Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

Project Management Interview Questions
Questions Answers Views Company eMail

You are the project manager for Changing Tides video games. You have gathered the inputs for the Activity Duration Estimating process. You will employ which tools and techniques to produce the outputs for this process? A. Activity list, analogous estimating, quantitatively based durations, and alternatives identification B. Activity list, analogous estimating, expert judgment, and quantitatively based durations C. Expert judgment, analogous estimating, quantitatively based durations, and reserve time D. Expert judgment, alternatives identification, quantitatively based durations, and reserve time

1161

As project manager, you know that all of the following are true concerning analogous estimating techniques except: A. It's a qualitatively based estimating technique. B. It's a top-down estimating technique. C. It's a tool and technique of Activity Duration Estimating and Cost Estimating. D. It’s a form of expert judgment.

1184

You have been hired as a contract project manager for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. Customers must pre-register before being allowed to order wine over the Internet so that legal age can be established. You tested using data from Grapevine's existing database. This new module cannot be tested until the data from the existing system is loaded. This is an example of which of the following? A. Preferential logic B. Soft logic C. Discretionary dependency D. Hard logic

1102

You have been hired as a contract project manger for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. One of the activities for this project is the installation and testing of several new servers. You know from past experience it takes about 16 hours per server to accomplish this task. Since you're installing 10 new servers, you estimate this activity to take 160 hours. Which of the estimating techniques have you used? A. Analogous estimating B. Bottom-up estimating C. Quantitatively based duration D. Reserve time

932

Your project sponsor has requested a cost estimate for the project. She would like the cost estimate to be as accurate as possible as this might be her one and only chance to secure the budget for this project due to recent cuts in special projects. You decide: A. To use analogous estimating techniques B. To use bottom-up estimating techniques C. To use top-down estimating techniques D. To use expert judgment techniques

1047

Your project sponsor has requested a cost estimate for the project you're working on. This project is similar in scope to a project you worked on last year. She would like to get the cost estimates as soon as possible. Accuracy is not her primary concern right now. She needs a ball park figure by tomorrow. You decide to use: A. Analogous estimating techniques B. Bottom-up estimating techniques C. Parametric modeling techniques D. Computerized modeling techniques

1022

All of the following are true regarding parametric modeling except: A. It's a form of top-down estimating. B. It's a mathematical model. C. It's a tool used to estimate project costs. D. It's a tool used to estimate project time.

1024

Your project's primary constraint is quality. In order to make certain the project team members don't feel too pressed for time and to avoid schedule risk, you decide to use which of the following activity estimating tools? A. Expert judgment B. Quantitatively based durations C. Reserve time D. Analogous estimating

950

You are the project manager for BB Tops, a nationwide toy store chain. You are working on estimates for your latest project and have gathered several variables for your model. You've determined the following: A. Parametric modeling is a top-down technique that uses variables to produce time estimates. B. Parametric modeling is a mathematical formula that uses variables to produce cost estimates. C. Contingency estimating is a top-down technique that uses variables to produce cost estimates. D. Contingency estimating is a mathematical model that uses variables to produce time estimates.

948

Which logical relationship does the PDM use most often? A. Start to finish B. Start to start C. Finish to finish D. Finish to start

1513

What are the Quality Planning process outputs? A. Quality management plan, bench marking, checklists, evaluation criteria B. Quality management plan, bench marking, operational definitions C. Quality management plan, checklists, inputs to other processes D. Quality management plan, operational definitions, checklists, inputs to other processes

967

Three people are responsible for establishing cost of quality theories. Crosby and Juran are two of them, and their theories respectively are: A. Grades of quality, fitness for use B. Fitness for use, zero defects C. Zero defects, fitness for use D. Cost of quality, zero defects

950

The theory that 85 percent of the cost of quality is a management problem is attributed to: A. Doming B. Kaizen C. Juran D. Crosby

1477

All of the following are benefits of meeting quality requirements except: A. An increase in stakeholder satisfaction B. Less rework C. Low turnover D. Higher productivity

1316

You are a project manager for Fountain of Youth Spring Water bottlers. You are installing a new accounting system and have identified several problems and their causes. You decide to use which of the following flowcharts to diagram the problems' causes and effects? A. Decision tree diagram B. Fishbone diagram C. Benchmark diagram D. Simulation tree diagram

1116


Post New Project Management Questions

Un-Answered Questions { Project Management }

You are the project manager for the Late Night Smooth Jazz Club chain, with stores in 12 states. Smooth Jazz is considering opening a new club in Kansas City or Spokane. You have derived the following information: Project Kansas City: The payback period is 27 months, and the IRR is 35 percent. Project Spokane: The payback period is 25 months, and the IRR is 32 percent. Which project should you recommend to the selection committee? A. Project Spokane because the payback period is shortest B. Project Kansas City because the IRR is highest C. Project Spokane because the IRR is lowest D. Project Kansas City because the payback period is longest ?

