Your project got delayed by 40 days and you have to keep it
back.what steps you would take.

Answers were Sorted based on User's Feedback



Your project got delayed by 40 days and you have to keep it back.what steps you would take...

Answer / srk

Either
Identify those activities and execute them in parallel
or
add more resources to the project activities
or both

Is This Answer Correct ?    16 Yes 0 No

Your project got delayed by 40 days and you have to keep it back.what steps you would take...

Answer / rajeev a

-Check those non critical activity which have some float, some of the resources from those activity can be put on critical actives.
-Try to see the activities which can be done in parallel.
-Check with customer if some low priority features can be postponed to further releases.
- Finally try to add some more resources which can be productive from day 1. Because in these kind of situation you will not have time to hand hold them.

Is This Answer Correct ?    3 Yes 0 No

Your project got delayed by 40 days and you have to keep it back.what steps you would take...

Answer / s.thiru selvan

i have planing before how the project are prefectly complte
.and then runs to the my project.

Is This Answer Correct ?    2 Yes 2 No

Your project got delayed by 40 days and you have to keep it back.what steps you would take...

Answer / a.barakat

first , we must start with critical activities ( most delay activities) and recover it first.

Is This Answer Correct ?    1 Yes 1 No

Post New Answer

More Project Management Interview Questions

Your project progressed as planned up until yesterday. Suddenly, an unexpected risk event occurred. You quickly devised a response to deal with this negative risk event using which of the following tools and techniques of Risk Monitoring and Control? A. Risk management plan updates B. Workarounds C. Corrective action D. Additional risk identification

0 Answers  


You are implementing a sap project. implementation compled and development started and at that time you found that there is major problem with the system .It would take again time and customer is not happy with that ,in that case how do you convince customer?

2 Answers   Siemens,


Which of the following describes a unique characteristic of the project Executing and Controlling processes? A. The core processes in the Executing and Controlling processes are from the Project Integration knowledge area from the Project Integration knowledge area. B. Both the Executing and Controlling processes measure variances in project performance and use corrective action to bring performance hack in line with the plan. C. Executing is an input to the Controlling processes, and Controlling is an input to Execution. D. Executing and controlling each have only one core process.

0 Answers  


People are motivated by the need for achievement, power, or affiliation according to which theory? A. Expectancy theory B. Achievement theory C. Contingency theory D. Theory X

0 Answers  


How to track your team members?

0 Answers  






Your project team is a close group all busily working on project activities. They're close to approaching the performing stage of Team Development. All six members must communicate frequently with each other. How many lines of communication are there? A. 12 B. 15 C. 18 D. 14

0 Answers  


All of the following are true regarding the Executing processes except: A. Executing has one core process. B. The majority of the project budget is spent here. C. The greatest conflicts are schedule conflicts. D. Project performance is measured to identify variances.

0 Answers  


You are the project manager for Changing Tides video games. You have gathered the inputs for the Activity Duration Estimating process. You will employ which tools and techniques to produce the outputs for this process? A. Activity list, analogous estimating, quantitatively based durations, and alternatives identification B. Activity list, analogous estimating, expert judgment, and quantitatively based durations C. Expert judgment, analogous estimating, quantitatively based durations, and reserve time D. Expert judgment, alternatives identification, quantitatively based durations, and reserve time

0 Answers  


All of the following describe the activity list except: A. It's an extension of the WBS. B. It includes all activities of the project. C. It describes the WBS updates. D. It includes a description of project activities.

0 Answers  


You are a project manager for Move It Now trucking company. Your company specializes in moving household goods across the city or across the country. Your project involves upgrading the nationwide computer network for the company. Your lead engineer has given you the following estimates for a critical path activity: 60 days most likely, 72 days pessimistic, 48 days optimistic. What is the standard deviation? A. 22 B. 20 C. 2 D. 4

0 Answers  


Which of the following are the tools and techniques of the Cost Budgeting process? A. Project management information system, analogous estimating, bottom-up estimating, mathematical analysis B. Analogous estimating, bottom-up estimating, mathematical analysis, computerized tools C. Project management software, analogous estimating, bottom-up estimating, parametric modeling D. Analogous estimating, bottom-up estimating, parametric modeling, computerized tools

0 Answers  


HI everyone, I am commerce graduate, completed MBA Finance in Distinction. I would like to do FI/CO. Could any one of you please suggest, which is the best instistute for FI/CO training in Hyderabad. Compulearn, Reliance, or other. Thanks in advance Rupa Gupta

4 Answers  


Categories