You are a project manager for a telecommunications firm. You're working on a project that entails upgrading technical hardware and equipment. The estimated cost of the hardware and equipment is $1,725,000. You are reviewing products from three different vendors. One of the vendors offers you and your family the use of the company yacht for the upcoming three-day weekend. What is the most appropriate response?
A. Thank them and accept. You don't believe there is a conflict of interest or an integrity issue at stake.
B. Thank them and decline. You know this could be considered personal gain, which could call your integrity into question.
C. Thank them and accept. Immediately report your actions to the project sponsor so that your motives are not called into question after the fact.
D. Thank them and decline. You know this could be considered an integrity issue on the part of the vendor.
No Answer is Posted For this Question
Be the First to Post Answer
PERT is: A. The longest path B. A weighted average technique C. A simulation technique D. Widely used in practice to determine schedule durations
You are a project manager for Snow Fun, a chain of retail shops specializing in winter spurts gear and clothing. You've been working on contract with Snow Fun and are ready to move on to your next assignment. As the project manager, you know all of the following are true regarding the project Closing processes except: A. Administrative Closure is always required at the close of the project. B. The Closing processes are the most often skipped processes. C. Administrative Closure should occur prior to Contract Closeout. D. Both Closing processes verify that the work and product of the project were completed satisfactorily.
You are project manager for a nonprofit organization. Your project has come about due to a social need. Your sponsor wants to get right to the Planning process. However, you know that a project charter should be published prior to proceeding to the Planning processes. All of the following are true regarding project charters except: A. Project charters always include cost and time estimates. B. Project charters always include the product description and business need for the product. C. Project charters recognize and acknowledge the existence of the project. D. Project charters commit organizational resources to the project.
Which logical relationship does the PDM use most often? A. Start to finish B. Start to start C. Finish to finish D. Finish to start
As a PMP, one of your responsibilities is to ensure integrity on the project. When your personal interests are put above the interests of the project or when you use your influence to cause others to make decisions in your favor without regard for the project outcome, this is considered: A. Conflict of interest B. Using professional knowledge inappropriately C. Culturally unacceptable D. Personal conflict issue
What is tracing process? How this can be enabled?
Three people are responsible for establishing cost of quality theories. Crosby and Juran are two of them, and their theories respectively are: A. Grades of quality, fitness for use B. Fitness for use, zero defects C. Zero defects, fitness for use D. Cost of quality, zero defects
Which organization has set the de facto standards for project management techniques? A. PMBOK B. PMO C. PMI D. PMA
Your hardware vendor left you voicemail saying that a potential snowstorm in the Midwest might prevent your equipment from arriving on time. She wanted to give you a heads-up and asked that you return the call. Which of the following is true? A. This is a secondary risk, which is an output of Risk Response Planning. B. This is a contingency plan, which is an output of Risk Response Planning. C. This is a risk, which is an output of Risk Identification. D. This is a trigger, which is an output of Risk Identification.
You are a project manager for Laurel’s theater productions. Your new project is coming in over budget and requires a cost change through the cost change control system. The cost variance was projected using which of the following tools and techniques? A. Performance measurements B. Cost baseline measurements C. Computerized tools D. Performance reports
You are the project manager for a construction company that is building a new city and county office building in your city. Your CCB recently approved a scope change. You know that scope change might come about as a result of all of the following except: A. Schedule revisions B. Product scope change C. Changes to the agreed-upon WBS D. Changes to the project requirements
You have been assigned to a project that will allow job seekers to fill out applications and submit them via the company website. You report to the VP of human resources. You are also responsible for screening applications for the information technology division and setting up interviews. The project coordinator has asked for the latest version of your changes to the online application page for his review. Which organizational structure do you work in? A. Functional organization B. Weak matrix organization C. Projectized organization D. Balanced matrix organization