You are working on a project that was proceeding well until a manufacturing glitch occurred that requires corrective action. It turns out the glitch was an unintentional enhancement to the product, and the marketing people are absolutely crazy about its potential. The corrective action is canceled, and you continue to produce the product with the newly discovered enhancement. As the project manager, you know that a change has occurred to the project scope. Which of the following is true?
A. Project scope changes do not require CCB approval.
B. Performance measurement baselines are affected by scope changes.
C. Project scope change uses inspection to determine if change has occurred.
D. Project scope change uses workarounds to correct unexpected problems with scope change.


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

What is the difference between risk impact and risk probability?

0 Answers  


What are the 10 knowledge areas of project management?

0 Answers  


Comparative methods, scoring methods, and economic and cash flow analysis are all part of which of the following? A. Benefit measurement methods, which are a tool and technique in Initiation B. Constrained optimization methods, which are a tool and technique C. Benefit measurement methods, which are an input to Initiation D. Decision models, which are an output of Initiation

0 Answers  


Which of the following tools and techniques shows the impacts of one decision over another as well as the probability and cost of each risk along a logical path? A. Simulation B. Decision tree C. Probability/impact risk matrix D. Sensitivity analysis

0 Answers  


Receivers in the communication model filter their information through all of the following except: A. Culture B. Knowledge of subject C. Conflict D. Language

0 Answers  






HI everyone, I am commerce graduate, completed MBA Finance in Distinction. I would like to do FI/CO. Could any one of you please suggest, which is the best instistute for FI/CO training in Hyderabad. Compulearn, Reliance, or other. Thanks in advance Rupa Gupta

4 Answers  


All of the following are true regarding the tools and techniques of Activity Sequencing except: A. GERT uses analogous methods. B. GERT allows for loops. C. GERT is a conditional diagramming method. D. GERT allows for conditional branches.

0 Answers  


You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any rime during the day. The project sponsor has promised you a bonus if you get this project completed two weeks sooner than the scheduled project end date. The bonus will come in handy on your trip to the Bahamas planned for later this spring. You've got a few remaining project activities to wrap up before you can close out the project. Which of the following is the most appropriate response? A. You tell the sponsor the project is complete and treat the remaining activities as though they're problems that came up after project closure so that you can still get the bonus. B. You tell the sponsor the remaining activities are outside the scope of the project so the project really is completed and collect your bonus. C. You tell the sponsor the stakeholders added these requirements after the project was well under way and you never agreed to include them in the project so the project really is complete, and you collect your bonus. D. You tell the sponsor you aren't going to make the two-week early completion date as there are remaining activities to finish up.

0 Answers  


Project managers have the greatest amount of authority in which kind of organizational structure? A. Functional B. Projectized C. Weak matrix D. Balanced matrix

0 Answers  


Which of the following project-scheduling techniques allows for conditional and probabilistic treatment? A. GERT B. CPM C. PERT D. CPM and PERT

0 Answers  


You are a project manager for Laredo Pioneer’s Traveling Rodeo Show. You’re heading up a project to promote a new line of souvenirs to be sold at the shows. You need to gather the inputs to write the scope statement. You gather which of the following? A. Project charter, product description, assumptions, and constraints B. Project charter, product analysis, and cost benefit analysis C. Product description, product analysis, and project charter D. Product description, assumptions, constraints, and product analysis

0 Answers  


What is triple constraint triangle in project management?

0 Answers  


Categories