You are a project manager for Pizza Direct, which is a retail pizza delivery store. Your company is competing with another retail score for the option of opening two new stores in a foreign country. You know, but have not yet informed your company, that you are going to go to work for the competitor, which happens to be bidding for this same opportunity. What is the most appropriate response?
A. You decline to participate in the initial meetings with the foreign business partners due to conflict of interest.
B. You've not yet received an official offer from the competing company for your new job opportunity, so you choose to participate in the initial meetings with the foreign business partners.
C. You decide to participate in the initial meetings with the foreign business partners because any information you gain now will help you when you make the move to the new company.
D. You inform the foreign business partners that you're going to be working with a new company and that you know the deal they'll receive from the competing company is better than the one this company is proposing.
No Answer is Posted For this Question
Be the First to Post Answer
You are a project manager for a software manufacturing firm. The project you've just finished created a new software product that is expected to become a number-one seller. A friend of yours is a certified software instructor. They have asked you for a copy of the software prior to the beta release through the marketing department so they can get familiar with it. What is the most appropriate response? A. Since your friend is certified to teach your company's brand of software, provide them with a copy of the software. B. Ask them to sign a nondisclosure agreement before releasing a copy of the software. C. Decline the request since you stand to gain from this transaction by receiving free training. D. Decline the request because the software is the intellectual property of the company.
You are the project manager for Changing Tides video games. You have gathered the inputs for the Activity Duration Estimating process. You will employ which tools and techniques to produce the outputs for this process? A. Activity list, analogous estimating, quantitatively based durations, and alternatives identification B. Activity list, analogous estimating, expert judgment, and quantitatively based durations C. Expert judgment, analogous estimating, quantitatively based durations, and reserve time D. Expert judgment, alternatives identification, quantitatively based durations, and reserve time
What is "Readjustig goal and Milestone" in project managment and project planing
You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 778 B. 780 C. 861 D. 833
How do you motivate team members?
What is your management Style
8 Answers ABC, Hospitality, Thomson,
Which of the following describes the cost of quality associated with scrapping, rework, and downtime? A. Internal failure costs B. External failure costs C. Prevention costs D. Appraisal costs
Brainstorming and the Delphi technique are two types of information-gathering techniques found in which process? A. Risk Management Planning B. Risk Response Control C. Risk Identification D. Quantitative Risk Analysis
Which of the following is true regarding the staffing management plan needed for project activities? It is an output of the Resource Planning process. A. It details the resource requirements and the quantity of resources needed for project activities. It is an output of the Resource Planning process. B. It details how and when staff resources will be brought on and take off the project. It is an output of the Organizational Planning process. C. It details how and when staff resources wilt be brought on and take off the project. It is an output of the Resource Planning process. D. It details the resource requirements and the quantity of resources needed for project activities. It is an output of the Organizational Planning process.
Which of the following is true regarding Administrative Closure? A. It occurs at the end of a project phase and at the end of the project. B. It occurs at the end of the project phase only. C. It occurs at the end of the project only. D. It is performed prior to Contract Closeout.
You have collected the performance measurement documentation for your project to be included in the project archives. What is the purpose of the performance measurement documentation? A. It's used as part of the formal acceptance process to verify contract expenditures. B. It's reviewed to make certain the project goals and objectives were met. C. It's included in the project archive documentation after confirming the accuracy of the measurements. D. It’s used as historical information for future project that are similar in scope to this project.
You are the project manager for a scheduled version release of your company’s software tracking product. You have linked the WBS and project scope definition and assigned roles and responsibilities. You might want to display the roles and responsibilities in which of the following? A. RDM B. PDM C. AOA D. RAM