You are project manager for an engineering company. Your company won the bid to add ramp-metering lights to several on-ramps along a stretch of highway at the south end of the city. You subcontracted a portion of the project to another company. The subcontractor's work involves digging the holes and setting the lamp poles in concrete. The subcontractor's performance is not meeting the contract requirements. All of the following are valid options except:
A. You document the poor performance in written form and send the correspondence to the subcontractor change request through Contract Administration.
B. You terminate the contract for poor performance and submit a change request through Contract Administration.
C. You submit a change request through Contract Administration to ask the subcontractor to comply with the terms of the contract.
D. You agree to meet with the subcontractor to see if a satisfactory solution can be reached.


No Answer is Posted For this Question
Be the First to Post Answer

Post New Answer

More Project Management Interview Questions

All of the following are true regarding the Executing processes except: A. Executing has one core process. B. The majority of the project budget is spent here. C. The greatest conflicts are schedule conflicts. D. Project performance is measured to identify variances.

0 Answers  


What is the name of the unplanned response used to deal with negative risk events in the Risk Monitoring and Control process? A. Mitigation B. Contingency plans C. Workarounds D. Corrective action

0 Answers  


You are a project manager for Uncle Sam's Flag Company. Your company has designed a new line of products featuring the American flag. Due to some unique circumstances, the products are in hot demand and the project sponsor has asked you to do whatever it takes to get this project completed early and make the products available. You are to add resources to the project. The sponsor agrees to pay the additional costs since time is now a critical factor. Which technique have you used? A. Crashing B. Resource leveling C. Fast tracking D. Resource loading

0 Answers  


How do you set goals for your team? And how do you track these goals?

0 Answers  


You are the project manager for an upcoming outdoor concert event. You're working on the procurement plan for the computer software program that will control the lighting and screen projections during the concert. You're comparing the cost of purchasing a software product to the cost of your company programmers writing a custom software program. You are engaged in which of the following? A. Procurement planning B. Sensitivity analysis C. Transference of risk D. Make or buy analysis

0 Answers  






Write about organising and staffing in management.

0 Answers   Mahatma Gandhi University,


You are the project manager for Lucky Stars Candies. You've identified the deliverables and requirements and documented them where? A. In the scope statement, which will be used as in input to the Scope Definition process B. In the scope definition document, which is used as an input to the Scope Planning process C. In the WBS, which is an output of the Scope Planning process D. In the WBS, which is a tool and technique of the Scope Definition process

0 Answers  


A negative result from an SV calculation means which of the following? A. PV is higher than EV. B. PV equals one. C. EV is higher than PV. D. EV is higher than AC.

0 Answers  


Critical path tasks are those tasks that: A. Have equal pessimistic, optimistic, and most likely estimated times B. Have a float rime of zero C. Have the same start date D. Have multiple early start dates and early finish dates

0 Answers  


Your project team is a close group all busily working on project activities. They're close to approaching the performing stage of Team Development. All six members must communicate frequently with each other. How many lines of communication are there? A. 12 B. 15 C. 18 D. 14

0 Answers  


You are the project manager for Fun Days vacation packages. Your new project assignment is to head up the Fun Days resort opening in Austin, Texas. You are estimating the duration of the project plan activities, devising the project schedule, and monitoring and controlling deviations from the schedule. Which of the Project Management Knowledge Areas are you working in? A. Project Scope B. Project Quality C. Project Integration D. Project Time

0 Answers  


You are the project manager for Lucky Stars nightclubs. They specialize in live country and western band performances. Your newest project is in the Planning process. You've published the scope statement and scope management plan. The document that describes who will receive copies of this information as well as future project information, how it should be distributed, and how the information should be stored and filed is which of the following? A. Scope management plan B. Communications management plan C. Information distribution plan D. Project charter

0 Answers  


Categories