What are the different kinds of project management tools you worked with?
No Answer is Posted For this Question
Be the First to Post Answer
You are a project manager for Candy Works candy factory. Your project involves reporting information from the newly installed candy-counting machine to the financial system. This will give executives the ability to see production run counts at any rime during the day. The project sponsor has promised you a bonus if you get this project completed two weeks sooner than the scheduled project end date. The bonus will come in handy on your trip to the Bahamas planned for later this spring. You've got a few remaining project activities to wrap up before you can close out the project. Which of the following is the most appropriate response? A. You tell the sponsor the project is complete and treat the remaining activities as though they're problems that came up after project closure so that you can still get the bonus. B. You tell the sponsor the remaining activities are outside the scope of the project so the project really is completed and collect your bonus. C. You tell the sponsor the stakeholders added these requirements after the project was well under way and you never agreed to include them in the project so the project really is complete, and you collect your bonus. D. You tell the sponsor you aren't going to make the two-week early completion date as there are remaining activities to finish up.
Describe function-oriented metrics.
Your procurement department has obtained independent estimates. The vendor's proposal is substantially different than the independent estimates. All of the following are true except: A. The SOW was not detailed enough. B. The vendor failed to respond according to the terms of the proposal. C. The vendor failed to respond to all items in the SOW. D. The vendor failed to respond to all items in the contract.
What is triple constraint triangle in project management?
You are working on a project that is similar in scope to a project performed last year by your company. You might consider which of the following? A. Using the previous project's alternatives identification as a template B. Reusing the previous project's benefit/cost analysis as justification for this project C. Using the previous project's WBS as a template D. Reusing the previous project's product description when writing the scope statement
How do you set goals for your team?
All of the following are true regarding the Executing processes except: A. Executing has one core process. B. The majority of the project budget is spent here. C. The greatest conflicts are schedule conflicts. D. Project performance is measured to identify variances.
You need to convey some very complex, detailed information to the project stakeholders. The best method of communicating this kind of information is? A. Verbal B. Vertical C. Horizontal D. Written
How do you motivate team members?
What is one of the most important skills a project manager can have? A. Negotiation skills B. Influencing skills C. Communication skills D. Problem-solving skills
You are the project manager working on a research project for a new drug treatment. Your preliminary project schedule runs past the due date for a federal grant application. You adjust the schedule and find that two activities previously scheduled to start sequentially can be started at the same time. This is an example of: A. Crashing B. Fast tracking C. Resource leveling D. Adjusting the resource calendar
You are the project manager for Design Your Web Site, Inc. Your company is designing the website for a national grocery store chain. You have your activity list in hand and several time estimates and are ready to diagram the activity dependencies. You should use which of the following? A. PDM techniques B. PDM or ADM techniques C. AON techniques D. ADM techniques