Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...

Project Management Interview Questions
Questions Answers Views Company eMail

You are the project manager for Insomniacs International. Since you don't sleep much, you get a lot of project work done. You're considering recommending a project that costs $575,000, and expected inflows are $25,000 per quarter for the first 2 years, and then $75,000 per quarter thereafter. What is the payback period? A. 40 months B. 38 months C. 39 months D. 41 months

1077

Which of the following is true regarding IRR? A. IRR assumes reinvestment at the cost of capital. B. IRR is the discount rate when NPV is greater than zero. C. IRR is a constrained optimization method. D. IRR is the discount rate when NPV is equal to zero. ?

1105

Mathematical models using linear, dynamic, integer, or algorithm models are considered: A. Project selection criteria B. A form of expert judgment C. Project selection methods D. A form of historical information

2388

You are the newly appointed project manager for a pharmaceutical company. Your company has asked you to head up a project to research a new children's medication. You've identified the lab equipment you'll need, the software needed to perform analysis and measurements, and the skill level and types of the technicians and researchers for this project. Which of the following is true? A. The project manager and resources have been identified as part of the outputs of the Initiation process, and this information can be found in the project charter. B. The resources and project manager have been identified as an input to the project Initiation phase. Further information is needed to produce the project charter, which will include the resources and project manager. C. The project manager and resources have been identified as part of the project selection process. The selection committee requires resource information to make a final decision. D. The resources and project manager have been identified as part of the project selection process. The selection committee requires resource information to make a final decision.

1119

Your selection committee meets on a semiannual basis. They've determined that projects must meet or exceed a specific profit limit in order to be accepted and prioritized on the project list. Which of the following is true? A. The selection committee has defined project selection criteria, which is a tool and technique of Initiation. B. The selection committee has defined project selection methods, which is a tool and technique of Initiation. C. The selection committee has defined project selection methods, which is an input to Initiation. D. The selection committee has defined project selection criteria, which is an input to Initiation.

1044

What are the Initiation process outputs? A. Project charter, historical information, and project manager identification and assignment B. Project charter, project manager identification and assignment, constraints, and assumptions C. Project charter, historical information, constraints, and assumptions D. Project charter, constraints, and assumptions

1040

Ruby is an administrative assistant with another department. Her manager has agreed to loan Ruby's services to you on a part-time basis during your current project. Ruby is putting together the cost projections you've gathered so far. You want to include these costs in the project charter. Ruby is formatting this information for you into a spreadsheet package and is printing copies. Which of the following is true? A. All of the costs, including Ruby's time, are charged to the project. B. All of the costs, Ruby is typing into the spreadsheet are project costs. Ruby's time is not directly related to the project and should not be included. C. The project costs, including Ruby's time, should be included in the project charter. D. The project costs, excluding Ruby's time, should be considered project constraints.

980

Your project selection committee used a weighted scoring model and found that Project B, with a score of 54, should be chosen over the other competing projects. Which of the following is true? A. Weighted scoring models are a benefit measurement method, which is a tool and technique in the Initiation process. B. Weighted scoring models are a constrained optimization method, which is an output of the Initiation process. C. Weighted scoring models are a constrained optimization method, which is a tool and technique in the Initiation process. D. Weighted scoring models are a benefit measurement method, which is an output of the Initiation process.

1081

Your selection committee is debating between two projects. Project A has a payback period of 18 months. Project B has a cost of $125,000 with expected cash inflows of $50,000 the first year and $25,000 per quarter after that. Which project should you recommend? A. Either Project A or Project B because the payback periods are equal B. Project A because Project B's payback period is 21 months C. Project A because Project B's payback period is 24 months D. Project A because Project B's payback period is 20 months

1199

Which of the following is true? A. Discounted cash flow analysis is the least precise of the cash flow techniques as it does not consider the time value of money. B. NPV is the least precise of the cash flow analysis techniques as it assumes reinvestment at the discount rate. C. Payback period is the least precise of the cash flow analysis techniques as it does not consider the time value of money. D. IRR is the least precise of the cash flow analysis techniques because it assumes reinvestment at the cost of capital.

923

Project selection criteria might include: A. Benefit measurement methods B. Constrained optimization analysis C. NPV calculations D. Potential market share or increased public perception

938

You are a project manager for Zippy Tees. Your selection committee has just chosen a project you recommended for implementation. Your project is to manufacture a line of miniature stuffed bears that will be attached to your company's trendy T-shirts. The bears will be wearing the same T-shirt design as the shirt they're attached to. Your project sponsor thinks you've really impressed the big boss and wants you to skip to the manufacturing process right away. What is your response? A. To agree with the project sponsor because they are your boss, and they have a lot of authority and power in the company. B. To require that a preliminary budget be established and a resource list be put together to alert other managers of the requirements of this project. This should be published and signed by the other managers who are impacted by this project. C. To require a project charter be published and signed off on by all stakeholders before proceeding. D. To require a project charter be written to include the resource needed, budget, and project manager's authority. The project manager is the only one who needs to see this document as other documents will be distributed later that contain the same detail as the charter.

1 2134

Which of the following is true regarding the project charter? A. The project charter should be published under the name of a manager external to the project. B. The project charter should be published under the project sponsor's name. C. The project charter should be published under the name of the project manager. D. The project charter should be published under the name of the project champion.

