If I have 3 different process chains then how can I create
a Metachain including all these 3 local chains ? Step by
Step procedure would be much appreciated as I am going to
try the suggestions provided on system. Thank you.
Answers were Sorted based on User's Feedback
Answer / ola oladute
Use event-controlled processing to automates all the 3
local chains as follows:
1. Use t-code SM62 to create an Event
2. Go to SM36 to create a job
3. Click on start condition, give the start date and time
of Process Chain no. 1
4. Create the job using program BTC_EVENT_RAISE. In the
variant give the event name as A
5. Include the event A in step 4 in the start condition of
PC (Process Chain) no. 1. Also include a program that will
raise event B
6.Include event B name in the start condition of PC no. 2.
Include a program that will raise event C
7.Include the event C name in the start condition of PC no.
3.
8. Go to SM64 to trigggered the event
Is This Answer Correct ? | 8 Yes | 0 No |
When a query is run with a loop, what does it generate? A) Cartesian product b)An incompatible combination of objects c) An SQL statement generation error d)Results returning too many rows e)Results returning too few rows
what is fullform of sap & college, institute of sap course
What is the name restriction on field when you append structure?
What is processing type customer exit?
What is a cell editor?
How will you change the default destination of open hub files?
how the master data is read?
How to gathering the requirement
What is a characteristic in CO-Pa?
What is a calculated key figure?
Define a communication structure?
what is meant by flat aggregate?explain in detail