Can it be configured in such a way that the external
requisitions can also be taken into account while MRP runs
in consumption-based planning if VB is selected as MRP type?
Answer Posted / vivek
Step 1 : Go to MRP1 screen view
Step 2 : Select MRP Type as ' VB' ( Automatic reorder point planning)
Step 3 : Go to Tcode : MD02 (MRP - Single Item - Multilevel)
Step 4 : Enter material number or name, Select MRP Area by hitting right button, now you can see the automatic MRP Type came as 'VB' along with MRP Area, MRP Plant. and enter.
Thanks
Is This Answer Correct ? | 3 Yes | 0 No |
Post New Answer View All Answers
What is special about one time vendor?
What information is maintained in accounting view of material master?
What do you mean by subcontracting?
Explain lot sizing
What is a business area?
How do we create a client in the mm module?
Explain the types of consignement stocks in sap mm
Explain the basic 'organizational structure' in mm?
What is purpose of purchase value key in material master?
How will you map subcontracting process for project stock?
How can we see the consignment stocks in sap?
What is the use of ‘info update’ indicator in purchasing documents?
Name some of the data points provided by purchasing for the materials.
What is an rfq and how is it different from the quotation form?
Which documents are used as references when we create po?