Why do you want to switch over from IT to management?


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

During your project meeting, a problem was discussed and a resolution to the problem was reached. During the meeting, the participants started wondering why they thought the problem was such a big issue. Sometime after the meeting, you received and e-mail from one of the meeting members saying they've changed their mind about the solution reached in the meeting and need to resurface the problem. The solution reached during the initial project meeting is an example of which of the following conflict resolution techniques? A. Confrontation B. Forcing C. Smoothing D. Storming

0 Answers  


Which performance measurement tells us what the projected total cost of the project will be at completion? A. ETC B. CPI C. SPI D. EAC

0 Answers  


You are a project manager for Cashiers systems. Your company produces cashiering systems and software for the retail industry. Your customer has requested a change to the product. You will handle this change using the scope change control system. All of the following are true except: A. Changes to product scope should be reflected in project scope. B. Project scope changes may result in adjustments to the performance measurement baselines. C. Changes to project scope should be reflected in the product scope. D. Scope changes may result in performance improvements.

0 Answers  


Which of the following is true regarding the critical path? A. It should never be compressed. B. It allows for looping and branching. C. The critical path technique is the same as PERT. D. It's the duration of all tasks with zero float.

0 Answers  


During a recent team meeting, you reached a resolution to a problem that's been troubling the team for several weeks. You took responsibility for searching out the facts of this problem and uncovered the right answer to this problem. You presented the facts at the project status meeting, and everyone reached agreement on the recommended solution based on the facts you presented. This is an example of what type of conflict resolution technique? A. Compromise B. Smoothing C. Confrontation D. Forcing

0 Answers  






You've constructed the WBS for your recent project. Level two assignments have been made, and you've requested that the sub project manager’s report back to you in 3 weeks with each of their individual WBS constructed. All of the following are true except: A. The work package level facilitates resource assignments. B. The work package level is the lowest level in the WBS. C. The work package level defines the agreed-upon deliverables. D. The work package level facilitates cost and time estimates. ?

0 Answers  


You are a project manager working on contract. You’ve performed earned value analysis and discovered that the project will be completed on time and under the original estimated amount. This means the profit to your company will decrease as will your personal bonus. Which of the following should you do? A. Add activities to the project to increase the cost enough to meet the original estimated amount. B. Tell the customer you're adding additional requirements to the project chat were originally cut because of cost constraints. C. Inform the customer that the project is completed and has come in under budget. D. Bill the customer for the full amount of the contract as this was the original agreed-upon price.

0 Answers  


You have been assigned to a project in which the objectives are to expand three miles of the north-south highway through your city by two lanes in each direction. You are in charge of the demolition phase of this project, and you report to the project manager in charge of this project. You have been hired on contract and will be released at the completion of the demolition phase. What type of organizational structure does this represent? A. Functional organization B. Weak matrix organization C. Projectized organization D. Balanced matrix organization

0 Answers  


HI everyone, I am commerce graduate, completed MBA Finance in Distinction. I would like to do FI/CO. Could any one of you please suggest, which is the best instistute for FI/CO training in Hyderabad. Compulearn, Reliance, or other. Thanks in advance Rupa Gupta

4 Answers  


You are the project manager for the Late Night Smooth Jazz Club chain, with stores in 12 states. Smooth Jazz is considering opening a new club in Kansas City or Spokane. You have derived the following information: Project Kansas City: The payback period is 27 months, and the IRR is 35 percent. Project Spokane: The payback period is 25 months, and the IRR is 32 percent. Which project should you recommend to the selection committee? A. Project Spokane because the payback period is shortest B. Project Kansas City because the IRR is highest C. Project Spokane because the IRR is lowest D. Project Kansas City because the payback period is longest ?

0 Answers  


You've reached a stale of independence where you're able to express yourself and perform at your peak level of performance. Being the best you can be is the motivator that drives you. Which of the following is true? A. This is an example of the Expectancy theory. B. You've reached self-actualization in Maslow's Hierarchy. C. This is an example of the Hygiene theory. D. You've reached the highest level of the Achievement theory.

0 Answers  


You are a project manager for Bluebird Technologies. Bluebird writes custom billing applications for several industries. A scope change has been requested. You know change is concerned with all of the following except: A. Managing change B. Verifying change C. Influencing causes of change D. Determining that a change occurred

0 Answers  


Categories