1. Five steps of implementation with full details.
Answer / devarshi shukla
ASAP stands for Accelerated SAP.
Its purpose is to help design SAP implementation in the most efficient manner possible. Its goal is to effectively optimize time, people, quality and other resources, using a proven methodology to implementation.
The Five Phases of Implementation as under:
Phase 1 Project Preparation
Phase 2 Business Blueprint
Phase 3 Realization
Phase 4 Final Preparation
Phase 5 Go-Live and support
Phase-1 initiates with a retrieval of information and resources. It is an important time to assemble the necessary components for the implementation. Some important milestones that need to be accomplished for phase 1 include
- Obtaining senior-level management/stakeholder support
- Identifying clear project objectives
- Architect an efficient decision-making process
- Creating an environment suitable for change and re-engineering
- Building a qualified and capable project team.
Phase 2- Business Blueprint
SAP has defined a business blueprint phase to help extract pertinent information about your company that is necessary for implementation. These blueprints are in the form of questionnaires that are designed to probe for information that uncovers how your company does business. As such, they also serve to document the implementation.
Each business blueprint document essentially outlines your future business processes and business requirements. The kinds of questions asked are germane to the particular business function, as seen in the following sample questions:
1) What information do you capture on a purchase order?
2) What information is required to complete a purchase order?
Phase- 3 - Realization
With the completion of the business in phase 2, "functional" experts are now ready to begin configuring SAP.
The Realization phase is broken in to two parts.
1) Your SAP consulting team helps you configure your baseline system, called the baseline configuration.
2) Your implementation project team fine-tunes that system to meet all your business and process requirements as part of the fine tuning configuration.
The initial configuration completed during the base line configuration is based on the information that you provided in your blueprint document. The remaining approximately 20% of your configuration that was not tackled during the baseline configuration is completed during the fine tuning configuration.
Fine tuning usually deals with the exceptions that are not covered in baseline configuration. This final bit of tweaking represents the work necessary to fit your special needs.
Configuration Testing-
With the help of your SAP consulting team, you segregate your business processes into cycles of related business flows. The cycles serve as independent units that enable you to test specific parts of the business process. You can also work through configuring the SAP implementation guide (IMG). A tool used to assist you in configuring your SAP system in a step by step manner.
Knowledge Transfer-
As the configuration phase comes to a close, it becomes necessary for the Project team to be self-sufficient in their knowledge of the configuration of your SAP system.Knowledge transfer to the configuration team tasked with system maintenance (that is, maintenance of the business processes after Go-live) needs to be completed at this time. In addition, the end users tasked with actually using the system for day-to-day business purposes must be trained.
Phase 4 - Final Preparation
As phase 3 merges into phase 4, you should find yourselves not only in the midst of SAP training, but also in the midst of rigorous functional and stress testing.Phase 4 also concentrates on the fine tuning of your configuration before Go-live and more importantly, the migration of data from your old system or systems to SAP.
Workload testing (including peak volume, daily load, and other forms of stress testing), and integration or functional testing are conducted to ensure the accuracy of your data and the stability of your SAP system. Because you should have begun testing back in phase 2, you do not have too far to go until Go-live.
Now is an important time to perform preventative maintenance checks to ensure optimal performance at your SAP system. At the conclusion of phase 4, take time to plan and document a Go-live strategy. Preparation for Go-live means preparing for your end-users questions as they start actively working on the new SAP system.
Phase 5 - Go-live and Support
The Go-live milestone is itself is easy to achieve; a smooth and uneventful Go-live is another matter altogether. Preparation is the key, including attention to what-if scenarios related not only to the individual business processes deployed but also to the functioning of technology underpinning these business processes and preparation for ongoing support, including maintenance contracts and documented processes and procedures are essential.
Is This Answer Correct ? | 1 Yes | 0 No |
What is the most difficult Ticket you faced in Support Project till date? In many interviews I have been asked this question. How to answer/ handle this question? They are asking/ insisting for most difficult & typical tickets and asking about my analysis and how I resolved that ticket? If you have any difficult tickets which can be easily explainable in an interview then provide me 2-3 Typical & Difficult tickets relevant to SD Module. This is a crucial question in any interview as it is deciding the fate of the candidate success or failure in any interview. If we are telling some simple tickets they are asking for most difficult ones and they are not satisfied with such easy tickets. So, I request you to provide me with 2-4 crucial & most difficult tickets so that I can answer well this question the next time I face Interview-------Thankx
1 Answers Accenture, IBM, iGate,
customer hierarchy in sap sd for account determination
What are the challenges you faced in your previous implementation project?
What are the two user exits you have used in your project?
How you identified whether this order is make to order or maket to stock in Order Level ?
5 Answers Tieto Software Technologies,
A customer ordered 100 qnt. of material A but company have only 50 nos., customer wants it immediately and company ordered rest 50 nos. to a vendor. There should be single sales order and customer wants a single invoice. How to solve this scenario.
Maintaining sales organization (tvko)?
when i try to release the document to G/L account using vf02 by clicking flag getting error msg : account 800000 requires an assignment to CO object, pls guide me detail step by step process to resolve this issue
1. In the Invoice output, there will be for example: 4 line address for the customer in the SAP standard functionality. If your client asks for 6 line address in the output, how you guide ur ABAPer to carryout this?
In a sales order processing, Condition records is already maintained but still that particular Condition Type does not shown in P.procedures in a sales order. Now what have to do in this situation . plz reply anyone ( IBM Interview) . **SUCHIT**
what is retro active billing?who is will create this?
Define the customer taxes in ovk3, you will maintain the tax code in customer master.