Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


The Project Human Resource Management knowledge area contains which of the following processes?
A. Staff Acquisition, Team Development, and Resource Planning
B. Staff Acquisition, Team Development, and Performance Reporting
C. Organizational Planning, Staff Acquisition, and Team Development
D. Organization Planning, Team Development, and Resource Planning


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

You are the project manager for an outdoor concert event scheduled for 1 year from today. You're working on the procurement plan for the computer software program that will control the lighting and screen projections during the concert. You've decided to contract with a professional services company that specializes in writing custom software programs. You want to minimize the risk to the organization, so you'll option for which contract type? A. Fixed price plus incentive B. Cost plus fixed fee C. Fixed price D. Cost plus incentive

0 Answers  


Critical path tasks are those tasks that: A. Have equal pessimistic, optimistic, and most likely estimated times B. Have a float rime of zero C. Have the same start date D. Have multiple early start dates and early finish dates

0 Answers  


You are a project manager for Dutch Harbor Consulting. Your latest project involved the upgrade of an organization’s operating system on 236 servers. You performed this project under contract. You are in the Closing process and know that product verification is for what purpose? A. To verify the goals of the project and assure the product of the project is complete B. To evaluate all the work of the project and compare results to project scope C. To verify all the work was completed correctly and satisfactorily D. To evaluate project goals and assure the product of the project meets the requirements

0 Answers  


You are the project manager for a cable service provider. Your team members are amiable with each other and are careful to make project decisions jointly. Which of the following is true? A. They are in the smoothing stage of Team Development. B. They are in the norming stage of Team Development. C. They are in the forming stage of Team Development. D. They are in the forcing stage of Team Development.

0 Answers  


You are going to lake some performance measurements for your current project. You know that PV = 450, AC = 500, and EV= 375. What is the CPI and SPI respectively? A. CPI = .90, and SPI = 1.2. B. CPI = .75, and SPI = .83. C. CPI = 1.2, and SPI = .90. D. CPI = .83, and SPI = .75.

0 Answers  


What is the difference between contingency and mitigation plan?

1 Answers  


The primary function of the Closing process is to: A. Formalize lessons learned and distribute this information to project participants B. Perform audits to verify the project results against the project requirements C. Formalize project completion and disseminate this information to project participants D. Perform post-implementation audits to document project successes and failures

0 Answers  


What are the Scope Planning process tools and techniques? A. Benefit/cost analysis, work breakdown structure templates, expert judgment, and supporting detail B. Product analysis, benefit/cost analysis, alternatives identification, and expert judgment C. Product analysis, work breakdown structure templates, supporting detail, and expert judgment D. Benefit/cost analysis, alternatives identification, supporting detail, and expert judgment

0 Answers  


The product description, strategic plan, project selection criteria, and historical information are considered: A. Inputs to the project Planning process B. Inputs to the project Overview process C. Inputs to the project Initiation process D. Inputs to the project Execution process

0 Answers  


Scope definition is necessary for all of the following reasons except: A. To subdivide project deliverables into smaller components B. To assess the stability of the project scope C. To facilitate time and cost estimates D. To facilitate responsibility and assignment

0 Answers  


Your company manufactures small kitchen appliances. They are introducing a new product line of appliances in designer colors with distinctive features for kitchens in small spaces. These new products will be offered indefinitely starting with the spring catalog release. In order to determine the characteristics and features of the new product line, you will have to perform which of the following? A. Fast tracking B. Consulting with the stakeholders C. Planning the project life cycle D. Progressive elaboration

0 Answers  


The Critical Path Method is a mathematical tool and technique of the Schedule Development process. All of the following are true regarding CPM except: A. Determines a single early and late start date and a single early and late finish date B. Calculates expected value C. Focuses on the calculation of float time D. Shows the critical path, or the path with the longest duration