You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any rime during the day. The project sponsor has promised you a bonus if you get this project completed two weeks sooner than the scheduled project end date. The bonus will come in handy on your trip to the Bahamas planned for later this spring. You've got a few remaining project activities to wrap up before you can close out the project. Which of the following is the most appropriate response?
A. You tell the sponsor the project is complete and treat the remaining activities as though they're problems that came up after project closure so that you can still get the bonus.
B. You tell the sponsor the remaining activities are outside the scope of the project so the project really is completed and collect your bonus.
C. You tell the sponsor the stakeholders added these requirements after the project was well under way and you never agreed to include them in the project so the project really is complete, and you collect your bonus.
D. You tell the sponsor you aren't going to make the two-week early completion date as there are remaining activities to finish up.


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

Explain the Principals of Management

0 Answers   Mahatma Gandhi University,


You are a project manager for Uncle Sam's Flag Company. Your company has designed a new line of products featuring the American flag. Due to some unique circumstances, the products are in hot demand and the project sponsor has asked you to do whatever it takes to get this project completed early and make the products available. You regularly check the progress of the project with your team members using which of the following techniques? A. E-mail communication B. Status review meetings C. Project management information systems D. Receiver communication model

0 Answers  


You are the project manager for Changing Tides video games. You have gathered the inputs for the Activity Duration Estimating process. You will employ which tools and techniques to produce the outputs for this process? A. Activity list, analogous estimating, quantitatively based durations, and alternatives identification B. Activity list, analogous estimating, expert judgment, and quantitatively based durations C. Expert judgment, analogous estimating, quantitatively based durations, and reserve time D. Expert judgment, alternatives identification, quantitatively based durations, and reserve time

0 Answers  


The project schedule is used to determine all of the following except: A. Cost estimates B. Activity start dates C. Float times D. Activity end dates

0 Answers  


Which of the following processes serve as inputs to each other? A. Executing and Controlling B. Planning and Executing C. Planning and Controlling D. Executing and Initiation

0 Answers  






The grouping of project elements by deliverables is known as what? A. The code of accounts B. The work package C. The work breakdown structure D. The work breakdown dictionary

0 Answers  


Which of the following are tools and techniques of the Initiation process? A. Project selection methods and expert judgment B. Project selection criteria and expert judgment C. Constraints and assumptions and expert judgment D. Expert judgment and project charter

0 Answers  


Which of the following is true regarding product descriptions? A. The product description is an output of the Initiation process. It describes the characteristics of the product or service. B. The product description is an output of the Initiation process. It describes the characteristics of the product or service and less detail in the early phases of the project. C. The product description is an input of the Initiation process. It describes the characteristics of the product or service and contains a lot of detail in the early phases of the project. D. The product description is an input of the Initiation process. It describes the characteristics of the product or service.

0 Answers  


You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D department has agreed to release two resources to work on your project in order to meet the federal grant application date. This is an example of: A. Crashing B. Fast trucking C. Resource leveling D. Adjusting the resource calendar

0 Answers  


What is your leadership style?

1 Answers   State Bank Of India SBI,


You work for a company that writes hilling software programs for the communication industry. You've just been assigned a new project. The customer is located in a distant country that limits the number of foreigners allowed into the country. You identify this risk in your risk management plan. The critical point during the project is installation and setup. You might do which of the following given these circumstances? A. Use a design of experiments technique to develop a contingency plan. B. Develop a cause-and-effect diagram that identifies the contract type you should use for a project like this. C. Use sensitivity analysis to assist you in developing the appropriate risk response for this situation. D. Develop a contingency plan for installation.

0 Answers  


What is one of the advantages of a functional structure? A. All employees report to one manager and have a clear chain of command. B. All employees report to two or more managers, but project team members show loyalty to functional managers. C. The organization is focused on projects and project work. D. Teams are collocated.

0 Answers  


Categories