in compatability and installation testings ,which one is conducted or performed on an application initially
1 3705You have been hired as a contract project manger for Grapevine Vineyards. Grapevine wants you to design an Internet wine club for their customers. One of the activities for this project is the installation and testing of several new servers. You know from past experience it takes about 16 hours per server to accomplish this task. Since you're installing 10 new servers, you estimate this activity to take 160 hours. Which of the estimating techniques have you used? A. Analogous estimating B. Bottom-up estimating C. Quantitatively based duration D. Reserve time