Project Management Interview Questions
Questions Answers Views Company eMail

The project schedule is used to determine all of the following except: A. Cost estimates B. Activity start dates C. Float times D. Activity end dates

1212

You are a project manager for Picture Shades, Inc. They manufacture window shades for hotel chains that have replicas of Renaissance-era paintings on the inside of the shades. Picture Shades is taking their product to the home market, and you're managing the new project. They will offer their products at retail stores as well as on their website. You're developing the project schedule for this undertaking and have determined the critical path. Which of the following is true? A. You calculated the most likely start date and most likely finish dates, float time, and weighted average estimates. B. You calculated the activity dependency, and the optimistic and pessimistic activity duration estimates. C. You calculated the early and late start dates, early and late finish dates, and float times for all activities. D. You calculated the optimistic, pessimistic, and most likely duration times and the float times for all activities.

1043

Which of the following is true regarding the critical path? A. It should never be compressed. B. It allows for looping and branching. C. The critical path technique is the same as PERT. D. It's the duration of all tasks with zero float.

621

All of the following are tools and techniques of the Schedule Development process except? A. CPM B. RAM C. GERT D. PERT

524

You are a project manager for a new software development project. You have a few activities that require specialized testing. The testing might need to be repeated more than once. Which of the following do you choose? A. The Graphical Evaluation and Review Technique because it allows for conditional branching and looping for the testing activity B. The Critical Path Method because it allows for float time to be calculated for the testing activity C. The Program Evaluation and Review Technique because it allows for conditional branching and looping for the testing activity D. The Program Evaluation and Review Technique because it allows for a weighted average distribution, which will even out the time needed for the testing activity

466

You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the expected value, or weighted average? A. 54 B. 66 C. 60 D. 30

704

You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the standard deviation? A. 22 B. 20 C. 2 D. 4

804

If you know expected value is 500 and the standard deviation is 12, you can say with approximately a 95 percent confidence rating which of the following? A. The activity will take between 488 and 512 days. B. The activity will take between 464 and 536 days. C. The activity will take between 494 and 506 days. D. The activity will take between 476 and 524 days.

515

If your expected value is ll0 and the standard deviation is l2, which of the following is true? A. There is approximately a 99 percent chance of completing this activity between 86 and 134 days. B. There is approximately a 68 percent chance of completing this activity between 98 and 122 days. C. There is approximately a 95 percent chance of completing this activity between 98 and 122 days. D. There is approximately a 75 percent chance of completing this activity between 86 and 134 days.

541

You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D department has agreed to release two resources to work on your project in order to meet the federal grant application date. This is an example of: A. Crashing B. Fast trucking C. Resource leveling D. Adjusting the resource calendar

651

You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. You adjust the schedule and find that two activities previously scheduled to start sequentially can be started at the same time. This is an example of: A. Crashing B. Fast tracking C. Resource leveling D. Adjusting the resource calendar

769

You are the project manager for Rivera Gourmet Adventure Vacations. Rivera combines the wonderful tastes of great gourmet food with outdoor adventure activities. Your project involves installing a new human resources software system. Jason, the database analyst working on this project, is over allocated. Which of the following is true? A. You should use resource requirements updates to determine availability and smooth out resource over allocation. B. You should use crashing to resource level the critical path tasks. C. You should use resource leveling heuristics to smooth out resource assignments. D. You should use fast tracking to resource level the critical path tasks.

1 1954

What is one of the problems with project management software? A. The project manager manages the software instead of the project B. Project duration calculations are sometimes approximate. C. You cannot override the project management software decisions regarding schedules. D. It’s expensive and difficult to use.

595

Obtaining formal project plan approval and sign-off is important for all of the following reasons except: A. Stakeholders are able to recommend a project Planning methodology to follow throughout the remaining process groups. B. Stakeholders are aware of the project details, which make them more likely to participate in future project decisions. C. Stakeholders will be more likely to cooperate. D. Stakeholders are aware of the specific details regarding project schedules, budgets, and risks.