1054


Your team is split between two buildings on either side of town. As a result, the team isn't very cohesive because the members don't know each other very well. The team is still in the storming stage because of the separation issues. Which of the following should you consider? A. Corrective action B. Collocation C. Training D. Conflict resolution

1239


Which organization has set the de facto standards for project management techniques? A. PMBOK B. PMO C. PMI D. PMA

1689


All of the following are tools and techniques of the Performance Reporting process except: A. Variance analysis B. Performance reporting C. Information distribution D. Performance reviews

1220


Your procurement department has obtained independent estimates. The vendor's proposal is substantially different than the independent estimates. All of the following are true except: A. The SOW was not detailed enough. B. The vendor failed to respond according to the terms of the proposal. C. The vendor failed to respond to all items in the SOW. D. The vendor failed to respond to all items in the contract.

1058


You are managing a project to install a new postage software system that will automatically print labels and administer postage for certified mailings, overnight packages, and other special mailing needs. You've attempted to gain the cooperation of the business analyst working on this project and need some answers. She is elusive and tells you that this project is not her top priority. To avoid situations like this in the future, you should: A. Establish the business analyst's duties well ahead of due dates and tell her you'll be reporting on her performance to her functional manager. B. Establish the business analyst's duties well ahead of due dates and tell her you are expecting her to meet these expectations because the customer is counting on the project meeting due dates to save significant costs on their annual mailings. C. Negotiate with the business analyst's functional manager during the planning process to establish expectations and request to participate in the business analyst's annual performance review. D. Negotiate with the business analyst's functional manager during the planning process to establish expectations and inform the functional manager of the requirements of the project. Agreement from the functional manager will assure the cooperation of the business analyst.

1875


Halloween is approaching fast. Your market research shows that the little yellow chicks and pink bunny marshmallow candies are the best-selling candy at Easter time, outselling all other types of candies. This prompts the company to introduce a new version of marshmallow candies with Halloween themes this season. Which of the following is true? A. This project came about due to customer request, and the primary constraint is time B. This project came about due to market demand, and the primary constraint is time. C. This project came about due to market demand, and the primary constraint is quality. D. This project came about due to customer request, and the primary constraint is quality.

1050


You are a project manager for an international marketing firm. You are ready to assign resources to your new project using a work authorization system. All of the following are true except: A. Work authorization systems clarify and initiate the work for each work package. B. Work authorization systems are written procedures defined by the organization. C. Work authorization systems are tools and techniques of the Project Plan Execution process. D. Work authorization systems are an output of the Project Plan Execution process.

1042


You are the project manager for a top-secret software project for an agency of the United States Government. Your mission, should you choose to accept it, is to complete the project using internal resources. The reason is because getting top secret clearances for contractors takes quite a bit of time and waiting for clearances would jeopardize the implementation date. Your programmers are 80 percent of the way through the programming and testing work when your agency appoints a new executive director. Your programmer’s are siphoned off this project to work on the executive director's hot new project. Which of the following addresses the purpose of Scope Verification in this case? A. It determines the correctness and completion of all the work B. It documents the level and degree of completion C. It determines if the project results comply with quality standards D. It documents the correctness of the work according to stakeholders' expectations

1222


The theory that 85 percent of the cost of quality is a management problem is attributed to: A. Doming B. Kaizen C. Juran D. Crosby

1477


You are the project manager for Design Your Web Site, Inc. Your company is designing the website for a national grocery score chain. You have your activity list in hand and are ready to diagram the activity dependencies using the PD technique. You know that: A. PDM uses AON diagramming methods. B. PDM uses AOA diagramming methods. C. PDM uses ADM diagramming methods. D. PDM uses PDM diagramming methods.

990


You are a project manager for Laurel’s theater productions. Your new project is coming in over budget and requires a cost change through the cost change control system. The cost variance was projected using which of the following tools and techniques? A. Performance measurements B. Cost baseline measurements C. Computerized tools D. Performance reports

1061


You are the project manager for Heartthrobs by the Numbers Dating Services. You’re working on an updated Internet site that will display pictures as well as short bios of prospective heartbreakers. You have your activity list and resource requirements in hand and are planning on using qualitatively based durations and reserve time to determine activity durations. Which of the following is true? A. You are using inputs of the Activity Duration Estimating process. B. You are using tools and techniques of the Cost Estimating process. C. You are using tools and techniques of the Activity Duration Estimating process. D. You are using inputs of the Cost Estimating process.

1001


Your nonprofit organization is preparing to host its first annual 5K run/walk in City Park. You worked on a similar project for the organization two years ago when it co-hosted the 10K run through Overland Pass. Which of the Initiation process inputs might be helpful to you on your new project? A. The strategic plan, because you'll want to make sure the project reflects the overall strategic direction of the organization. B. Historical information on the 10K run project. You might be able to gather helpful project information since this new project is similar in nature. C. The product description, which would describe all the details of the run/walk program. D. Historical information from the recent blood drive project.

1290


Describe the risk in software engineering.

911