How do we prepare weekly and monthly status-report as QA?
Answers were Sorted based on User's Feedback
Answer / rahul
Weekly Status Reports:
Overall activities Status RED/AMBER/GREEN
1. Title
2. Activities Planned this week:
3. Activities Completed this week:
- Sr. No
- Description
- Planned Start Date
- Actual Start Date
- Planned End Date
- Actual End Date
- % Compled
- Status
4. Activities in Progress
- Sr. No
- Description
- Planned Start Date
- Actual Start Date
- Planned End Date
- Actual End Date
- % Compled
- Status
5.Activities planned next week:
6. Defect Matrix
- No of defects
i) New
ii) Open
iii) Closed
iv) Deferred
v) Rejected
7. Risks and Issues if any
Monthly Status report is a high level report
Overall activities Status RED/AMBER/GREEN
1. Activities Planned
2. Activities Completed
3. Activities In Progress
4. Activities Planned Next
5. Risks and Issues
Is This Answer Correct ? | 23 Yes | 6 No |
Answer / srikumaran
Do you have any calculation for defects? Defect per
day/Total no. of defect in a week???
Is This Answer Correct ? | 4 Yes | 0 No |
Answer / sasi
hi rahul
can explain with example it is useful to me........pls
thnks
Is This Answer Correct ? | 2 Yes | 4 No |
Test summary report detail
can we test the product with out documents?
what is the velue of, 'x'?
can any one help me? What is the Trecebility matrix ? what is that use and when it use and where it use
what type of testing process is going on your company?
8 Answers Accenture, CTS, ISPG, Ordain Solutions,
Test Documents Reporting answers
Hello friends.. Can anybody here explain me or provides me notes of these topics in detail with interview questions... Topics are:- History of Software Engineering Waterfall Model Prototype Model Spiral Model Software Quality Testing Software Development Life Cycle Software Testing Life Cycle white box testing methodology black box grey box Definition of Quality,Quality Assurance,Quality Control Verification and Validation Static Testing Dynamic Testing only on my gmail mca.rachna21@gmail.com
if there are 10 step in test cases while executing if their is mismatch at step 5 what is status of test case ? pass or fail or anything else? if require tab is not available then what's the status of test case?
how will you report defects in your company?
what type of documents needed in every phase of sdlc for SQA?
What are the contents of Test Plan?
what are the fields in Bug Report