming, storming, norming, and performing B. Storming, norming, forming, and performing C. Norming, storming, forming, and performing D. Forming, norming, storming, performing
952All of the following are tools and techniques of the Quality Control process except: A. Monte Carlo Analysis B. Statistical sampling C. Pareto diagrams D. Trend analysis
957You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. You do not expect these variances to continue, as they're atypical. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 25 B. 760 C. 775 D. 833
1110Post New Project Management Questions
All of the following are true regarding the ADM method except: A. It's a tool and technique of Activity Sequencing. B. It uses one time estimate to determine durations. C. It's also called AOA. D. It's rarely used today.
You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization’s operating system on 236 servers. You performed this project under contract. You are in the Closing process and know that product verification is for what purpose? A. To verify the goals of the project and assure the product of the project is complete B. To evaluate all the work of the project and compare results to project scope C. To verify all the work was completed correctly and satisfactorily D. To evaluate project goals and assure the product of the project meets the requirements
Change control system, configuration management, performance measurement, additional planning, and project management information system are tools and techniques of which process? A. Integrated Change Control B. Scope Change Control C. Schedule change control D. Cost change control
You are the project manager for Heartthrobs by the Numbers Dating Services. You're working on an updated Internet site that will display pictures as well as short bios of prospective heartbreakers. You've just completed your project staff assignments and published the project team directory. Which process are you in? A. Resource Planning B. Organizational Planning C. Project Development Planning D. Staff Acquisition
You are the project manager for a software consulting firm that is working on developing a new software program for a customer in another country. Things seem to be progressing well. Recently, your stakeholders examined the work of the project and formally accepted the work results. Which process was just performed? A. Scope Verification B. Quality Assurance C. Performance Reporting D. Quality Control
All of the following are inputs to the Administrative Closure process except: A. Performance measurement documentation B. Product documentation C. Other project records D. Contract documents
You are the project manager for a large construction project. The project objective is to construct a set of outbuildings to house the Olympic support team that will be arriving in your city 18 months from the project start date. Resources are not readily available as they are currently assigned to other projects. Jack, an expert crane operator, is needed for this project two months from today. Which of the following skills will you use to get Jack assigned to your project? A. Negotiation and influencing skills B. Communication and organizational skills C. Communication skills D. Problem-solving skills
You are developing your project schedule and have decided to use the PERT method to determine project duration. The estimates you've gathered so far include the following: Most likely is 200 hours, optimistic is 180 hours, and pessimistic is 220 hours. Which of the following is the correct PERT estimate? A. 190 B. 266 C. 200 D. 210
You are a project manager with technical expertise in the pharmaceutical industry. You've decided to try your hand at project management in the entertainment industry. Which of the following is true? A. You will likely be successful because communication skills are your strong suit. You anticipate having technical experts on your project team to address industry specifics that you're not familiar with. B. You will likely be successful because your organizational skills are excellent. You anticipate having technical experts on your project team to address industry specifics that you're not familiar with. C. You will probably be successful because you have a friend in the entertainment industry that has briefed you on all the important aspects of this project that you'll need to know. You anticipate having technical experts on your project team to address industry specifics that you're not familiar with. D. You will probably not be successful because you have little knowledge of the entertainment industry even though you anticipate having technical experts on your project team to address industry specifics that you're not familiar with.
As a PMP, you will be required to comply with the Project Management Professional Code of Professional Conduct. Part of your responsibility concerns applying professional knowledge. All of the following are part of applying professional knowledge except: A. Developing relationships based on mutual respect B. Staying abreast of project management practices C. Keeping up with industry trends and new technology D. Honestly reporting your project management experience
Describe size oriented metrics.
You are a project manager for Safari Outfitters. Your company is going to offer a new product line in the upcoming spring catalog. Your project team has 10 months to secure contracts with suppliers, finalize the designs, get the product into the catalog, and stock the warehouse. This is an example of: A. An assumption because the project team has worked on projects like this before and know they can meet the 10-month deadline B. An assumption because the project team has a limited amount of time to complete the project C. A constraint because the project team has a limited amount of time to complete the project D. A constraint because the project team is working with a new product line that hasn't been developed before
You are managing a project to install a new postage software system that will automatically print labels and administer postage for certified mailings, overnight packages, and other special mailing needs. You've attempted to gain the cooperation of the business analyst working on this project and need some answers. She is elusive and tells you that this project is not her top priority. To avoid situations like this in the future, you should: A. Establish the business analyst's duties well ahead of due dates and tell her you'll be reporting on her performance to her functional manager. B. Establish the business analyst's duties well ahead of due dates and tell her you are expecting her to meet these expectations because the customer is counting on the project meeting due dates to save significant costs on their annual mailings. C. Negotiate with the business analyst's functional manager during the planning process to establish expectations and request to participate in the business analyst's annual performance review. D. Negotiate with the business analyst's functional manager during the planning process to establish expectations and inform the functional manager of the requirements of the project. Agreement from the functional manager will assure the cooperation of the business analyst.
Each of the following describes an element of the Scope Definition process except: A. Breaking down the major deliverables of the project into smaller, manageable components B. Supporting detail C. Decomposition D. Improving the accuracy of time and cost estimates
Write about organising and staffing in management.