1089

You are the project manager for Zippy Tees. Your company has decided to outsource the manufacturing of miniature bears to be attached to your trendy T-shirts. Which of the following is true? A. A good product description is all that's required. The project manager will supply this to the vendor. B. The contract can serve as the project charter. The product description will be included in the contract. C. The project manager should write the project charter because the project manager will be managing the vendor portion of this project as well. D. The vendor should write the project charter as they are responsible for manufacturing the bears.

1117

The project charter: A. Includes a product description, describes the business need of the project, and is published by the project manager B. Includes a product description, describes the business need of the project, and is published by the project sponsor C. Includes the contract when the project is performed by a vendor and is published by a manager external to the project D. Includes a product description, describes the business need of the project, and is published by a manager external to the project

856


Post New Project Management Questions

Un-Answered Questions { Project Management }

What is the w5hh (wwwwwhh) principle given by barry boehm?

1591


You are a project manager working on a new software product. Your company plans to market to businesses. The project sponsor told you that the project must be completed by September 1. The company plans to demo the new software product at a trade show in late September and therefore needs the project completed in time for the trade show. However, the sponsor has also told you that the budget is fixed at $85,000 and cannot be increased by even $10 due to overall budget cuts this year. You must complete the project within the given time frame and budget. Which of the following is the primary constraint for this project? A. Budget B. Quality C. Time D. Schedule

1131


You are a project manager working on contract. You’ve performed earned value analysis and discovered that the project will be completed on time and under the original estimated amount. This means the profit to your company will decrease as will your personal bonus. Which of the following should you do? A. Add activities to the project to increase the cost enough to meet the original estimated amount. B. Tell the customer you're adding additional requirements to the project chat were originally cut because of cost constraints. C. Inform the customer that the project is completed and has come in under budget. D. Bill the customer for the full amount of the contract as this was the original agreed-upon price.

1028


You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail store for the option of opening two new stores in a foreign country. You've been told that it is culturally unacceptable to eat certain foods in this country. You know that one of these foods happens to be a secret ingredient in the pizza sauce. What is the most appropriate response? A. Inform the potential partners that your sauce recipe is secret, but you’re certain there are no forbidden ingredients in it. B. Inform the potential partners that you suspect there might be a forbidden ingredient in the sauce and you'll request an investigation to determine if any of them exist in the sauce. C. Inform the potential partners that a forbidden ingredient exists in the sauce and determine to work with them to come up with another ingredient to replace that one. D. Don't tell the potential partners about the ingredient because the sauce they'll be using in the stores is shipped to them already prepared in cans. They won't know the ingredient is in the sauce.

1133


What is the concept of project management?

899


You are a project manager with technical expertise in the pharmaceutical industry. You've decided to try your hand at project management in the entertainment industry. Which of the following is true? A. You will likely be successful because communication skills are your strong suit. You anticipate having technical experts on your project team to address industry specifics that you're not familiar with. B. You will likely be successful because your organizational skills are excellent. You anticipate having technical experts on your project team to address industry specifics that you're not familiar with. C. You will probably be successful because you have a friend in the entertainment industry that has briefed you on all the important aspects of this project that you'll need to know. You anticipate having technical experts on your project team to address industry specifics that you're not familiar with. D. You will probably not be successful because you have little knowledge of the entertainment industry even though you anticipate having technical experts on your project team to address industry specifics that you're not familiar with.

1066


Change control system, configuration management, performance measurement, additional planning, and project management information system are tools and techniques of which process? A. Integrated Change Control B. Scope Change Control C. Schedule change control D. Cost change control

941


What is raid in project management?

934


During your project meeting, a problem was discussed and a resolution to the problem was reached. During the meeting, the participants started wondering why they thought the problem was such a big issue. Sometime after the meeting, you received and e-mail from one of the meeting members saying they've changed their mind about the solution reached in the meeting and need to resurface the problem. The solution reached during the initial project meeting is an example of which of the following conflict resolution techniques? A. Confrontation B. Forcing C. Smoothing D. Storming

1041


You are in the Planning process of your project, and your project sponsor has requested an accurate cost estimate in two weeks from today. You'll use which of the following techniques to provide her with the most accurate cost estimate? A. Bottom-up B. Analogous C. Top-down D. Earned value

1015


Explain the Principals of Management

1004


Which of the following might require rebaselining of the cost baseline? A. Corrective action B. Revised cost estimates C. Updates to the cost management plan D. Budget updates

1042


You are the project manager for Lucky Stars Candies. You've identified the deliverables and requirements and documented them where? A. In the scope statement, which will be used as in input to the Scope Definition process B. In the scope definition document, which is used as an input to the Scope Planning process C. In the WBS, which is an output of the Scope Planning process D. In the WBS, which is a tool and technique of the Scope Definition process

1154


Procurement audits review what? A. The procurement process from Procurement Planning through Contract Administration B. The contract administration process from Solicitation Planning through Contract Administration C. The procurement process from Procurement Planning through Contract Closeout D. The contract administration process from Solicitation Planning through Contract Closeout

956


You are a project manager for Penguin Software. Your company creates custom software programs for hospitals and large dental offices. You have just completed a project and are gathering the documentation of the product of the project. This might include all of the following except: A. Technical specifications B. Electronic files C. Programming plans D. Performance measurements

963