Thirty men take 20 days to complete a job working 9 hours a
day.How many hour a day should 40 men work to complete the
job? (a) 8 hrs (b) 7 1/2 hrs (c) 7 hrs (d) 9 hrs

Answers were Sorted based on User's Feedback



Thirty men take 20 days to complete a job working 9 hours a day.How many hour a day should 40 men ..

Answer / komal

the answer is <c>
i go with aneesh's answer but (45*3)/20=6.75=7(app)

Is This Answer Correct ?    27 Yes 5 No

Thirty men take 20 days to complete a job working 9 hours a day.How many hour a day should 40 men ..

Answer / aneesh

ans : (b)
30 mem in 180hrs in 20 days
efficiency of each person is 1/180*30
efficiency of 40 mem is 40/180*30 = 1/45*3
no.of hrs per day = 45*3/20 = 7.22 hrs (app)

Is This Answer Correct ?    30 Yes 15 No

Thirty men take 20 days to complete a job working 9 hours a day.How many hour a day should 40 men ..

Answer / suraj sharma

b)7 1/2 hrs

Is This Answer Correct ?    30 Yes 16 No

Thirty men take 20 days to complete a job working 9 hours a day.How many hour a day should 40 men ..

Answer / nimo

i believe that 30 men ---20days
9 hr/day

40 men--- 20 days
x hr/day

there fore 30*9 = 40*x
x= 6.75 which is more like 6 hrs 75 mins
which is not applicable , therefore
its 7 hrs 15 mins ( 7 1/2 app ) to
be in the safe side.

Is This Answer Correct ?    9 Yes 4 No

Thirty men take 20 days to complete a job working 9 hours a day.How many hour a day should 40 men ..

Answer / kunal

The solutions given , comes out to be 6.75 and not 7 or 7.22...Check it out and help with me out with the right solution..

Is This Answer Correct ?    4 Yes 1 No

Thirty men take 20 days to complete a job working 9 hours a day.How many hour a day should 40 men ..

Answer / mr h

Forty men should still work 9 hours a day until the jobs
finished, thats obviously the length of their shift.

Is This Answer Correct ?    2 Yes 2 No

Thirty men take 20 days to complete a job working 9 hours a day.How many hour a day should 40 men ..

Answer / prachi

6.75

Is This Answer Correct ?    3 Yes 3 No

Thirty men take 20 days to complete a job working 9 hours a day.How many hour a day should 40 men ..

Answer / iswariya

7 1/2 hrs

Is This Answer Correct ?    9 Yes 14 No

Thirty men take 20 days to complete a job working 9 hours a day.How many hour a day should 40 men ..

Answer / guest

b 7 1/2hrs

Is This Answer Correct ?    1 Yes 6 No

Thirty men take 20 days to complete a job working 9 hours a day.How many hour a day should 40 men ..

Answer / mathiazhagan

B) 7 1/2 hrs

Is This Answer Correct ?    5 Yes 11 No

Post New Answer

More General Aptitude Interview Questions

If on an item a shop gives 25% discount, they earn 25% profit. If they now give 10% discount then what is the profit percentage.

10 Answers  


if the area of sqare increases by 69% then side of the sqr incr by

5 Answers   Verifone,


in which state does bay of bengal exist

2 Answers   IBM,


How many triangles are there in the following figure?

2 Answers   CAT, EA Electronic Arts, Oriental Bank Of Commerce,


pls send general aptitude previous question papers for my email id

0 Answers  






sir , i hv done 85 correct question in ssc cgl-tier-i 2010 after checking through my source which is correct , tell me whether i m eleigible for tier-ii or not charan , jalandhar

0 Answers  


Seema's weight is 25% of Sunita's weight and 40% of Tanisha's weight. What percentage of Tanisha's weight is Sunita's weight?

0 Answers   Cap Gemini,


Direction for Qn 1-8 Ans A using I only Ans B using II only Ans C using both I and II Ans D not solvable 1. Raman and Gaurav Brought eggs from a vendor. How many eggs were bought by each of them i. Raman bought half as many as Gaurav ii. The dealer had a stock of 500 eggs at the beginning of day 2. What is the age of Ramprakash? i. Ramprakash was born when his father was 26 yrs old ii. Ramprakash's mothers age is 3yrs less than his father's 3. How much time is reqd for downloading the software? i. The Data transfer rate is 6 kbps ii. The size of the software is 4.5 megabytes 4. Sanjay and Vijay started their journey from Mumbai to Pune. Who reached Pune first? i. Sanjay overtakes two times Vijay and Vijay overtakes Sanjay two times ii. Sanjay started first 5. Is the GDP of country X higher than Country Y? i. GDP's of X and Y has been increasing at a compounded annual growth rate of 5% and 6% over he past 5 yrs ii. 5 yrs ago GDP of X was 1.2 times Y 6. A boat can ferry 1500 passengers across a river in 12 hrs. How many round trips does it make during the journey? i. The boat can carry 400 passengers at a time ii. During its journey, the boat takes 40 mins time each way and 20 mins waiting time at each end. 7. What are the values of m and n? i. n is an even integer, m is odd integer and m is greater than n. ii. The product of m and n is 30 8. How much is the weight of 20 mangoes and 30 oranges? i. 1 orange weighs twice that of 1 mango ii. 2 mangoes and 3 oranges weigh 2 kg

0 Answers  


what are the things to be studied for the post of Executive trainee in Hindustan Latex Ltd.?

0 Answers  


A queen had 3 rings in a jewel box. She had 3 daughter's and one day the king said that the queen should give one ring to each of her daughter's and she should also keep a ring in that jewel box . The queen did what the king said. How is this possible ?

3 Answers  


15 men take 21 days of 8 hrs. each to do a piece of work. How many days of 6 hrs. each would it take for 21 women if 3 women do as much work as 2 men?

0 Answers   Mu Sigma,


What number should be added to or subtracted from each term of the ratio 17 : 24 so that it becomes equal to 1 : 2.

0 Answers   Accenture,


Categories