what r the activites we have to do before just golive ?
Answers were Sorted based on User's Feedback
Answer / mmreddy
Hi,
Before golive we have done the following activities.
1.Finalise the entire system configuration.
2.done all testing like integration testing,gui testing etc
3.Cutover activities mean uploading of all master datas
4.user training.
Regards,
Mallesh.
Is This Answer Correct ? | 6 Yes | 0 No |
Answer / rajeev
checking of all the configuraion
sign off on all the business process
uploading of the legecy system data
validation of the uploaded data into sap
testing of the all the scenariao
integration testing with other module
testing of the configured test system to the user
providing all the user manual to the user.
setting of all the access control
audit by the concern agencicy
Is This Answer Correct ? | 3 Yes | 0 No |
Answer / sathya
Hi,
Before go to go live we should follow the four
implementation phases.
1. Project preparation:
The focus should be on the company’s core business
and how the SAP solution will better enable that core
business to be successful.
2. Sizing and blue printing
Build a new SAP DATA CENTER facility or transform
the current data center into a foundation capable of
supporting the SAP SOLUTION STACK
3. Functional development
Create a foundation for the SAP systems management
and SAP computer operations, by creating a SAP OPERATIONS
MANUAL and by evaluating SAP management applications.
4. Final preparation
Plan, prepare and execute the CUTOVER, by creating
a CUTOVER PLAN that describes all cutover tasks that have
to be performed before the actual go-live
Regards,
Sathya.M
Is This Answer Correct ? | 0 Yes | 4 No |
Answer / guest
BEFORE GOING TO GO LIVE WE WOULD DO DIFFRENT TYPES OF
TESTING,AND ALL THE MODULES SHOULD BE INTERGRATED,AD AT
LAST WE WOLD CALL OUR HIGHER AUTHORITY AND WE WILL SHOW HIM
THE LIVE SHOW,AFTER HE IS SATISFIED OR IF ANY CHANES TO BE
DONE WE WILL FINALISE AND WE WILL CLOSE THT PART....
Is This Answer Correct ? | 1 Yes | 6 No |
what do you mean by the tolerance group?
Brief about g/r I/r clearing. Can’t v avoid this a/c? Process?
what is end to end impletion? and what are the areas to be involved by fi consultant from starting to end could you pls explaing anybody.? Rgds, Swapna Sinha
In sap fico what are the terms of payment and where are they stored?
What is the difference between Activity Type and Statistical Key figure because both are tracing factors. Do we need to configure both in controlling area?
Our company has 2 divisions: Food Service & Food Beverage Units Now we have a problem... The customer no. 500 , is shared between our Food Service and Food & Beverage units. T we do not have a customer hierarchy for the following combination: sales org. 1000 dist. channel 10 ( for food service) division 00. We cannot set this up because we have the customer hierarchy already created for sales org.1000, dist. channel 11 ( for food and beverage) division 00 Is there anyway that we can set up the customer hierarchy for food service units? Please let me know
How do you manage relationship between two currencies in sap fi?
What are the options available while performing revaluation in an actual costing run?
What is the use of account receivables in fi?
Why does sap support linux?
dear fico expert's..in asset accounting..i completed all configuration steps..and purchased asset also..with tc.f-90..problem here depreciation run with(AFAB..it isnot successful..spool is not showing any depreciated value's..i want sale asset and go for further posting..please help.
what is SD Cycle plz entries and where the start for the gernal entires and t.code