What is FRC and JIT in scheduling agreement?
Answers were Sorted based on User's Feedback
FRC used for scheduling agreement release type for long term planning.
JIT used for SA release type for short term i.e., weekly,day basis.
Is This Answer Correct ? | 3 Yes | 0 No |
Answer / s.sandeep kumar
in frc(forecasting) material schedules according to month-basis.
where as in just in time it schedules on day-basis
Is This Answer Correct ? | 1 Yes | 0 No |
If you want to make item ok check boix as default then what will you do?
hi All can someone please suggest me a good instructor or institute with more focus on real time scenarios/projects for SAP MM in Hyderabad I have a experience of over 7 years in Supply Chain and Logistics , looking to build my career in SAP as I have been using SAP for 7 years now Thank you
How do you create movement types? What are the steps involved? When will you recommend a new movement type?
What is the function of obyc?
we want to change some data like price, data etc in created purchase order. But system is not allowing the same. As a support sap mm functional consultant whatyou would do?
What is the interaction between sap mm and sap abap consultant and how does they interact?
when i am creating info record:purch.organisation data 1:i am getting error make an entry in all required fields
In SAP under Material Master how items will be codified?
You want to automatically convert purchase requisition to purchase order. How would you configure the system?
What is material attribute? How you will differentiate Row material and Finish goods?
What happens when a goods receipt is posted?
How and where to make automatic check of Free item checkbox while creating PO?