how would you lock the wbs elements? that the user can not release the pr
Answers were Sorted based on User's Feedback
Answer / vbb
Create USER STATUS for WBS and set it according to your requirement
Is This Answer Correct ? | 6 Yes | 0 No |
Answer / avinash reddy
Do not release the WBS for which you do not want to release teh PR
Is This Answer Correct ? | 8 Yes | 4 No |
Answer / krishnachaitanya
we can change the status of the WBS element to time reporting closed
Is This Answer Correct ? | 3 Yes | 0 No |
Answer / tushar
probably you can put your project on display mode which will not allow any editing or changing of data.
Is This Answer Correct ? | 3 Yes | 6 No |
Can any one describe PS and other module integration? How can we do integration between PS-FI, PS-CO, PS-SD, PS-MM,PS-PM, PS-P2P etc. with details in configuration also?
you want to set field status of wbs as mandatory. How would you do it?
What does a processes ensure?
How to set field status of wbs as mandatory, (wbs element, and ntw) ?
How do you estimate in the three point estimating method?
What are the important aspects of a hr plan for the project team?
List the parameters of project system.
Do you think professionalism and integrity are essential qualities of a pm?
How will you define a project?
What are the different time profiles?
Explain planning profile.
Can progress be updated in wbs elements?