Suppose a tester reports the bug to the developer and
developer rejects it saying that the bug which is reported by
tester is not a bug.In such a case what should a tester
do?...Kindly answer this question ..
Answers were Sorted based on User's Feedback
Answer / amol
First, discuss with developer why s/he is not saying this
as defect.
Still, if you are feeling this as defect then
1) Provide the screenshots of defect
2) Provide the requirment from SRS
after providing this if still developer is not accepting
this as defect then discuss with Development and testing
lead
Is This Answer Correct ? | 29 Yes | 0 No |
Answer / mohit
If really it is a valid defet then provide the reference of
the requirement which failed in to the defect from SRS to
developer.
Is This Answer Correct ? | 9 Yes | 1 No |
Answer / preeti mishra
1) Provide the detail of functional requirement
2) Provide the detail of Business requirement
3) Provide the screen shots on which basis you've logged the
defect.
Still If developer is not agree then get the confirmation
from QA Lead (From customer side) and update the business
response in the defect.
Is This Answer Correct ? | 5 Yes | 0 No |
Answer / rashmi sumit
Before reporting any issues to the dev team,you need to
verify for the issue in two different m/c coz there cud be
a possibility of difference in environment or missing data
base changes.
Once this is confirmed as an issue,report it to the dev
team.If he do not agree with it then-
1.Give him the detailed steps to re-produce the bug.
2.Sit with the dev team n reproduce the bug ur self.
3.Give him the environment details in which the bug was
found.
4.Send him the screen shot of the issue.
5.Re-direct him to the FS which talks abt this particular
requirement.
Is This Answer Correct ? | 4 Yes | 0 No |
Answer / chaitanya1987
if the tester rejectd the bug,we should not compromise.we
again recheck that bug.then also if we feel that the bug is
really a defect then we will REOPEN the bug and will send it
to developer again.
if suppose he is not willing to accept that
one as a defect then we will show him the required path
(CTM)which describes how we generate that defect and make
him to realize that the defect is a valid one.
Is This Answer Correct ? | 2 Yes | 1 No |
Answer / manik
First,the test eng ask the developer why s/he is not saying
this
as defect.
Still, if you are feeling this as defect then
1) Provide the screenshots of defect
2) Provide the requirment from SRS
after providing this if still developer is not accepting
this as defect then TE talk with TM,PM about bug they are
also responding TE raises this bug as "issue"
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / ram
In that situation , we report to the Test team lead, team lead will inform to the developing team lead,developing team will intimate to the developer and all the four members will sit in a room and discuss abt that issue
Is This Answer Correct ? | 1 Yes | 0 No |
Answer / nakul gupta
in that case tetser can talk regarding this to the team lead
because this is the case of reject request
Is This Answer Correct ? | 1 Yes | 3 No |
what is defect density ? we say it is No of defects / line of code.. what is line of code ? pls if possible give some real example
What is the input for System testing?
What are the cases when you’ll consider to choose automated testing over manual testing?
What is Environment Requirement?
what is version 1
What is Internalisation testing?
1>what is defect matrix? 2>which is the high priority bug in "Open Window"(when we open some file the window get appear)
What factors do you consider while estimation test efforts?
1 )if you have 1000 test cases ,you find out one defect in second build that time which testing you are using Regression Testing or Retesting ? explain with detail as well as you want to execute all the test cases?
what is Scalability,Critical Analysis
I have a build in which there are 17 files, now 3 new files added, in this case what type of testing will do
As the software development process progresses, proper setup and maintenance of test traceability requires that the test process starts when?