All of the following are true regarding the WBS except:
A. It is a deliverables-oriented grouping of project deliverables and elements.
B. It defines and organizes the work of the project in a hierarchical form.
C. It provides a framework for the work of the project, and work not shown on the WBS is not included in the project.
D. It defines all the deliverables of the project, but the activities level should not be listed on the WBS.


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

All of the following are types of project closures or endings except: A. Addition B. Integration C. Verification D. Extinction

0 Answers  


How do you ensure that your project is always on track?

0 Answers  


You are a project manager for Giraffe Enterprises. You've recently taken over for a project manager who lied about his PMI certification and was subsequently fired. Unfortunately, he did a poor job of Scope Definition. You know if you don't correct this, one of the following could happen: A. The stakeholders will require overtime from the project team to keep the project on schedule. B. The WBS will adversely affect the deliverable breakdowns, and costs will increase. C. The scope management plan will require changes. D. The project costs could increase, there might be rework, and schedule delays may result.

0 Answers  


How a project is made and deliverd to client? please put all detailed steps internally?

2 Answers   CIT,


You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. The manager of the R&D department has agreed to release two resources to work on your project in order to meet the federal grant application date. This is an example of: A. Crashing B. Fast trucking C. Resource leveling D. Adjusting the resource calendar

0 Answers  






Your project progressed as planned up until yesterday. Suddenly, an unexpected risk event occurred. You quickly devised a response to deal with this negative risk event using which of the following tools and techniques of Risk Monitoring and Control? A. Risk management plan updates B. Workarounds C. Corrective action D. Additional risk identification

0 Answers  


A negative result from an SV calculation means which of the following? A. PV is higher than EV. B. PV equals one. C. EV is higher than PV. D. EV is higher than AC.

0 Answers  


You work for a large manufacturing plant. You're working on a new project for an overseas product release. This is the company's first experience in the overseas market, and they hope to make a big splash with the introduction of this product. The project entails producing your product in a concentrated formula and packaging it in smaller containers than the U.S. product uses. A new machine is needed in order to mix the first set of ingredients in the concentrated formula. Which of the following is true? A. The new machine, the concentrated formula, and the smaller package are each project constraints. B. The new machine, the concentrated formula, and the smaller package description must be incorporated into the product description document. C. The new machine, the concentrated formula, and the smaller package are each project assumptions. D. The new machine, the concentrated formula, and the smaller package are each considered deliverables.

0 Answers  


You are a project manager with several years of experience in project management. You’ve just accepted your first project in a foreign country. You've been in the country a week or two and are experiencing some disoriented feelings. This is known as: A. Collocation B. Diversity shock C. Global culturing D. Culture shock

0 Answers  


You are a project manager for a documentary film company. In light of a recent national tragedy, the company president wants to get a new documentary on the rescue efforts of the heroic firefighters to air as soon as possible. She's looking to you to make this documentary the best that's ever been produced in the history of this company. She guarantees you free rein to use whatever resources you need to get this project done quickly. However, the best photographer in the company is currently working on another assignment. Which of the following is true? A. The primary constraint is time because the president wants the film done quickly. She told you to get it to air as soon as possible. B. Resources are the primary constraint. Even though the president has given you free rein on resource use, you assume she didn't mean those actively assigned to projects. C. The schedule is the primary constraint. Even though the president has given you free rein on resource use, you assume she didn’t mean those actively assigned to projects. The photographer won’t be finished for another three weeks on his current assignment, so schedule adjustments will have to be made. D. The primary constraint is quality because the president wants this to be the best film ever produced by this company. She's given you free rein to use whatever resources needed to get the job done.

0 Answers  


Your project depends on a key deliverable from a vendor you've used several times before with great success. You're counting on the delivery to arrive on June 1. This is an example of : A. Constraint B. Objective C. Assumption D. Goal

0 Answers  


What is one of the advantages of a functional structure? A. All employees report to one manager and have a clear chain of command. B. All employees report to two or more managers, but project team members show loyalty to functional managers. C. The organization is focused on projects and project work. D. Teams are collocated.

0 Answers  


Categories