Describe the 4 p’s in software project management.


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

Which of the following is true regarding the project charter? A. The project charter should be published under the name of a manager external to the project. B. The project charter should be published under the project sponsor's name. C. The project charter should be published under the name of the project manager. D. The project charter should be published under the name of the project champion.

0 Answers  


Your project has experienced some changes to the agreed-upon WBS elements. The changes were approved through the proper change control process. The WBS changes may in turn require which of the following? A. Scope changes B. Cost changes C. Schedule revisions D. Risk response changes

0 Answers  


What is your management Style

8 Answers   ABC, Hospitality, Thomson,


You are a project manager for Picture Shades, Inc. They manufacture window shades for hotel chains that have replicas of Renaissance-era paintings on the inside of the shades. Picture Shades is taking their product to the home market, and you're managing the new project. They will offer their products at retail stores as well as on their website. You're developing the project schedule for this undertaking and have determined the critical path. Which of the following is true? A. You calculated the most likely start date and most likely finish dates, float time, and weighted average estimates. B. You calculated the activity dependency, and the optimistic and pessimistic activity duration estimates. C. You calculated the early and late start dates, early and late finish dates, and float times for all activities. D. You calculated the optimistic, pessimistic, and most likely duration times and the float times for all activities.

0 Answers  


The grouping of project elements by deliverables is known as what? A. The code of accounts B. The work package C. The work breakdown structure D. The work breakdown dictionary

0 Answers  






What are the inputs to the Initiation process? A. Product description, strategic plan, project selection criteria, and historical information B. Product description, strategic plan, project overview document, and historical information C. Strategic plan, project overview document, feasibility study, and historical information D. Product description, strategic plan, constraints, and assumptions

0 Answers  


You are a project manager for a network cabling project for your organization. Your project team is made up of six full-time employees and three contractors. This is the first time they have all worked together. This project requires accurate information exchange at all times during the life of the project. How many lines of communication exist among the project team members? A.36 B.41 C.18 D.34

0 Answers  


You have been hired as a contract project manger for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. One of the activities for this project is the installation and testing of several new servers. You know from past experience it takes about 16 hours per server to accomplish this task. Since you're installing 10 new servers, you estimate this activity to take 160 hours. Which of the estimating techniques have you used? A. Analogous estimating B. Bottom-up estimating C. Quantitatively based duration D. Reserve time

0 Answers  


Which of the following is true regarding constraints and assumptions? A. Constraints restrict the actions of the project team, and assumptions are considered true for planning purposes. B. Constraints are considered true for planning purposes, and assumptions limit the options of the project team. C. Constraints consider vendor availability and resource availability to be true for planning purposes. Assumptions limit the project teamwork within predefined budgets or time lines. D. Constraints and assumptions are inputs to the Initiation process. They should be documented, as they will be used throughout the project Planning process.

0 Answers  


People are motivated by the need for achievement, power, or affiliation according to which theory? A. Expectancy theory B. Achievement theory C. Contingency theory D. Theory X

0 Answers  


You work for a large manufacturing plant. You're in the Initiation process of a new project for an overseas product release. This is the company's first experience in the overseas market, and they hope to make a big splash with the introduction of this product. The project entails producing your product in a concentrated formula and packaging it in smaller containers than the U.S. product uses. A new machine is needed in order to mix the first set of ingredients in the concentrated formula. Which of the following actions should the project manager take? A. The project manager should document the project's goals and known deliverables in a high-level overview document and recommend the project proceed. B. The project manager should document the project's goals and known deliverables in a high-level overview document and assume the project is a go. C. The project manager should document the project's goals and known deliverables in a high-level overview document and recommend a feasibility study be performed. D. The project manager should document the project's goals and known deliverables in a high-level overview document and deliver it to the stakeholders.

0 Answers  


You’re promised your team two days of paid time off plus a week’s training in the latest technology of their choice if they complete their project ahead of schedule. This is an example of which of the following? A. Achievement theory B. Expectancy theory C. Maslow's theory D. Contingency theory

0 Answers  


Categories