When reviewing a system development project an IS auditor
would be PRIMARILY concerned with whether:

A. business objectives are achieved.

B. security and control procedures are adequate.

C. the system utilizes the strategic technical infrastructure.

D. development will comply with the approved quality
management processes



When reviewing a system development project an IS auditor would be PRIMARILY concerned with whether..

Answer / guest

Answer: A

The most important issue in reviewing system development
processes to ensure that business objectives are achieved. A
software development project should meet its objectives.
Security and control procedures are to be considered as a
subset of business objectives, because a well-controlled
system that does not meet business needs is of little
benefit to the organization.

Is This Answer Correct ?    1 Yes 0 No

Post New Answer

More CISA Certification Interview Questions

When developing a risk management program, the FIRST activity to be performed is a/an: A. threats assessment. B. classification of data. C. inventory of assets. D. criticality analysis.

1 Answers  


Which of the following would be included in an IS strategic plan?

7 Answers   Deloitte,


During a post-implementation review of an enterprise resource management system, an IS auditor would MOST likely: A. review access control configuration. B. evaluate interface testing. C. review detailed design documentation. D. evaluate system testing.

2 Answers  


The BEST time to perform a control self-assessment involving line management, line staff and the audit department is at the time of: A. compliance testing. B. the preliminary survey. C. substantive testing. D. the preparation of the audit report.

1 Answers  


Which of the following BEST describes the necessary documentation for an enterprise product reengineering (EPR) software installation? A. Specific developments only B. Business requirements only C. All phases of the installation must be documented D. No need to develop a customer specific documentation

2 Answers  


Which of the following BEST describes an integrated test facility? A. A technique that enables the IS auditor to test a computer application for the purpose of verifying correct processing B. The utilization of hardware and/or software to review and test the functioning of a computer system C. A method of using special programming options to permit printout of the path through a computer program taken to process a specific transaction D. A procedure for tagging and extending transactions and master records that are used by an IS auditor for tests

1 Answers  


Which of the following controls will detect MOST effectively the presence of bursts of errors in network transmissions? A. Parity check B. Echo check C. Block sum check D. Cyclic redundancy check

3 Answers  


A company performs full backup of data and programs on a regular basis. The primary purpose of this practice is to: A. maintain data integrity in the applications. B. restore application processing after a disruption. C. prevent unauthorized changes to programs and data. D. ensure recovery of data processing in case of a disaster.

2 Answers  


An audit charter should: A. be dynamic and change often to coincide with the changing nature of technology and the audit profession. B. clearly state audit objectives for the delegation of authority for the maintenance and review of internal controls. C. document the audit procedures designed to achieve the planned audit objectives. D. outline the overall authority, scope and responsibilities of the audit function.

2 Answers  


The MOST significant level of effort for business continuity planning (BCP) generally is required during the: A. testing stage. B. evaluation stage. C. maintenance stage. D. early stages of planning.

2 Answers  


A number of system failures are occurring when corrections to previously detected errors are resubmitted for acceptance testing. This would indicate that the maintenance team is probably not adequately performing which of the following types of testing? A. Unit testing B. Integration testing C. Design walk-throughs D. Configuration management

1 Answers  


Which of the following would an IS auditor consider the MOST relevant to short-term planning for the IS department? A. Allocating resources B. Keeping current with technology advances C. Conducting control self-assessment D. Evaluating hardware needs

1 Answers  


Categories
  • Cisco Certifications Interview Questions Cisco Certifications (2321)
  • Microsoft Certifications Interview Questions Microsoft Certifications (171)
  • Sun Certifications Interview Questions Sun Certifications (45)
  • CISA Certification Interview Questions CISA Certification (744)
  • Oracle Certifications Interview Questions Oracle Certifications (64)
  • ISTQB Certification Interview Questions ISTQB Certification (109)
  • Certifications AllOther Interview Questions Certifications AllOther (295)