Can it be configured in such a way that the external
requisitions can also be taken into account while MRP runs
in consumption-based planning if VB is selected as MRP type?

Answer Posted / vivek

Step 1 : Go to MRP1 screen view

Step 2 : Select MRP Type as ' VB' ( Automatic reorder point planning)

Step 3 : Go to Tcode : MD02 (MRP - Single Item - Multilevel)

Step 4 : Enter material number or name, Select MRP Area by hitting right button, now you can see the automatic MRP Type came as 'VB' along with MRP Area, MRP Plant. and enter.

Thanks

Is This Answer Correct ?    3 Yes 0 No



Post New Answer       View All Answers


Please Help Members By Posting Answers For Below Questions

What is special about one time vendor?

679


What information is maintained in accounting view of material master?

740


What do you mean by subcontracting?

632


Explain lot sizing

676


What is a business area?

731






How do we create a client in the mm module?

695


Explain the types of consignement stocks in sap mm

661


Explain the basic 'organizational structure' in mm?

613


What is purpose of purchase value key in material master?

664


How will you map subcontracting process for project stock?

690


How can we see the consignment stocks in sap?

636


What is the use of ‘info update’ indicator in purchasing documents?

651


Name some of the data points provided by purchasing for the materials.

666


What is an rfq and how is it different from the quotation form?

686


Which documents are used as references when we create po?

658