Go Live and Cutover plan?
Answers were Sorted based on User's Feedback
Answer / shammee
Cutover Activities are Master/Transaction Data uploading
strategies depending upon the when we are going live. As
per that, you have to give the information to your core
team. If you going live at the middle you have to upload
the all P&L Account items and B/S Items. If you going live
at the financial year start, you have to only upload the
B/S Items.
a. Master Data uploads into production system
1. G/L Master Upload thru BDC or LSMW (FS00 & FS01)
2. Vendor Master Upload thru BDC or LSMW (Will be Taken
Care by MM)
3. Customer Master Upload thru BDC or LSMW (Will be Taken
Care by SD)
4. Asset Master Upload (AS90)
5. Cost Element Master Upload
6. Cost Center Master Upload
7. Profit Center Master Upload
b. Transaction data upload
1. G/L Balances (F-02)
2. Vendor Balances (F-43)
3. Customer Balances (F-22)
4. Customer Advances (F-29)
5. Vendor Advances (F-48) - Before uploading Vendor
Balances you have to take care of TDS Information.
6. Asset value uploads (AS91).
c. Controlling area related upload
1. Upload Cost center plan
2. Execute the allocation cycles within cost center
accounting
3. Update planned activity
4. Calculate Activity prices
5. Execute product costing run.
d. Other Pre-Go live activities
1. Ensure all the customizing request is in the production
system
2. Ensure all the number ranges for all the modules have
been maintained in the production system
3. Ensure that Operating concern has been generated
4. Ensure all material masters (all material types) have
been loaded
5. Upload Open purchase orders
6. Stock upload
7. Mark and Release the cost estimates.
Normally, in asset accounting the day to day transactions
is posted with values through FI bookings and at the same
time the asset reconciliation is updated online realtime.
Whereas In data Migration the asset master is updated with
values through a transaction code called as AS91. The
values updated on the master are Opening Gross value and
the accumulated depreciation. The reconciliation GL account
is not automatically updated at this point of time.
The reconciliation accounts (GL codes) are updated manually
through another transaction code called as OASV.
If profit center is active, then after uploading assets
through AS91 you should transfer the asset balances to
profit center accounting through a program.
Thereafter you remove the Asset GL code (reconciliation
accounts) from the 3KEH table for PCA and update the Asset
reconciliation account (GL code) through OASV.
After this step you again update the Asset reconciliation
account in the 3KEH table.
The reason you remove the Asset reconciliation code from
3KEH table is that double posting will happen to PCA when
you update the Asset reconciliation manually.
Is This Answer Correct ? | 29 Yes | 0 No |
The transfer of data from the quality assurance system, as
well as legacy data in a customer's previous system, to the
production system.
The cutover activities are specified in the ASAP Cutover
Plan and include setting up and initializing the production
system, closing legacy systems, and entering data manually
in the new system.
You need to copy and paste all the previous data into your
new system. However you have to be careful while merge the
information. Make sure about the posting dates and other
relevant information especially when you deal with asset
accounting
Is This Answer Correct ? | 40 Yes | 12 No |
Answer / venkat
Project Before go Live
We have to do the cut over activites like Vender
master,Customer, masterial master,tax code Migrated from
legacy system to Sap system
Is This Answer Correct ? | 30 Yes | 7 No |
Answer / sapfico
Cut over data means, the data from Legacy system will be
transfer (Cut) into SAP. They will make a format for the
transfer of Data to SAP through Legacy.
Is This Answer Correct ? | 23 Yes | 8 No |
Answer / sidhartha
whatever changes/development made in development server
that has to transfer to quality server for testing.before
shifting it to producton server all the final touches we
give to the implimentation datas ( master record,
configurations,different testings )is basicaly called
cutover plan.Go-live comes after cut over .
Is This Answer Correct ? | 10 Yes | 3 No |
Answer / kuramani patro
Cuttover means Non Software data will upload in real Production system in the help of LSMW or BDC.
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / pavan
it is refernce documents that discribe the systems,procedures,activities setting up and intilizing the production envirinment
Is This Answer Correct ? | 1 Yes | 1 No |
Answer / krishna
Go Live is Project is ready or already on live
Cutover Plan is part of BDC. How the data can be migrated
from legacy system to SAP. and their activities so on.
Is This Answer Correct ? | 11 Yes | 31 No |
Explain the TDS Procedure & its T.Code
Explain the value of creating a cost center?
What are the steps for configuring lockboxes?
Is it possible to use standard sap co-product functionality in repetitive manufacturing?
Hi viewers, My questions is, how can we make cleared item as open item in the Accounts Receivable. & How the checks are useful in the accounts receivable.
Hi Dear Friends, I am Sridhar, M.com, age is 50, working as a Finance Manager in a software company. I need your clarification, shall i enter as a SAP FICO consultant in this age, Please advice.
what is asset accounting?what is account determination,asset masterrecord?
will please anybody forward the project report on sap fico? my mail id : sriramy@gmail.com
What is mySAP ERP. How is it different to SAP ERP.
Hi, Is it possible to do the partial payments in APP?
What is an operating chart of accounts?
Which function type has to be used for using "at exit-command" ?