Golgappa.net | Golgappa.org | BagIndia.net | BodyIndia.Com | CabIndia.net | CarsBikes.net | CarsBikes.org | CashIndia.net | ConsumerIndia.net | CookingIndia.net | DataIndia.net | DealIndia.net | EmailIndia.net | FirstTablet.com | FirstTourist.com | ForsaleIndia.net | IndiaBody.Com | IndiaCab.net | IndiaCash.net | IndiaModel.net | KidForum.net | OfficeIndia.net | PaysIndia.com | RestaurantIndia.net | RestaurantsIndia.net | SaleForum.net | SellForum.net | SoldIndia.com | StarIndia.net | TomatoCab.com | TomatoCabs.com | TownIndia.com
Interested to Buy Any Domain ? << Click Here >> for more details...


If you are a team leader and u have to complete your
testing job of 5 days into 2 days, how would u handle this
situation with team members?

Answers were Sorted based on User's Feedback



If you are a team leader and u have to complete your testing job of 5 days into 2 days, how would ..

Answer / rajendra

To complete Testing job of 5 days into 2 days:

Lead choose different ways:

1.Working more hours
2.Using Highly skilled testers in corresponding project
domain.
3.Prioritizing the test cases,and executing the only
highlevel testcases.

or other than the above three ways lead may take approriate
decission.

byee

Rajendra Prtasad Reddy .P
raendra_penumalli@yahoo.com

Is This Answer Correct ?    1 Yes 0 No

If you are a team leader and u have to complete your testing job of 5 days into 2 days, how would ..

Answer / sharadarsule

good answer..!!Thnx.
i've given the same, but i don't think they(interviewer)
are satisfied with my answer.

Is This Answer Correct ?    0 Yes 0 No

If you are a team leader and u have to complete your testing job of 5 days into 2 days, how would ..

Answer / ritika

i have got the same kind of experience.then i made a
planout where i distributed the work to my team and was
keeping a full vigil on them, we have completed the task in
one weeks time.at the same time i was also looking into
functionality and bugs related issues.

Is This Answer Correct ?    0 Yes 0 No

If you are a team leader and u have to complete your testing job of 5 days into 2 days, how would ..

Answer / sharadarsule

Ok

Is This Answer Correct ?    0 Yes 0 No

If you are a team leader and u have to complete your testing job of 5 days into 2 days, how would ..

Answer / gajendra rawat

Just simple Make time table for 2 day's according to bug
problum distribute work to team
and select only those tester who can work fast because
finely work will don by tester

Is This Answer Correct ?    0 Yes 0 No

If you are a team leader and u have to complete your testing job of 5 days into 2 days, how would ..

Answer / jagdish hinduja

Well I think, that the lead should see what the client
wants in the release. Then accordingly the prioritization
should be done of modules and work should be delegated
amongst the team. This will help the team to atleast test
the most important modules that are required by the client.

Similarly, if it is a maintenance project and this
situation arises, then I think the bugs which are on
highest priority should be given first preference.

Is This Answer Correct ?    0 Yes 0 No

If you are a team leader and u have to complete your testing job of 5 days into 2 days, how would ..

Answer / raz

As a responsible team lead, the person should think of the
below points before going to start testing:

1.Gather the testcases and find the highly prioritized test
cases to be finish.
2.With the design and Fun specs, risk mitigation documents
and find out the risk areas where we have much scope to get
errors.
3.Check the similar scenarios, where we got errors
previously and test them thorougly...not to get those
errors again
4.If we are working for a maintenance project then, we must
not fail to test regression test cases.
5.Must and should follow this step....
-->Choose such a test case, where testing one TC can cover
two or more test finctionalities.
-->lead should have healthy and effective communication
with the team so that, no one should test repetitive
testing...one is testing a scenario which is already tested
by other tester.

Is This Answer Correct ?    0 Yes 0 No

If you are a team leader and u have to complete your testing job of 5 days into 2 days, how would ..

Answer / chandra

if teamleader ask like that. first we have to arrange the
test cases in priority wise (ie. in terms of release ).and
remaining test cases next.and he want complete whole means
we have to spend more time ask for time ,man power.

Is This Answer Correct ?    0 Yes 1 No

Post New Answer

More Manual Testing Interview Questions

Difference Between Usability and GUI Testing with Example?

2 Answers   ICICI, Wells Fargo,


Tell me about CMM LEVEL -4 …what are steps that to be followed to achieve the CMM -IV standards?

1 Answers   AZTEC, Virtusa,


what are the testing strategies to be followed in testing banking applications?

0 Answers  


I heard that 2 0r 3 tier applications can be tested using Browser in the <<Intranet>> Is it correct. pls correct me

1 Answers  


Can anyone Give me examples for high priority and Low priority defects?

3 Answers   Wipro,


write a test cases for facebook

2 Answers  


When the Developer fixes and releases a defect.. then the tester tests it and fails the defect. Suppose the developer again fixes it and the tester again fails it and this process continues for the same defect for more times then what is that u do for getting the defect closed?

1 Answers  


what is difference between metric and report ?

6 Answers   Covansys, Polaris,


how mapp the defect id in quality center?

0 Answers  


How will you link the Defect to the test case? Explain Bug life cycle

2 Answers   IBM,


Suppose if you have given Login screen to Test. What type of tests r u going to do on that.How many test cases can u write.?

10 Answers   Infeneon Technologies,


what is test initiation? can anybody post the answer. very urgent?

6 Answers   Accenture, Maveric,


Categories