876

Which of the following are the tools and techniques of the Cost Budgeting process? A. Project management information system, analogous estimating, bottom-up estimating, mathematical analysis B. Analogous estimating, bottom-up estimating, mathematical analysis, computerized tools C. Project management software, analogous estimating, bottom-up estimating, parametric modeling D. Analogous estimating, bottom-up estimating, parametric modeling, computerized tools

510


Post New Project Management Questions

Un-Answered Questions { Project Management }

Your company has asked you to be the project manager for the product introduction of their new DeskTop Rock media system. You recently published a document that establishes the scope baseline. Which of the following is true? A. This is the scope statement, which is an output of the Scope Planning process. B. This is the scope statement, which is an output of the Scope Definition process. C. This is the scope statement, which is a tool and technique of the Scope Definition process. D. This is the scope management plan, which is an output of the Scope Definition process.

584


Your project team is a close group all busily working on project activities. They're close to approaching the performing stage of Team Development. All six members must communicate frequently with each other. How many lines of communication are there? A. 12 B. 15 C. 18 D. 14

560


You are the project manager for Lucky Stars nightclubs. They specialize in live country and western band performances. Your newest project is in the Planning process. You are working on the WBS. The finance manager has given you a numbering system to assign to the WBS. Which of the following is true? A. The numbering system is a unique identifier known as the code of accounts, which is used to track the costs of the WBS elements. B. The numbering system is a unique identifier known as the WBS dictionary, which is used to track the descriptions of individual work elements. C. The numbering system is a unique identifier known as the code of accounts, which is used to track time and resource assignments for individual work elements. D. The numbering system is a unique identifier known as the WBS dictionary, which is used to assign quality control codes to the individual work elements. ?

507


As a project manager, you know that the most important activity to ensure customer and stakeholder satisfaction is which of the following: A. Documenting the requirements B. Documenting the performance measurements C. Reporting changes and updating the project plan and other project documents where appropriate D. Reporting project status timely and regularly

582


Write about organising and staffing in management.

536






The tools and techniques of the Source Selection process include all of the following except: A. Contract negotiation B. Correspondence C. Independent estimates D. Screening system

495


You have accumulated project information throughout the project and need to distribute some important information you just received. All of the following are part of information distribution methods except; A. Electronic mail B. Videoconferencing C. Electronic databases D. Voice mail

665


You are the newly appointed project manager for a pharmaceutical company. Your company has asked you to head up a project to research a new children's medication. You've identified the lab equipment you'll need, the software needed to perform analysis and measurements, and the skill level and types of the technicians and researchers for this project. Which of the following is true? A. The project manager and resources have been identified as part of the outputs of the Initiation process, and this information can be found in the project charter. B. The resources and project manager have been identified as an input to the project Initiation phase. Further information is needed to produce the project charter, which will include the resources and project manager. C. The project manager and resources have been identified as part of the project selection process. The selection committee requires resource information to make a final decision. D. The resources and project manager have been identified as part of the project selection process. The selection committee requires resource information to make a final decision.

685


Integrity in the project management field is accomplished through all of the following except: A. Training to learn how to manage relationships with others from different cultures B. Adhering to an ethical code C. Applying established project management processes D. Following the Project Management Professional Code of Professional Conduct

536


Which logical relationship does the PDM use most often? A. Start to finish B. Start to start C. Finish to finish D. Finish to start

887


Which of the following is true regarding constraints and assumptions? A. Constraints restrict the actions of the project team, and assumptions are considered true for planning purposes. B. Constraints are considered true for planning purposes, and assumptions limit the options of the project team. C. Constraints consider vendor availability and resource availability to be true for planning purposes. Assumptions limit the project teamwork within predefined budgets or time lines. D. Constraints and assumptions are inputs to the Initiation process. They should be documented, as they will be used throughout the project Planning process.

763


You are the project manager for a cable service provider. Your project team is researching a new service offering. They have been working together for quite some time and are in the performing stage of Team Development. This stage of Team Development is similar to which of the following? A. Smoothing B. Achievement theory C. Hygiene theory D. Self-actualization

554


What are decision models? A. Project selection criteria B. Project selection methods C. Project selection committees D. Project resource and budget selection criteria

512


What change would you like to bring in the management of your previous organization ?

533


What are the outputs of the Team Development process? A. Performance improvements, input to performance appraisals B. Input to performance appraisals, reward and recognition systems C. Performance improvements, input to performance appraisals, performance reports D. Work results, input to performance appraisals, performance reports

552