Project Management Interview Questions
Questions Answers Views Company eMail

Many times software delivery is late, why? Give reason.

529

Describe capability maturity model (cmm).

513

How will you measure software quality?

509

How do you handle change request?

531

What are the different types of software risks?

498

What are the framework activities and umbrella activities?

530

Describe the 4 p’s in software project management.

464

What are the csfs in the software project management ?

480

How do you start a project plan?

532

What is raid in project management?

525

How do you ensure that your project is always on track?

482

What is the difference between risk impact and risk probability?

465

What are the functions of project management tool?

476

How do you manage team performance?

480

How do you set goals for your team?

463


Post New Project Management Questions

Un-Answered Questions { Project Management }

Your project team is a close group all busily working on project activities. They're close to approaching the performing stage of Team Development. All six members must communicate frequently with each other. How many lines of communication are there? A. 12 B. 15 C. 18 D. 14

550


What is the concept of project management?

494


You are a project manager for Cinema Snicker Productions. Your company specializes in producing comedy films for the big screen. Your latest project has just been completed and accepted. You've been given your next project, which starts right away. Which of the following is true? A. This project ended due to extinction because it was completed and accepted. B. This project ended due to integration because it was completed and accepted and the project manager moved on to a new project. C. This project ended due to addition because it was completed and accepted and archived into the company's catalog of available films. D. This project ended due to integration because it was completed and accepted.

703


The project charter: A. Includes a product description, describes the business need of the project, and is published by the project manager B. Includes a product description, describes the business need of the project, and is published by the project sponsor C. Includes the contract when the project is performed by a vendor and is published by a manager external to the project D. Includes a product description, describes the business need of the project, and is published by a manager external to the project

477


During the opening rounds of contract negotiation, the other party uses a fait accompli lactic. Which of the following is true? A. One party agrees to accept the offer of the other party but secretly knows they will bring the issue hack up at a later time. B. One party claims the issue under discussion was documented and accepted as part of Scope Verification. C. One party claims the issue under discussion has already been decided and can't be changed. D. One party claims to accept the offer of the other party provided a contract change request is submitted describing the offer in detail.

513






what is software project planning?

497


All of the following strategies are tools and techniques of Risk Response Planning used to reduce or control risk except? A. Mitigation B. Simulation C. Avoidance D. Acceptance

528


If your expected value is ll0 and the standard deviation is l2, which of the following is true? A. There is approximately a 99 percent chance of completing this activity between 86 and 134 days. B. There is approximately a 68 percent chance of completing this activity between 98 and 122 days. C. There is approximately a 95 percent chance of completing this activity between 98 and 122 days. D. There is approximately a 75 percent chance of completing this activity between 86 and 134 days.

524


Why do you want to switch over from IT to management?

487


Which of the following contracts should you use for projects that have a degree of uncertainty and require a large investment early in the project life cycle? A. Fixed price B. Cost reimbursable C. Lump sum D. Unit price

905


You are a project manager for a manufacturing firm that produces Civil War-era replicas and memorabilia. You discover a design error during a test production run on your latest project. Which of the following is the most likely response to this problem? A. Reduce the technical requirements so that the error is no longer valid. B. Go forward with production and ignore the error. C. Go forward with production but inform the customer of the problem. D. Develop alternative solutions to address the error.

669


You are the project manager for your company's annual Spring Fling. You've made all the plans and reserved the outdoor grounds for the appropriate day and time. You are now two days away from the big day, and the forecast is calling for light rain showers in the afternoon. You rented tents just in case this risk occurred. This is an example of which Risk Response Planning tool and technique? A. Passive acceptance B. Contingency planning C. Avoidance D. Transference

497


According to the Guide to the PMBOK, the project manager is identified and assigned during which process? A. As an input to the Initiation process B. As an input to the Planning process C. As an output of the Initiation process D. As an output of the Scope Planning process

803


You are the newly appointed project manager for a pharmaceutical company. Your company has asked you to head up a project to research a new children's medication. You've identified the lab equipment you'll need, the software needed to perform analysis and measurements, and the skill level and types of the technicians and researchers for this project. Which of the following is true? A. The project manager and resources have been identified as part of the outputs of the Initiation process, and this information can be found in the project charter. B. The resources and project manager have been identified as an input to the project Initiation phase. Further information is needed to produce the project charter, which will include the resources and project manager. C. The project manager and resources have been identified as part of the project selection process. The selection committee requires resource information to make a final decision. D. The resources and project manager have been identified as part of the project selection process. The selection committee requires resource information to make a final decision.

673


What are the different project scheduling techniques?

520