how costing is done in pp or how u will know the cost of a
product which is manufactured in ur plant
Answers were Sorted based on User's Feedback
Answer / vicente pires
In discrete scenario (with production orders) all movements
to order (like raw materials consuption and activities
posting) are valuated and recorded in each order when
confirmations ocurrs, increasing the cost balance of order.
when material is posted to stock, the order balance is
decreased by the value of the material.
After order is finished remaining diferences in the order´s
balance is posted to liquidation rule of the order, usually
the order´s material acount, valuating the stocks.
In Repetitive scenario the process is almost the same, just
changing the cost object from order to cost colector. In
that case you can´t evaluate costs by orders, just by
periods.
Is This Answer Correct ? | 21 Yes | 2 No |
Answer / nanduri k. prasad
There are different methods of doing product cost estimate.
e.g., Std. cost estimate or variable cost estimate.
From the BOM and routing the total no of components used
for that product is calculated using the price mentioned in
accouting views and from routings each operation cost is
calculated from the activity types defined in workcenters.
Collectively this cost is displayed in Product cost
estimate as cost of manufacture in the T.code CK 11n.
In case of variable cost, all the variables are considered
for the production order and the actuals are considered for
calculating the product cost. It is also posible to have
cost estimates and actual costs from which we can find the
variances.
Is This Answer Correct ? | 16 Yes | 0 No |
Answer / rashmi kant
Ist we estimate the material in t-code CK11N
THEN we do costing of the product in CK24
T-code CK4ON can be used for group costing.
Is This Answer Correct ? | 3 Yes | 0 No |
What are the three 'mrp procedures'?
Tell me important of the Production scheduling profile what are the things have to maintain in this profile
What are the production process in sap?
What are different MRP types?
What is planning file entry and Where can we use
What is the transaction code to run MRP for sales order?
Can we create a production order without BOM and Routing?
What is 'work center' in sap pp?
what do you mean by planning time fence
What is gap
What is a 'product hierarchy'?
why their is need of production version