Can it be configured in such a way that the external
requisitions can also be taken into account while MRP runs
in consumption-based planning if VB is selected as MRP type?
Answers were Sorted based on User's Feedback
Answer / vivek
Step 1 : Go to MRP1 screen view
Step 2 : Select MRP Type as ' VB' ( Automatic reorder point planning)
Step 3 : Go to Tcode : MD02 (MRP - Single Item - Multilevel)
Step 4 : Enter material number or name, Select MRP Area by hitting right button, now you can see the automatic MRP Type came as 'VB' along with MRP Area, MRP Plant. and enter.
Thanks
Is This Answer Correct ? | 3 Yes | 0 No |
yes, reorder point will be set for ATP(available to promise)
quantities
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / shriya
Yes you can do it based on the MRP2 tab for materila master
oyu need to given you MRP type as VB and in Mrp2 set
automatic reorder point tab . Now run MD02 and MD04
Is This Answer Correct ? | 1 Yes | 1 No |
What are some of the data points provided by purchasing for a material?
Can you explain how to use IDOC/EDI processes in purchasing like PO and in what context
What are the configuration are client specific in mm ?
3 Answers Accenture, Dishnet, Neco,
Explain release strategy
What is a reference purchase organization? When can it be used?
whats is difference between info record and source list
Anyone knows the good faculty for SAP MM In pune?
What all different type of master available in MM Module?
What does "structure" mean in SAP? Also, what does "enhancement category" mean in SAP?
In material master do you know any basic tables?
"only 0.000 pieces are available" what does it mean during goods issue??
What is the significance of Qty/Value update check box (e.g. by valueation area) in Material Type configuration?