Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


How to estimate the cost of projects ?

Answers were Sorted based on User's Feedback



How to estimate the cost of projects ?..

Answer / akki

There are various methods of estimates. Ex. Function point,
creating work break down structure and estimating for each
work packages in it.
There can be predefined/ready estimation tool with your
organization based on similar project learning experience.
Using such methods cost for each deliverable/mile stone can
be estimated. Overall estimation for each mile stone is cost
budget for your project.

Is This Answer Correct ?    8 Yes 3 No

How to estimate the cost of projects ?..

Answer / c. nagaraju

First we need to check clients requirement. How he need it?
When he needs it? Whether he needs it in low budget or In a
high budget? One thing we have to keep in mind that, the
Quality Control need to be maintained as much as possible.
If we give clients a good service, they will prefer to give
more projects. We should not expect more profit and giving
him a bad service/quality. Keep a reasonable margin and
give "THE BEST SERVICE" from your end.

regards
C. NAGARAJU
Nagarabhavi

Is This Answer Correct ?    6 Yes 4 No

How to estimate the cost of projects ?..

Answer / svs gopinath

1. Create the WBS of the project.
2. Assign TeamMember for each Task
3. Prepare the schedule of the Project.
4. Calculate the Effort based on the schedule & Number of
Team members

For example:

Project Shedule is 2 Month with 2 Team Member( Considering
8 Hrs per day)

That Means Effort is 4 Manmonths

Assume that Per Hour cost is 20$
One day cost per resource is 8 * 20 = 160$
One day Cost for two resources are 165*2 = 320$


Number of Working days in one Month is 22 days.
Number of Working days in 2 Months are 2* 22 = 44 days.

Add 4 Hours of Project Management that means Number of
days for project Management is 22 Days.

Total Number of days = 44+22 = 66 days

The Total Poroject Cost = 66 *320$ = 21120$

( Note: I have Assumed cost per hour is 20$ for Project
Management Also. This cost may be diferent

I have Considered this Project executed @ offOsore
Onsite Cost will be more.

If the project is executed in ofshore/Onsite model , cost
will be diferent)

)

Is This Answer Correct ?    4 Yes 3 No

Post New Answer

More Project Planning Interview Questions

Write a function that inserts an integer into a linked list in ascending order. Write the test cases for this function.

0 Answers   Microsoft,


What are the different inputs and outputs of the phases in SDLC ?

7 Answers   Apple, Honeywell,


What are the different phases in Software life cycle

6 Answers  


Q1. A. How can we determine performance standards? B. Write note on chaining views. Q2. A. Discuss the working with task in Gantt chart view. B. Explain the creation project schedule. Q3. A. What is understand in resource tracking? B. Write short notes on Caturing Baseline. Q4. A. How to customize workgroup message? B. How to use hyperlink? Q5. A. Explain the installation of project server? B. Discuss the working with to-do lists. Q6. A. Explain the working of templates? B. What is visual basic? C. Write shortnotes on user forms.

0 Answers  


How will gather requirements and where do you record. Is it in word / Excel or do you have any tool for that ?

3 Answers   Microsoft,


funds flows analysis how to prepare for interview

0 Answers   Mphasis,


You have 3 jars. Each jar has a label on it: white, black, or white&black. You have 3 sets of marbles: white, black, and white&black. One set is stored in one jar. The labels on the jars are guaranteed to be incorrect (i.e. white will not contain white). Which jar would you choose from to give you the best chances of identifying the which set of marbles in is in which jar?

12 Answers   Intel, Microsoft,


About current project architecture ?

2 Answers   ADP, Microsoft,


Why analysis and testing phases are very important ?

2 Answers   AGR, Infosys,


What procedures do you follow to arrive at the project schedule?

3 Answers  


What are the different phases of SDLC ?

94 Answers   College School Exams Tests, Geometric Software, Infosys, Microsoft, NIIT, Samyak, Sun Microsystems, TCS,


When you come in to the office, how do you know what you have to do during the day?

0 Answers   ABC,


Categories