How will prioritize tasks in your projects?


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

You are ready to perform the Activity Sequencing process for your project. To make your job easier, you're going to use a software tool to help you draw a PDM network diagram. Most software programs use this technique. You know all of the following are true regarding the PDM except: A. It shows the activities on arrows and connects them to dependencies usually depicted as circles. B. It’s also called AON. C. It shows the activities in boxes with arrows connecting the dependent activities. D. It uses four types of dependency relationships of which finish to start is one.

0 Answers  


You've constructed the WBS for your recent project. Level two assignments have been made, and you've requested that the sub project manager’s report back to you in 3 weeks with each of their individual WBS constructed. All of the following are true except: A. The work package level facilitates resource assignments. B. The work package level is the lowest level in the WBS. C. The work package level defines the agreed-upon deliverables. D. The work package level facilitates cost and time estimates. ?

0 Answers  


These diagrams rank order factors for corrective action by frequency of occurrence. They are also a type of histogram: A. Control charts B. Process flowcharts C. Scatter diagrams D. Pareto diagrams

0 Answers  


Which of the following is true regarding schedule variances? A. They impact scope, which impacts the schedule B. They sometimes impact the schedule C. They always impact the schedule D. They never impact the schedule

0 Answers  


Explain the meaning of management.

0 Answers   Mahatma Gandhi University,






HI everyone, I am commerce graduate, completed MBA Finance in Distinction. I would like to do FI/CO. Could any one of you please suggest, which is the best instistute for FI/CO training in Hyderabad. Compulearn, Reliance, or other. Thanks in advance Rupa Gupta

4 Answers  


The tools and techniques of the Source Selection process include all of the following except: A. Contract negotiation B. Correspondence C. Independent estimates D. Screening system

0 Answers  


You are a project manager working for Mail House King. Your company processes orders for several mail-order catalog companies. Your project is to install new mail-sorting equipment and software. You’ve had some problems and experienced some variances so far during the project. Your project sponsor has asked for an EAC. You know the following information: PV = 800, BAC = 700, EV = 675, AC = 750, and ETC = 30. Which of the following is the correct EAC given the circumstances? A. 778 B. 780 C. 861 D. 833

0 Answers  


How do you handle conflicts in the Team Management ?

0 Answers   Microsoft,


You are a project manager with several years of experience in project management. You’ve just accepted your first project in a foreign country. You've been in the country a week or two and are experiencing some disoriented feelings. This is known as: A. Collocation B. Diversity shock C. Global culturing D. Culture shock

0 Answers  


You are a project manager for Laurel’s theater productions. Your new project is coming in over budget and requires a cost change through the cost change control system. The cost variance was projected using which of the following tools and techniques? A. Performance measurements B. Cost baseline measurements C. Computerized tools D. Performance reports

0 Answers  


All of the following are true regarding the project plan except: A. Some of its inputs are outputs from other Planning processes. B. It's used to guide the project executing and controlling processes and is the baseline used to measure project performance. C. It consists of one document that should be formally approved and signed by stakeholders. D. It contains things like the WBS, project schedule, and resource assignments.

0 Answers  


Categories